05000261/FIN-2010402-01 | 2010Q3 | H.2 | Security |
05000261/FIN-2010006-03 | 2010Q3 | | Materially Inaccurate Information Provided to NRC in LER 2009-001 which impacted the Regulatory Process |
05000261/FIN-2010004-02 | 2010Q3 | | Failure to Design and Implement a Simulator Model that Demonstrated Reference Plant Response |
05000261/FIN-2010004-03 | 2010Q3 | | Deficiencies in Non Safety-Related Cable Installation Result in Fire and Reactor Trip |
05000261/FIN-2010004-04 | 2010Q3 | H.7 | Failure to Establish an Adequate PATH-1 Emergency Operating Procedure |
05000261/FIN-2010004-01 | 2010Q3 | H.7 | Failure to Have Adequate Work and Post Maintenance testing Instructions for the Volume Control Tank Comparator Module |
05000261/FIN-2010006-01 | 2010Q3 | P.1 P.1(a) | Failure to Correct a Control Power Fuse Defect in 4kV Breaker 52/24 |
05000261/FIN-2010004-05 | 2010Q3 | H.9 | Failure to Correctly Implement a Systems Approach to Training for the Licensed Operator Requalification Program |
05000261/FIN-2010011-02 | 2010Q4 | P.5 P.2(a) | Failure To Ensure that the Full Range of Emergency Diesel Generator Frequency is Accounted for in the Safety Analyses |
05000261/FIN-2010005-03 | 2010Q4 | | Emergency Diesel Generator Inoperable in Excess of Technical Specifications Completion Time Due to Output Breaker Failure |
05000261/FIN-2010011-07 | 2010Q4 | H.7 | Failure to Implement Adequate Post Maintenance Test of Residual Heat Removal Valve Interlock Function |
05000261/FIN-2010011-06 | 2010Q4 | P.5 P.2(b) | Failure to Translate Vendor Recommendations Into Procedures for 480V Circuit Breakers |
05000261/FIN-2010011-05 | 2010Q4 | H.7 | Inadequate Criteria to Prevent Spurious Actuation of Amptector Trip Devices |
05000261/FIN-2010011-04 | 2010Q4 | | Failure to Correctly Translate EDG Starting Air System Design Requirements into TS |
05000261/FIN-2010011-03 | 2010Q4 | | Failure to Demonstrate the Capability of the Fuel Oil Storage Tank and the Service Water Pumps to Fulfill Their Safety Functions Under All Conditions |
05000261/FIN-2010011-01 | 2010Q4 | | Failure to Establish Proper In-service Testing Acceptance Criteria to Prevent Reverse Rotation of the SDAFW Pump |
05000261/FIN-2010012-02 | 2010Q4 | | C RCP Motor Failure and Seal Damage |
05000261/FIN-2010005-01 | 2010Q4 | | Failure to Perform 5-year Vendor Manual Specified Reactor Coolant Pump Motor Inspections |
05000261/FIN-2010012-03 | 2010Q4 | P.3 | Operator Transient Response Adversely Affected by Uncorrected, Known Plant Deficiency |
05000261/FIN-2010012-01 | 2010Q4 | H.13 | Procedure Violation for Overriding Feedwater Isolation Safety Function in Mode 3 |
05000261/FIN-2011002-04 | 2011Q1 | | Refueling Water Storage Tank Operability While On Purification |
05000261/FIN-2011405-02 | 2011Q1 | | Security |
05000261/FIN-2011405-01 | 2011Q1 | H.2 | Security |
05000261/FIN-2011002-01 | 2011Q1 | H.9 | Two of Six Operating Crew Failures on the Simulator Operational Evaluation Portion of the 2011 Annual Requalification Operating Test |
05000261/FIN-2011002-03 | 2011Q1 | H.14 | Inadequate 10 CFR 50.59 evaluation results in Emergency Core Cooling System Inoperability |
05000261/FIN-2011002-02 | 2011Q1 | | Failure to Update the Updated Final Safety Analysis Report Contributed to Insufficient Emergency Diesel Generator Lube Oil Inventory |