Title | Failure To Include Screening Criteria In The Boric Acid Corrosion Control Program |
Description | The inspectors identified a Green noncited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, which states, in part, that Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished. Specifically, Procedure 70TI-9ZC01, Boric Acid Walkdown Leak Detection, Revision 11 did not include appropriate screening criteria to satisfactorily evaluate boric acid leaks and deposits that may cause degradation of risk significant system barriers. The condition was placed in the corrective action program as Palo Verde Action Request 3691351. The inspectors determined the failure to include appropriate screening criteria into Procedure 70TI-9ZC01 was a performance deficiency. The performance deficiency is more than minor because it is associated with the procedure quality attribute of the Barrier Integrity Cornerstone and adversely affects the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Using Phase 1 of NRC Manual Chapter 0609, Significance Determination Process, the finding screens as having very low safety significance (Green) because the finding does not represent a degradation of a radiological barrier, does not represent a degradation of the control room toxic barrier functions, does not represent an actual open pathway of reactor containment, and does not involve an actual degradation of hydrogen igniters in the reactor containment. The finding includes a cross-cutting aspect in the area of problem identification and resolution, associated with the corrective action program component, because the licensee failed to take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. Specifically, the licensee identified similar deficiencies in the self assessment of the boric acid program in September 2010 however, failed to take appropriate corrective actions to fully correct the identified deficiencies. |
Site: | Palo Verde |
---|---|
Report | IR 05000528/2011003 Section 1R08 |
Date counted | Jun 30, 2011 (2011Q2) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.08 |
Inspectors (proximate) | G Guerra R Lantz M Brown P Elkmann G George J Adams J Bashore M Baquera S Hedger |
CCA | P.3, Resolution |
INPO aspect | PI.3 |
' | |