| Q | CCA | Title |
---|
05000298/FIN-2010004-02 | 2010Q3 | P.2 | Failure to Follow Procedure Results in Repeat Equipment Failure |
05000298/FIN-2010004-01 | 2010Q3 | H.14 | Failure to Adequately Monitor the Performance of the Screen Wash System |
05000298/FIN-2010005-03 | 2010Q4 | P.5 | Failure to Adequately Assess and Manage Risk During Maintenance Activities |
05000298/FIN-2010006-01 | 2010Q4 | P.1 | Inadequate Post-Fire Safe Shutdown Procedures |
05000298/FIN-2010006-02 | 2010Q4 | H.14 | Failure to Monitor the Performance of the Emergency Lights Against the Maintenance Rule Criteria |
05000298/FIN-2010005-01 | 2010Q4 | H.14 | Failure to Implement Fire Protection Plan Requirements Related to Hot Work Activities |
05000298/FIN-2010005-02 | 2010Q4 | H.14 | Failure to Assess and Manage Risk for Electrical Switchyard Impacting Maintenance |
05000298/FIN-2010005-05 | 2010Q4 | | Diesel Generator Overspeed Governor Loose Bolting Issue |
05000298/FIN-2010005-06 | 2010Q4 | | Failure to Update Flood Protection for Safety Related Buildings |
05000298/FIN-2010005-04 | 2010Q4 | P.3 | Failure to Have Guidelines for the Choice of Protective Actions During an Emergency Consistent with Federal Guidance |
05000298/FIN-2010007-04 | 2010Q4 | P.5 | Inadequate Design Control |
05000298/FIN-2010007-06 | 2010Q4 | S.2 | Faulty General Electric Switches |
05000298/FIN-2010007-01 | 2010Q4 | H.7 | Failure to Translate Design and Operating Requirements into Procedures |
05000298/FIN-2010007-02 | 2010Q4 | H.14 | Failure to promptly Correct Conditions Adverse to Quality |
05000298/FIN-2010007-03 | 2010Q4 | H.7 | Inadequate Test Control |
05000298/FIN-2010007-05 | 2010Q4 | H.14 | Ice Deflector Pontoon Barge Storage in Service Water Discharge Canal |
05000298/FIN-2010007-07 | 2010Q4 | | URI 05000298/2007011-07, Fuel Oil Storage Tank Required Submergence To Prevent Vortexing And Available Volume Are Marginal Without Accounting For Instrument Uncertainties |
05000298/FIN-2010007-08 | 2010Q4 | | URI 05000298/2007011-08, High Pressure Coolant Pump Swap-Over from Emergency Condensate Storage Tank to Torus Vortex Calculation |
05000298/FIN-2011009-01 | 2011Q1 | P.2 | Inadequate Post-Fire Safe Shutdown Procedures |
05000298/FIN-2011002-02 | 2011Q1 | P.3 | Failure to Assess and Manage Risk for Maintenance That Could Impact Initiating Events |
05000298/FIN-2011002-04 | 2011Q1 | P.3 | Repeat Failure to Follow Procedure for Initiating Condition Reports |
05000298/FIN-2011002-03 | 2011Q1 | H.8 | Failure to Adequately Implement Foreign Material Exclusion Controls |
05000298/FIN-2011002-01 | 2011Q1 | H.14 | Failure to Properly Evaluate All Senior Operator License Holders during Annual Operating Test |
05000298/FIN-2011002-05 | 2011Q1 | H.14 | Failure to Notify the NRC within Eight Hours of a Nonemergency Event |
05000298/FIN-2011003-08 | 2011Q2 | H.12 | Failure to Follow Procedure Results in Degraded Emergency Diesel Generator |
05000298/FIN-2011006-05 | 2011Q2 | H.14 | Failure to Correctly Translate Design Requirements into Installed Plant Configuration |
05000298/FIN-2011003-01 | 2011Q2 | H.14 | Failure to Assess Potential Adverse Effects on Internal Flooding Analysis |
05000298/FIN-2011008-01 | 2011Q2 | H.8 | Unclear Work Instructions |
05000298/FIN-2011008-02 | 2011Q2 | H.5 | Failure to Recognize Work Order Risk |
05000298/FIN-2011008-03 | 2011Q2 | H.12 | Failure to Implement Human Performance Procedure |
05000298/FIN-2011008-04 | 2011Q2 | H.14 | Failure to Revise Unclear Work Instructions |
05000298/FIN-2011008-05 | 2011Q2 | H.5 | Failure to Perform an Adequate High Radiation Area Briefing |
05000298/FIN-2011008-06 | 2011Q2 | H.12 | Failure to Follow Radiation Protection Job Coverage Procedures |
05000298/FIN-2011003-04 | 2011Q2 | | Communication of an NRC Inspectors Presence by Station Personnel |
05000298/FIN-2011006-02 | 2011Q2 | P.2 | Failure to Report Conditions Prohibited by Technical Specifications and Safety System Functional Failures |
05000298/FIN-2011006-03 | 2011Q2 | P.2 | Failure to Perform 10 CFR 50.59 Evaluation for Design Change |
05000298/FIN-2011006-04 | 2011Q2 | P.2 | Failure to Take Action for an Ineffective Corrective Action |
05000298/FIN-2011003-02 | 2011Q2 | P.2 | Failure to Follow Procedure Results in Inadequate Operability Determinations |
05000298/FIN-2011003-03 | 2011Q2 | H.4 H.5 | Failure to Follow Procedure Results in Personnel Contaminations |
05000298/FIN-2011003-05 | 2011Q2 | H.11 H.12 | Failure to Follow Radiation Work Permit Requirements |
05000298/FIN-2011003-06 | 2011Q2 | | Failure to Correctly Translate Design Requirements into Installed Plant Configuration |
05000298/FIN-2011003-07 | 2011Q2 | | Failure to Adequately Assess and Manage Risk When Disabling A Hazard Barrier |
05000298/FIN-2011003-09 | 2011Q2 | H.6 | Failure to Initiate Condition Reports for Nonconformances Identified During System Walk Downs |
05000298/FIN-2011003-10 | 2011Q2 | P.1 | Failure to Promptly Correct an Adverse Condition Related to Emergency Core Cooling System Venting |
05000298/FIN-2011006-01 | 2011Q2 | P.1 | Failure to Promptly Identify and Correct Conditions Adverse to Quality |