05000400/FIN-2010005-04
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate Post Maintenance Test Procedure Results in Deenergization of the B Safety Bus and Loss of Decay Heat Removal |
Description | A self-revealing Green NCV of TS 6.8.1, Procedures, was identified for the licensees failure to develop an adequate procedure for the post maintenance test of the recently replaced main generator lockout relay (MGLR). Specifically, the licensee failed to ensure that the post maintenance testing (PMT) was within the clearance boundary that was established for the MGLR replacement. This resulted in the inadvertent deenergization of the B Safety Bus and the B Residual Heat Removal (RHR) pump, which was the only pump providing decay heat removal (DHR). As corrective action, the licensee entered AOP-25, Loss of One Emergency AC Bus, and restored DHR with the B RHR pump after approximately three minutes. The resultant increase in Reactor Coolant System temperature was approximately one degree. Additionally, the licensee plans to revise PLP-400, Post Maintenance Testing, to provide the work planner with additional guidance in the development of PMT for protective relays. The licensee entered this issue into their CAP as AR #431732. The licensees failure to develop an adequate procedure for the post maintenance test of the recently replaced MGLR was a performance deficiency. The performance deficiency was more than minor because it is associated with the procedure quality attribute of the Mitigating Systems cornerstone, and it affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, it resulted in the inadvertent deenergization of the B Safety Bus and loss of DHR. Using IMC 0609, Significance Determination Process, Phase 1 screening worksheet of the SDP, the inspectors determined that the use of Appendix G, Shutdown Operations Significance Determination Process, was necessary. Using Checklist 3 of Attachment 1 of Appendix G, the inspectors determined that this issue affected both the DHR equipment guidelines and the emergency electrical bus guidelines and therefore required a Phase 2 analysis. Using Worksheet 8 of Attachment 2 of Appendix G, the inspectors determined that recovery credit was appropriate because 1) sufficient time was available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training was conducted on the existing procedures under conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use. Using a time to boil of greater than one hour and the fact that the steam generators were not available for cooling, the result of the Phase 2 was that a Phase 3 was necessary. A regional Senior Reactor Analyst evaluated the performance deficiency under the Phase 3 protocol of the Significance Determination Process. Based upon the results of that evaluation, the performance deficiency was characterized as of very low safety significance (Green). The finding has a cross-cutting aspect of Work Coordination, as described in the Work Control component of the Human Performance cross-cutting area because the licensee did not understand the potential operational impact of the work activities or adequately account for current plant conditions (H.3(b)). |
Site: | Harris |
---|---|
Report | IR 05000400/2010005 Section 1R19 |
Date counted | Dec 31, 2010 (2010Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.19 |
Inspectors (proximate) | R Kellner A Nielsen J Rivera-Ortiz R Hamilton W Loo J Austin M Bates S Walker R Musser D Mas-Penaranda M Coursey P Lessard J Eargle N Childs |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |
Finding - Harris - IR 05000400/2010005 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Harris) @ 2010Q4
Self-Identified List (Harris)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||