| Title | Failure to Identify and Perform Testing for the Gaseous Radwaste System |
| Description | The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, for the failure of the licensee to assure that all required testing for the gaseous radwaste (GR) system was identified and performed in accordance with written test procedures which incorporated the requirements and acceptance limits contained in applicable design documentation. Specifically, from May 1995 to October 26, 2011, the licensee did not identify nor perform functional testing on GR system equipment which is credited in the Updated Final Safety Analysis Report (UFSAR) to preclude the internal hydrogen explosion event. The licensee developed written test procedures and successfully completed appropriate functional tests on all three units as a corrective action to restore compliance. The licensee documented their corrective actions for this issue in Palo Verde Action Requests 3440072, 3931118, and 4004489. The licensees failure to perform functional testing on GR system equipment was a performance deficiency. The performance deficiency is more than minor, and therefore a finding, because it is associated with the Initiating Events Cornerstone attribute of procedure quality in the area of testing procedure adequacy and it adversely affected the cornerstone objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations. Specifically, the lack of having functional testing on GR system components could result in a credible hydrogen explosion event which could initiate a radiological release. Using Inspection Manual Chapter 0609, Appendix F, Fire Protection Significance Determination Process, the finding was determined to have very low safety significance (Green) because the condition represented a low degradation rating due to the fact that nitrogen dilution valves and compressor auto trip features all passed recent functional testing successfully. This finding has no cross-cutting aspect assigned because the finding is not reflective of current performance |
| Site: | Palo Verde |
|---|---|
| Report | IR 05000528/2011005 Section 4OA2 |
| Date counted | Dec 31, 2011 (2011Q4) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71152 |
| Inspectors (proximate) | L Ricketson G Guerra R Lantz M Brown B Baca D Allen J Melfi B Parks A Fairbanks E Uribe M Baquera D Reinert S Hedger |
| INPO aspect | |
| ' | |
Finding - Palo Verde - IR 05000528/2011005 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Palo Verde) @ 2011Q4