Finding | |
---|---|
Title | Evaluation of Change to Alternate Shutdown Cooling Flowpath |
Description | The team identified an unresolved item related to engineering change modifications that changed a procedure to include the replacement of automatic actions with manual actions. Specifically, the10 CFR 50.59 evaluation proposed a change to substitute automatic flow control of shutdown cooling flow and temperature with manual control using the low pressure safety injection loop injection valves alternate shutdown cooling flow control. During a review of Engineering Change Modification 54058, Procedure Change to Allow Closing of HCV-335 while on Alternate Shutdown Cooling, the team identified that the licensee changed a procedure to include the replacement of an automatic action with a manual action. Specifically, the engineering change proposed to close both shutdown cooling heat exchanger isolation valve HCV-335 and flow control valve FCV-326 while pinning open valve HCV-341 and manually throttling low pressure safety injection loop injection valves to maintain the desired RCS temperature and flow rate. The team questioned whether the licensee required prior NRC review and approval to make this change since flow control valve FCV-326 normally controls temperature and flow automatically as described in Section 9.3.4.3 of the USAR. The licensee entered this issue of concern into the CAP. Additional NRC review and follow up will be required to determine if this issue represents a performance deficiency associated with meeting the 10 CFR 50.59 requirement of more than a minimal increase in the likelihood of occurrence of a malfunction of a system, structure, or component important to safety previously evaluated in the USAR. This item is unresolved pending review of the licensees evaluation. This issue is identified as URI 05000285/2013008- 30, Evaluation of Change to Alternate Shutdown Cooling Flowpath. |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2013008 Section 1R17 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | URI: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.17 |
Inspectors (proximate) | B Cummings C Roque-Cruz G George I Anchondo J Josey J Melfi P Elkmann R Hagar S Alferink S Janicki S Schneidera Klettc Smith M Davis J Josey C Bickett G Warnick M Hay J Brand J Groom M Keefe R Latta W Schaup J Watkins B Hagar A Allen J Wingebach K Martin L Wilkins S Morrow R Deese F Ramirez |
INPO aspect | |
' | |
Finding - Fort Calhoun - IR 05000285/2013008 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2013Q2