Finding | |
|---|---|
| Title | Failure to Establish an Adequate PATH-1 Emergency Operating Procedure |
| Description | (TBD) The inspectors identified an apparent violation (AV) of Technical Specifications (TS) 5.4.1, Procedures , for the licensees failure to establish and maintain an adequate emergency procedure that ensured reactor coolant pump (RCP) seal cooling was maintained following a reactor trip. The licensee has entered this into the CAP as nuclear condition report (NCR) 423147. Corrective actions for this finding are still being evaluated. The failure to establish and maintain an emergency procedure that would ensure adequate reactor coolant pump seal cooling, preventing seal degradation and a possible seal LOCA was a performance deficiency. The finding is more than minor because it is associated with the Initiating Events Cornerstone and affected the cornerstone objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during shutdown as well as power operations, specifically a loss of seal cooling to prevent the initiation of a RCP seal loss of coolant accident (LOCA). Using Manual Chapter Attachment 0609.04, Phase 1 - Initial Screening and Characterization of Findings, the inspectors determined the finding required a Phase 2 analysis because the finding could result in RCS leakage exceeding Technical Specification limits. The Phase 2 analysis determined that this finding was potentially greater than green; therefore, a Phase 3 analysis is required by a regional senior reactor analyst due to an increase in the likely hood of an RCP seal LOCA. The significance of this finding is designated as To Be Determined (TBD) until the safety characterization has been completed. The cause of this finding had a cross-cutting aspect of Documentation, Procedures, and Component Labeling, in the Resources component of the cross-cutting area of Human Performance, in that the licensee failed to ensure procedures for emergency operations were adequate to assure nuclear safety. |
| Site: | Robinson |
|---|---|
| Report | IR 05000261/2010004 Section 4OA3 |
| Date counted | Sep 30, 2010 (2010Q3) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71153 |
| Inspectors (proximate) | C Kontz G Laska L Wert M Bates W Rogersa Nielsenc Kontz D Bollock D Mills G Laska G Skinner J Beavers J Brady J Hickey J Worosilo M Bates P Braxton R Musser |
| CCA | H.7, Documentation |
| INPO aspect | WP.3 |
| ' | |