EPID:L-2019-LRM-0079, SECY-18-0100: Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission'S Digital Instrumentation and Control Regulatory Infrastructure (Open) |
|
MONTHYEARML18275A3272018-10-0909 October 2018 SECY-18-0100: Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission'S Digital Instrumentation and Control Regulatory Infrastructure Project stage: Request W3F1-2019-0034, Letter-of-Intent to Submit License Amendment Requesting Using Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, Revision 2 and Request for NRC Fee Waiver2019-05-16016 May 2019 Letter-of-Intent to Submit License Amendment Requesting Using Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, Revision 2 and Request for NRC Fee Waiver Project stage: Request W3F1-2019-0082, Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2019-12-0505 December 2019 Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification Project stage: Meeting ML19344D0362019-12-19019 December 2019 Request for Withholding Information from Public Disclosure Affidavit Dated December 4, 2019, Executed by Zachary S. Harper of Westinghouse Electric Company LLC Meeting Slides Project stage: Withholding Request Acceptance ML20013G2592020-02-0707 February 2020 Summary of December 11, 2019 Partially Closed Presubmittal Meeting with Entergy Operations, Inc., to Discuss the Effect of a Planned LAR for Digital Instrumentation and Control Modification on Accident Analyses at Waterford (L-2019-LRM-0079 Project stage: Meeting 2019-12-05
[Table View] |
|
---|
Category:Letter type:W
MONTHYEARW3F1-2023-0056, Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 W3F1-2022-0028, Annual Radiological Environmental Operating Report - 20212022-04-26026 April 2022 Annual Radiological Environmental Operating Report - 2021 W3F1-2022-0029, Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.22062022-04-26026 April 2022 Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.2206 W3F1-2022-0009, Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2022-04-25025 April 2022 Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors W3F1-2022-0031, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-2842022-04-25025 April 2022 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-284 W3F1-2022-0020, Review of Preliminary Accident Sequence Precursor Report2022-04-11011 April 2022 Review of Preliminary Accident Sequence Precursor Report W3F1-2022-0017, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20212022-04-0707 April 2022 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2021 W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis W3F1-2022-0011, Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-02-0808 February 2022 Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0008, SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days2022-02-0101 February 2022 SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days W3F1-2021-0074, Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-022021-12-16016 December 2021 Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02 W3F1-2021-0064, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 2842021-11-30030 November 2021 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 284 W3F1-2021-0061, Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-10-14014 October 2021 Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0063, Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery2021-10-12012 October 2021 Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery W3F1-2021-0050, Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt2021-10-0101 October 2021 Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt W3F1-2021-0060, Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-09-30030 September 2021 Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0039, Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years2021-08-25025 August 2021 Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years W3F1-2021-0055, Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual2021-08-20020 August 2021 Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual W3F1-2021-0057, (Waterford 3) - Emergency Plan Revision 0522021-08-18018 August 2021 (Waterford 3) - Emergency Plan Revision 052 W3F1-2021-0054, License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 20202021-07-29029 July 2021 License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 2020 W3F1-2021-0051, Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator2021-07-19019 July 2021 Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator 2023-09-28
[Table view] |
Text
Entergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel 601-368-5546 Keith Jury VP, Regulatory Assurance 10 CFR 50.90 10 CFR 170.11 W3F1-2019-0034 May 16, 2019 ATTN: Document Control Desk Chief Financial Officer U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Letter-of-Intent to Submit License Amendment Requesting Using Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, Revision 2 and Request for NRC Fee Waiver Waterford Steam Electric Station, Unit 3 NRC Docket No. 50-382 Renewed Facility Operating License No. NPF-38 The purpose of this letter is to inform the U.S. Nuclear Regulatory Commission (NRC) that Entergy Operations Inc. (Entergy) intends to submit a license amendment request (LAR) for a digital instrumentation and control (DI&C) modification at Waterford Steam Electric Station, Unit 3 (Waterford 3). Entergy will develop and submit this LAR in accordance with the Alternate Review Process (ARP) guidance in NRC DI&C Interim Staff Guidance-(ISG)-06, "Licensing Process," Revision 2 (Reference 1).
The DI&C modification at Waterford 3 will replace the existing instrumentation of the Core Protection Calculator (CPC) system and Control Element Assembly Calculator (CEAC) system with a digital system based on an NRC-approved licensing topical report. Entergy expects to submit this LAR in the first quarter of 2020 to support installation of the modification during the Waterford 3 refueling outage starting in Spring 2022.
In addition, Entergy requests that the NRC review fees associated with the NRC evaluation of this LAR be waived in accordance with 10 CFR 170.11(a)(1)(ii) on the basis that the review of the LAR will assist the NRC in implementing generic regulatory improvements or efforts (i.e., as a "lead plant" or "pilot plant"). The promulgation and eventual implementation of the ARP in DI&C-ISG-06, Revision 2 represents a significant generic regulatory improvement effort, as follows.
W3F1-2019-0034 Page 2 of 3 The current revision to DI&C-ISG-06 was initiated by the NRC staff in response to an NRC directive to develop an integrated strategy to modernize the NRC's DI&C regulatory infrastructure. This integrated strategy is documented in SECY-16-0070, "Integrated Strategy to Modernize the Nuclear Regulatory Commissions Digital Instrumentation and Control Regulatory Infrastructure," (Reference 2). In this document, the revision to DI&C-ISG-06 is identified as essential to prioritizing and implementing regulatory activities that would be needed to provide near-term regulatory clarity, and support industry confidence to perform digital I&C upgrades.
In SECY-18-0100, "Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission's Digital Instrumentation and Control Regulatory Infrastructure,"
(Reference 3), the NRC staff described continued progress in streamlining the licensing review process for major DI&C upgrades. This progress included a pending revision of DI&C-ISG-06 which would include the new ARP. As stated in Reference 3, the ISG revision would reduce the scope of licensee document submittals and provide an alternative for earlier approval, which, unlike the current process, would precede factory acceptance testing, for digital designs that are based on approved topical reports.
On February 22, 2018, the NRC conducted a teleconference with industry stakeholders to discuss the status of a proposed revision to DI&C-ISG-06. This teleconference is documented in an internal NRC memorandum dated May 3, 2018 (Reference 4). During that teleconference, the NRC requested the status for identification of a potential lead plant that would submit a DI&C LAR using the ARP in the draft revision to DI&C-ISG-06. The NRC expressed concerns with potential delays in the identification of a lead plant, and pointed out that the DI&C-ISG-06 revision project was accelerated in order to accommodate a lead plant application.
In that Entergy will be the first licensee to utilize the ARP described in DI&C-ISG-06, Revision 2, and given the NRC's desire for a lead plant application to demonstrate the effectiveness of the ARP as part of the DI&C-ISG-06 revision, Entergy believes that the planned LAR submittal satisfies the standard for an NRC review fee waiver described in 10 CFR 170.11(a)(1)(ii).
Entergy respectfully requests a decision on the request for NRC fee waiver as soon as practicable to support timely and efficient scheduling of pre-submittal meetings and LAR development.
This letter contains no new regulatory commitments.
Should you have any questions or require additional information, please contact Stephenie Pyle, Senior Manager, Fleet Regulatory Assurance at 601-368-5516.
Respectfully, Keith Jury KJ/jls
W3F1-2019-0034 Page 3 of 3
References:
- 1) U.S. NRC Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, "Licensing Process," Revision 2 (ADAMS Accession No. ML18269A259)
- 2) SECY-16-0070, "Integrated Strategy to Modernize the Nuclear Regulatory Commissions Digital Instrumentation and Control Regulatory Infrastructure," (ADAMS Accession No. ML16097A182)
- 3) SECY-18-0100, "Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission's Digital Instrumentation and Control Regulatory Infrastructure," (ADAMS Accession No. ML18275A327)
- 4) J. A. Golla (NRC) to D. C. Morey (NRC) memorandum dated May 3, 2018 (ADAMS Accession No. ML18101A151) cc: NRC Region IV Regional Administrator NRC Senior Resident Inspector - Waterford Steam Electric Station, Unit 3 NRC Project Manager - Waterford Steam Electric Station, Unit 3