05000361/FIN-2010007-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Ensure At Least One Train of Equipment Necessary to Achieve Hot Shutdown Conditions Is Free of Fire Damage |
Description | The team identified a cited violation of License Condition 2.C(14), Fire Protection, for failure to correct a noncompliance. Specifically, Inspection Report 05000361;362/2007008 documented a noncompliance involving the failure to ensure that at least one train of safe shutdown equipment would remain free from fire damage in each fire area. The NRC exercised discretion not to cite this violation at that time because the licensee met the criteria described in Enforcement Guidance Memorandum 98-002, Revision 2, and Supplement 2 to that revision. Enforcement Guidance Memorandum 07-004 superseded Enforcement Guidance Memorandum 98-002 and required licensees to complete corrective actions for noncompliances related to post-fire operator manual actions by March 6, 2009. This violation is being cited due to the failure to complete corrective actions and restore compliance within the required time. This finding was entered into the licensees corrective action program as Notification NN 200940265. The failure to promptly restore adequate fire protection and/or separation of required safe shutdown systems was a performance deficiency. This performance deficiency was more than minor because it was associated with the protection against external factors (fire) attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events in order to prevent undesirable consequences. Because the violation involved multiple fire areas, the team could not evaluate this issue using Phase 2 of Inspection Manual Chapter 0609, Appendix F, and a Phase 3 significance determination process risk assessment was performed by a senior reactor analyst. The finding was determined to have very low risk significance (Green), with a delta-CDF of 3.2E-8/yr, because of a combination of the availability of long recovery times for feasible operator manual actions and low-probability fire damage scenarios in the nine fire areas with fire sources which could potentially damage cables of required safe shutdown components. This finding involved a cross-cutting aspect in the decision-making component in the human performance area because the licensee failed to make a risksignificant decision using a systematic process when considering the scheduling of corrective actions H.1(a) (Section 1R05.01)(EA 10-191). |
Site: | San Onofre |
---|---|
Report | IR 05000361/2010007 Section 1R05 |
Date counted | Sep 30, 2010 (2010Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.05 |
Inspectors (proximate) | G Miller S Gravese Uribei Anchando J Mateychick N O'Keefe N Okonkwo S Alferink S Marquez |
CCA | H.13, Consistent Process |
INPO aspect | DM.1 |
' | |
Finding - San Onofre - IR 05000361/2010007 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (San Onofre) @ 2010Q3