05000255/FIN-2015001-07
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Inadequate Procedure Leads to Primary Coolant Pump Seal Degradation |
| Description | A finding of very low safety significance and an associated NCV of Technical Specification (TS) 5.4.1(a) was self-revealed when the C primary coolant pump (PCP) seal degraded as a result of an inadequate maintenance procedure. Specifically, maintenance procedure PCSM54, N9000 Primary Coolant Pump Shaft Seal Assembly, did not identify critical steps in the assembly of the PCP seal and, as a result, the work activity was not adequately controlled. This issue was entered into the licensees Corrective Action Program (CAP) as CRPLP201403495, Planned Outage Required Due to Two Stages of the Primary Coolant Pump P-50C Seal Not Performing as Expected, dated June 21, 2014. The performance deficiency was determined to be more than minor because it was associated with the Equipment Performance attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective of limiting the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the C PCP seal was not correctly assembled or installed during refueling outage (RFO) 1R23, which resulted in premature seal degradation. Based on a detailed risk evaluation performed by a Region III Senior Reactor Analyst (SRA) using SAPHIRE Version 8.20 and the Events and Conditions Assessment Feature of the Palisades Standardized Plant Analysis Risk (SPAR) model (Version 8.1.2), the inspectors determined the finding was of very low safety significance. This finding had a cross-cutting aspect in the Work Management component of the Human Performance cross-cutting area. Specifically, the licensee did not effectively screen the PCP seal assembly through the work management process to identify that it should have been classified as a critical maintenance activity. In addition, insufficient emphasis was placed on in-field vendor oversight during work execution. |
| Site: | Palisades |
|---|---|
| Report | IR 05000255/2015001 Section 4OA2 |
| Date counted | Mar 31, 2015 (2015Q1) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | Self-revealing |
| Inspection Procedure: | IP 71152 |
| Inspectors (proximate) | J Cassidy J Lennartz M Phalen R Elliott R Walton A Garmoe A Scarbeary E Duncan |
| Violation of: | Technical Specification - Procedures Technical Specification |
| CCA | H.5, Work Management |
| INPO aspect | WP.1 |
| ' | |