Title | Failure to Implement Risk Management Actions During Elevated Risk |
Description | An NRC-identified Green NCV of 10 CFR 50.65(a)(4) was identified for the failure of the licensee to manage the increase in risk that resulted from the E6 bus outage. Specifically, between May 19, 2013 and May 21, 2013, the licensee did not manage the increase in risk on Unit 2 during the E6 bus outage by use of appropriate risk management actions (RMAs). Operations personnel took immediate actions to protect the equipment in the control room and in the field. The licensee entered this issue into the CAP as NCR 607741. The inspectors determined that the failure of the licensee to manage risk during the E6 outage by performing RMAs for the protected 2A RHR and RHRSW loops, the 2A and 2B core spray and the hardened vent was a performance deficiency. The finding was more than minor because if left uncorrected, the failure to perform RMAs when required could result in safety-related mitigating equipment being unavailable during already elevated plant risk, specifically the 2A RHR and RHRSW loops, the 2A and 2B core spray and the hardened vent. This finding was associated with the human performance attribute of the Mitigating Systems Cornerstone. Using IMC 0609, Appendix K, issued May19, 2005, Maintenance Risk Assessment and Risk Management Significance Determination Process, Flowchart 2, Assessment of RMAs, the inspectors determined the finding screened as very low safety significance (Green) since the incremental core damage probability was less than 1E-6. The finding has a cross-cutting aspect in the area of human performance associated with the work control attribute because the licensee did not appropriately plan work activities by incorporating risk insights during the E6 bus outage. |
Site: | Brunswick ![]() |
---|---|
Report | IR 05000324/2013003 Section 1R13 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.13 |
Inspectors (proximate) | M Catts M Schwieg R Taylor G Hopper J Dodson |
Violation of: | 10 CFR 50.65(a)(4) 10 CFR 50.65 |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |
Finding - Brunswick - IR 05000324/2013003 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|