Similar Documents at Salem |
|---|
|
LER-2004-001, Regarding as Found Value for Main Steam Safety Value Lift Setpoint Exceeds Technical Specification Allowable Limit |
| Event date: |
|
|---|
| Report date: |
|
|---|
| Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|---|
| 2722004001R00 - NRC Website |
|
text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 O PSEG ATu clear LLC JUN 0 3 2004 LR - N04 - 0235 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
LER 272/04-001-00 SALEM - UNIT 1 FACILITY OPERATING LICENSE NO. DPR-70 DOCKET NO. 50-272 This Licensee Event Report, "As Found Value for Main Steam Safety Valve Lift Setpoint Exceeds Technical Specification Allowable Limit" is being submitted pursuant to the requirements of the Code of Federal Regulations 10 CFR 50.73(a)(2)(i)(B), Operation or Condition Prohibited by technical Specifications.
The attached LER contains no commitments.
Sincere an ager-Salem Attachment
/EHV C
Distribution LER File 3.7 95-2168 REV. 7/99
Abstract
During the Salem Unit 1 sixteenth refueling outage (1 R16), ten of the Main Steam Safety Valves were initially lift setpoint tested in accordance with the Inservice Test (IST) Program. On April 9, 2004, PSEG discovered that one of the Main Steam Safety Valves tested failed its as-found lift setpoint test. The as-found actuation pressure for Main Steam Safety Valve 1 3MS1 3 was below the lower limit of minus 3% of the nameplate setpoint as stated in the Salem Technical Specification (TS) Table 3.7-1. The TS value is 1110 psig +/- 3%.
The apparent cause of this event has been attributed to excessive seat leakage, which caused the valve to lift at a low set pressure. A contributing cause to the event is suspected to be steam cutting of the seating surfaces. Because the actual lift set point of the 13MS13 was not within the required acceptance criterion of
+1-3%, two additional Main Steam Safety Valves were tested. The two additional Main Steam Safety Valves (11 MS1 3 and 11 MS1 4) tested satisfactory and no further testing was required. The failed valve was replaced with a pre-tested and certified spare.
This event is reportable per the requirements of 10 CFR 50.73(a)(2)(i)(B), Operation or Condition Prohibited by technical Specifications.
NFIC FORM 366 (7-2001)
(If more space Is required, use additional copies of (If more space is required, use additional copies of (If more space is required, use addiionalcopies of NRC Form 366A) (17)
SAFETY CONSEQUENCES AND IMPLICATIONS
There was no safety significance to this event.
There are twenty MSSVs installed in Salem Unit 1. These valves are equally distributed in four Main Steam Headers each containing five MSSVs with setpoints varying from a low of 1070 psig to a high of 1125 psig and a tolerance of +/- 3%. The MSSVs provide over pressurization protection for the Steam Generators on the secondary side and the Main Steam System.
During 1 R1 6 a total of twelve MSSVs were tested, including two additional MSSVs as a result of the failure of 13MS13. Eleven valves lifted within the set point tolerances and one valve lifted earlier by a few tenths of one pound. A Main Steam Safety Valve lifting earlier (greater than - 3%) is an operational transient that would result in depressurizing the main steam lines. However, the potential consequences of the inadvertent depressurization caused by the lifting of a safety valve are bounded by the main steam line break analyses.
In this case, the small difference between the allowable setpoint and the as found lift setpoint, just a few tenths of one pound, would have had minimal to no impact on plant safety. The ability of the Main Steam Safety Valve to provide over pressurization protection for the Steam Generators on the secondary side was never compromised.
This event does not constitutes a Safety System Functional Failure (SSFF) as defined in Nuclear Energy Institute (NEI) 99-02, Regulatory Assessment Performance Indicator Guideline.
CORRECTIVE ACTIONS
- 1. The failed MSSV was replaced with a pre-tested and certified spare.
- 2. Expanded scope of MSSV testing to include an additional two MSSVs from another header in accordance with the IST Program. The two additional MSSVs tested satisfactorily.
- 3. The failed MSSV valve was removed and is currently at the offsite test facility and will be disassembled and repaired.
COMMITMENTS
The corrective actions cited in this LER are voluntary enhancements and do not constitute commitments.
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000272/LER-2004-001, Regarding as Found Value for Main Steam Safety Value Lift Setpoint Exceeds Technical Specification Allowable Limit | Regarding as Found Value for Main Steam Safety Value Lift Setpoint Exceeds Technical Specification Allowable Limit | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000311/LER-2004-001, Failure to Take Proper Compensatory Containment Air Samples | Failure to Take Proper Compensatory Containment Air Samples | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) | | 05000272/LER-2004-002, Regarding Non Conservative Technical Specifications - Containment Fan Coil Units | Regarding Non Conservative Technical Specifications - Containment Fan Coil Units | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000311/LER-2004-002, Regarding Failure to Comply with Technical Specifications During Reactor Protection Instrument Calibration | Regarding Failure to Comply with Technical Specifications During Reactor Protection Instrument Calibration | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000272/LER-2004-003, Regarding Completion of Plant Shutdown to Comply with Technical Specifications - 3.6.1.1 Containment Integrity | Regarding Completion of Plant Shutdown to Comply with Technical Specifications - 3.6.1.1 Containment Integrity | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000311/LER-2004-003, Regarding Control Room Emergency Air Conditioning System Unable to Mitigate the Consequences of an Accident | Regarding Control Room Emergency Air Conditioning System Unable to Mitigate the Consequences of an Accident | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System | | 05000272/LER-2004-004, Regarding Non-essential Loads Not Isolated with One Chiller Inoperable as Required by Technical Specifications | Regarding Non-essential Loads Not Isolated with One Chiller Inoperable as Required by Technical Specifications | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) | | 05000311/LER-2004-004, Regarding Technical Specification Required Plant Shutdown Following Loss of 2B 230-Volt Vital Bus | Regarding Technical Specification Required Plant Shutdown Following Loss of 2B 230-Volt Vital Bus | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000272/LER-2004-005, ECCS Leakage Outside Containment Exceeds Dose Analysis Limits (11 RHR Heat Exchanger) | ECCS Leakage Outside Containment Exceeds Dose Analysis Limits (11 RHR Heat Exchanger) | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System 10 CFR 50.73(a)(2)(viii)(A) | | 05000311/LER-2004-005, Regarding Auto Safety Injection Signal Not Unblocked Prior to Mode Change from 5 to 4 | Regarding Auto Safety Injection Signal Not Unblocked Prior to Mode Change from 5 to 4 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000311/LER-2004-006, Re Reactor Trip Due to a Malfunction of Main Feedwater Regulating Valve (21 BF1 9) | Re Reactor Trip Due to a Malfunction of Main Feedwater Regulating Valve (21 BF1 9) | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000272/LER-2004-006, Operation in a Condition Prohibited by Technical Specification - Containment Isolation Valves | Operation in a Condition Prohibited by Technical Specification - Containment Isolation Valves | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System 10 CFR 50.73(a)(2) | | 05000272/LER-2004-007, Re Operation in a Condition Prohibited by Technical Specification - Technical Specification 3.3.2.1 | Re Operation in a Condition Prohibited by Technical Specification - Technical Specification 3.3.2.1 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-2004-007, Manual Reactor Trip Due to a Malfunction of a Main Feedwater Regulating Valve (23BF19) | Manual Reactor Trip Due to a Malfunction of a Main Feedwater Regulating Valve (23BF19) | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000311/LER-2004-008, Unplanned Reactor Trip Due to Main Generator Exciter Brush Failure | Unplanned Reactor Trip Due to Main Generator Exciter Brush Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) | | 05000311/LER-2004-009, Re ECCS Leakage Outside Containment Exceeds Dose Analysis Limits (23 Charging Pump) | Re ECCS Leakage Outside Containment Exceeds Dose Analysis Limits (23 Charging Pump) | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) |
|