2009/01/08-In the Matter of Entergy Nuclear Vermont Yankee, LLC, and Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station). CUF Analyses on CS Nozzle and RO Nozzle at Vermont Yankee Nuclear Power Station
ML090230555
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 01/08/2009
From: Travieso-Diaz M F
Entergy Nuclear Operations, Entergy Nuclear Vermont Yankee, Pillsbury, Winthrop, Shaw, Pittman, LLP
To: Karlin A S, Reed W H, Wardwell R E
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-271-LR, ASLBP 06-849-03-LR, RAS M-396
Download: ML090230555 (4)


Text

9 SH -S 9 pillsburq 2300 N Street, N.W. Tel 202.663.8000 Washington, D.C. 20037-1128 Fax 202.663.8007 www.pillsburylaw.com Matias F. Travieso-Diaz tel 202.663.8142 matias.travieso-diaz@pillsburylaw.com January 8, 2009 Alex S. Karlin, Esq., Chairman Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Administrative Judge Dr. Richard E. Wardwell Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Administrative Judge Dr. William H. Reed Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 DOCKETED USNRC January 8, 2009 (11:21am)OFFICE OF SECRETARY RULEMAKINGS AND ADJUDICATIONS STAFF In the Matter of Entergy Nuclear Vermont Yankee, LLC, and Entergy Nuclear Operations, Inc.(Vermont Yankee Nuclear Power Station)Docket No. 50-271-LR; ASLBP No. 06-849-03-LR Gentlemen:

In accordance with the provisions of the Board's Partial Initial Decision (Ruling on Contentions 2A, 2B, 3, and 4), LBP-08-25, 68 N.R.C. (Nov. 24, 2008), slip op. at 67, Entergy has performed confirmatory environmentally assisted fatigue (CUFen) analyses on the Core Spray (CS) nozzle and the reactor pressure vessel recirculation outlet (RO) nozzle at the Vermont Yankee Nuclear Power Station. The results of these analyses are presented in the following Structural Integrity Associates, Inc. (SIA) calculations:

Calculation 0801038.301, Revision 0, "Design Inputs and Methodology for ASME Code Fatigue Usage Analysis of Reactor Core Spray Nozzle;" Calculation No. 080103 8.302, Revision 0, "Stress Analysis of Reactor Core Spray Nozzle;" Calculation No. 0801038.303, Revision 0, "Fatigue Analysis of Core Spray Nozzle;" Calculation No. 0801038.304, Revision 0, "Design Inputs and Methodology for ASME Code Fatigue Usage Analysis of Reactor Recirculation Outlet Nozzle;" Calculation No. 080103 8.305, Revision 0, "Stress Analysis of Reactor Recirculation Outlet Nozzle;" and Calculation No. 0801038.306, Revision 0, "Fatigue Analysis of Recirculation Outlet Nozzle."

January 8, 2009 Page 2 Entergy is serving at this time electronic copies of those analyses on the parties to the above captioned proceeding.

Hard copies are also being sent today by overnight mail to the NRC Staff, the New England Coalition and the Vermont Department of Public Service.The methodology applied in the referenced CS and RO confirmatory analyses is in accordance with the approach used in the SIA calculations for the feedwater nozzle that were introduced into evidence in this proceeding, and contains no significantly different scientific or technical judgments from those used in the feedwater nozzle calculations.

See Calculation 0801038.301 at 4, n.1 and Calculation 0801038.304 at 4, n..l.As set forth in the referenced calculations, the limiting calculated CUFen for the CS nozzle is 0.140, a value that is less than unity and is therefore acceptable.

Calculation 0801038.303 at 7. Also, the limiting calculated CUFen for the RO nozzle is 0.119, a value that is less than unity and is therefore acceptable.

Calculation 0801038.306 at 7.Sincerely, Matias Travieso-Diaz Counsel for Entergy cc: Service List Pillsbury Winthrop Shaw Pittman LLP CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter were served on the persons listed below by deposit in the U.S. Mail, first class, postage prepaid; where indicated by an asterisk, by electronic mail; and where indicated by a double asterisk, by both overnight and electronic mail, this 8 th day of January, 2009.*Administrative Judge Alex S. Karlin, Esq., Chairman Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ask2(anrc.

gov*Administrative Judge Dr. William H. Reed 1819 Edgewood Lane Charlottesville, VA 22902 whrcville(Delnbarqmail.com

  • Administrative Judge Dr. Richard E. Wardwell Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 rewanrc.gov
  • Secretary Att'n: Rulemakings and Adjudications Staff Mail Stop 0-16 C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 secy(@nrc.gov, hearingdocket(,,nrc.gov Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
    • Sarah Hofmiann, Esq.Director of Public Advocacy Department of Public Service 112 State Street -Drawer 20 Montpelier, VT 05620-2601 Sarah.hofinann(astate.vt.us
  • Office of Commission Appellate Adjudication Mail Stop 0-16 CI U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 OCAAmail(inrc.gov
    • Lloyd Subin, Esq.**Mary Baty, Esq.**Susan L. Uttal, Esq.Office of the General Counsel Mail Stop 0-15-D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 LBS3@,nrc.gov; mcbl (nrc.gov;jessica.bielecki

(@nrc. gov; susan.uttal(lnrc.gov

    • Raymond Shadis 37 Shadis Road PO Box 98 Edgecomb, ME 04556 shadis(a,)prexar.com
  • Peter L. Roth, E~sq.Office of the New Hampshire Attorney General 33 Capitol Street Concord, NH 03301 Peter.roth(@doi.nh.gov
  • Matthew Brock, Esq.Assistant Attorney General Environmental Protection Division Office of the Attorney General One Ashburton Place, 18th Floor Boston, MA 02108 Matthew.Brock(astate.ma.us
  • Zachary Kahn, Esq.Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 zachary.kalmh(nrc.gov Matias Travieso-Diaz 4