MONTHYEARML12181A4902012-06-26026 June 2012 6/26/12 - Vermont Pub Serv V NRC Opinion ML12181A5092012-06-26026 June 2012 Order Denying Petitions for Review ML12146A1592012-05-21021 May 2012 5/25/12 - Fed Respondents Post Argument Filing ML1211006992012-04-13013 April 2012 Order - Deferring Motion to Strike ML1211006872012-04-12012 April 2012 Motion for Admission Pro Hac Vice ML1211007042012-04-0909 April 2012 Order - VY Order Support Appendix ML12152A0802012-03-19019 March 2012 Final Respondents Brief ML12152A1062012-03-19019 March 2012 Entergy Final Brief ML1203004582012-01-27027 January 2012 Oral Argument Scheduled for May 9, 2012, Vermont Dept of Public Service,Et, Al., Petitioners V. USNRC, Et Al., Respondents ML1105407332011-02-23023 February 2011 Letter from Annette L. Vietti-Cook to the Honorable Paul W. Hodes Re Director'S Decision 11-01 ML1019305132010-07-12012 July 2010 Memorandum to the Participants Chairman Gregory B. Jaczko'S Upcoming Tour of the Vermont Yankee Nuclear Power Station and Round Table Discussion ML0914106802009-05-21021 May 2009 2009/05/21-Vermont Yankee - Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power Station - Supplement 1 ML0906903022009-02-26026 February 2009 Letter to Board Advising of Some Inconsequential Cha Nges in the Confirmatory Environmentally Assisted Fatigue Analyses That Were Provided to the Parties on January 9, 2009 ML0902305552009-01-0808 January 2009 in the Matter of Entergy Nuclear Vermont Yankee, LLC, and Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station). CUF Analyses on CS Nozzle and RO Nozzle at Vermont Yankee Nuclear Power Station ML0903303352009-01-0808 January 2009 Entergy Nuclear Vermont Yankee, LLC, and-Entergy Nuclear Operations, Inc., (Vermont Yankee), Corrected Letter to Board & Parties Re Confirmatory Calculations for CS & RO ML0900502542008-12-23023 December 2008 Motion for Leave and Brief Amicus Curiae on Parties in the Matter of Entergy Nuclear Vermont Yankee, and Entergy Nuclear Operations in Reliance Upon Certificate of Service List from NRC Staff'S Petition for Review Dated December 9, 2008 ML0823211072008-08-13013 August 2008 Joint Proposed Transcript Corrections ML0821200552008-07-18018 July 2008 Request for Explanation Re. Absence of Kenneth Chang to Testify ML0820605492008-07-18018 July 2008 State of New Hampshire List of Hearing Attendees ML0820406362008-07-15015 July 2008 New England Coalition, Inc.'S List of Hearing Attendees ML0820406162008-07-14014 July 2008 Entergy'S List of Hearing Attendees ML0819602912008-07-11011 July 2008 Vermont Yankee - Letter to Administrative Judges Transmitting Staff Non- Disclosure Agreements for Hearing ML0819602392008-07-11011 July 2008 Vermont Yankee - Letter to Administrative Judges Regarding Unavailability of NRC Staff Witness for Hearing July 20, 2008 ML0817506792008-06-20020 June 2008 Vermont Yankee - Letter to Board Transmitting Proposed Questions ML0816908252008-06-17017 June 2008 Vermont Yankee - NRC Staff Hearing File Update Supplement 23 ML0815504222008-05-28028 May 2008 Commonwealth of Massachusetts' Designation of Single Representative ML0814906312008-05-28028 May 2008 2008/05/28-Letter to Board from Staff Transmitting NUREG-1907-Safety Evaluation Report Related to License Renewal of Vermont Yankee Nuclear Power Station, Volumes 1 and 2 ML0814306822008-05-22022 May 2008 Letter to Atomic Safety and Licensing Board Corrected Affidavit of Kenneth Chang (Exhibit 2) and Missing Page 4-43 to Staff Exhibit 1 ML0812903772008-05-0202 May 2008 2008/05/02-Memorandum to Chairman Klein from the Inspector General on the Subject of NRC Staff Review of License Renewal Applications ML0812805922008-04-29029 April 2008 New England Coalition, Inc.'S (NEC) Motion to Withdraw Motion to Compel and for Subpoena ML0812603282008-04-25025 April 2008 in the Matter of Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 & 3), Forwarding Courtesy Copy of Court of Appeals Decision to Deny Commonwealth of Massachusetts' Petitions for Review for Pilgrim and Vermont Yanke ML0810704562008-04-0404 April 2008 Entergy'S Statement of Witness Availability ML0810502602008-04-0404 April 2008 New England Coalition, Inc.'S (NEC) Statement of Witness Availability ML0810501382008-04-0404 April 2008 Transmittal of State of New Hampshire'S Statement of Date Blackout ML0810603232008-04-0303 April 2008 2008/04/03-State of Vermont Response to Order Requiring Information of Anticipated Schedule Conflicts in August and September Evidentiary Hearings for Vermont Yankee Nuclear Power Station License Renewal ML0807204812008-03-12012 March 2008 Vermont Yankee - NRC Staff Declaration of Position ML0807401992008-03-0707 March 2008 New England Coalition, Inc.'S (NEC) Final Witness List ML0807204262008-03-0606 March 2008 Entergy'S Final List of Witnesses ML0806700882008-03-0606 March 2008 Vermont Yankee - NRC Staff Final Witness List ML0805706532008-02-26026 February 2008 Vermont Yankee - Letter to the Licensing Board Regarding Issuance of SER ML0733212822007-11-26026 November 2007 E-mail from Sarah Hofmann to the Board and Parties Re Black Out Dates for Evidentiary Hearings ML0731204512007-11-0808 November 2007 Commonwealth of Massachusetts V. United States Nuclear Regulatory Commission and the United States of America, Nos. 07-1482, 07-1483 (Consolidated) ML0731204532007-11-0101 November 2007 Commonwealth of Massachusetts V. United States and Unites States Nuclear Regulatory Commission Nos. 07-1482; 07-1483 ML0730502172007-10-31031 October 2007 Commonwealth of Massachusetts V. NRC, No. 07-1482 ML0727500532007-10-0101 October 2007 Letter from J. Samuel Walker to Scott H. Strauss and Rebecca J. Baldwin Re Local 369 Petition for Leave to Intervene ML0725601052007-08-29029 August 2007 Commonwealth of Massachusetts V. USNRC, Nos. 07-1482 and 07-1483; Unopposed Motion for Extension of Time to File Respondents' Brief ML0721900342007-07-24024 July 2007 Letter from Karen Tyler Enclosing a Complete Copy of Attachment A. an Incomplete Copy Was Erroneously Filed with New England'S Coalition, Inc.'S Supplement to Opposition to Entergy'S Motion for Summary Disposition...Dated 07/19/07 ML0719302612007-07-11011 July 2007 Notice of Withdrawal of Mitzi A. Young ML0719903452007-06-29029 June 2007 Letter from Sarah Hofmann to Administrative Judges Informing That the Counsel for the Vermont Department of Public Service Are Available Any of the Dates for the Site Visit Except for October 5, 8, 9 and 10 ML0718702962007-06-29029 June 2007 Letter from Sarah Hofmann to Administrative Judges Informing That Counsel for the Vermont Department of Public Service Are Available Throughout February and March of 2008 for Hearings 2012-06-26
[Table view] |
Text
DOCKETED UNITED STATES USNRC NUCLEAR REGULATORY COMMISSION July 12, 2010 (3:15p.m.)
WASHINGTON, D.C. 20555-0001 OFFICE OF SECRETARY RULE MAKINGS AND ADJUDICATIONS STAFF July 12, 2010 SERVED July 12, 2010 OFFICE OF THE CHAIRMAN MEMORANDUM TO THE PARTIES IN: ENTERGY NUCLEAR VERMONT YANKEE, LLC, and EI\lTERGY NUCLEAR OPERATIOI\lS, II\lC.
Docket No. 50-271-LR (Vermont Yankee Nuclear Power Station)
This is to inform the parties that Chairman Jaczko will be holding a roundtable discussion with Vermont Yankee area stakeholders in Brattleboro, Vermont on Wednesday, July 14, 2010. The roundtable discussion will take place from 9:30 a.m. to 11 :00 a.m. at the Ramada Hotel and Conference Center at 1380 Putney Road and will be open to public observation. Following the roundtable discussion, he will meet with reporters and then travel to the Vermont Yankee Nuclear Power Station. The Chairman will conduct a tour of the facility, meet with the NRC resident inspectors and hold an all-hands meeting with plant employees. The purpose of the Chairman's activities is to gain greater familiarity with the facility and discuss general matters relating to the facility. The Chairman will not engage in substantive discussions regarding any of the issues in the ongoing adjudicatory proceeding.
c~ ~.~ ~/_AC-Lisa Clark Legal Counsel to Chairman Jaczko cc: Service list
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ENTERGY NUCLEAR VERMONT YANKEE, Docket No. 50-271-LR LLC, and ENTERGY NUCLEAR OPERATIONS, INC.
(Vermont Yankee Nuclear Power Station)
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing MEMORANDUM TO THE PARTICIPANTS RE:
CHAIRMAN GREGORY B. JACZKO'S UPCOMING TOUR OF THE VERMONT YANKEE NUCLEAR POWER STATION AND ROUND TABLE DISCUSSION have been served upon the following persons bye-mail and first class mail or through NRC internal distribution in this license renewal proceeding.
Office of Commission Appellate U.S. Nuclear Regulatory Commission Adjudication Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission Mail Stop 0-16C1 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Hearing Docket E-mail: hearingdocket@nrc.gov Atomic Safety and Licensing Board Panel Lloyd B. Subin, Esq.
Mail Stop - T-3 F23 Maxwell C. Smith, Esq.
U.S. Nuclear Regulatory Commission Susan L. Uttal, Esq.
Washington, DC 20555-0001 Mary B. Spencer, Esq.
Brian Newell, Paralegal Alex S. Karlin, Chair Office of the General Counsel 015021 Administrative Judge U.S. Nuclear Regulatory Commission E-mail: ask2@nrc.gov Washington, DC 20555-0001 E-mail: L1oyd.Subin@nrc.gov; Richard E. Wardwell maxwell.smith@nrc.gov; susan.utall@nrc.gov; Administrative Judge bpn@nrc.gov; mcb1 @nrc.gov E-mail: rew@nrc.gov William H. Reed Administrative Judge Atomic Safety and Licensing Board Panel 1819 Edgewood Lane Charlottesville, VA 22902 E-mail: E-mail:whrcville@embargmail.com Lauren Bregman, Law Clerk E-mail: laren.bregman@nrc.gov
2 DOCKET NO. 50-271-LR MEMORANDUM TO THE PARTICIPANTS RE: CHAIRMAN GREGORY B. JACZKO'S UPCOMING TOUR OF THE VERMONT YANKEE NUCLEAR POWER STATION AND ROUND TABLE DISCUSSION Sarah Hofmann, Esq. Anthony Z. Roisman, Esq.
Director for Public Advocacy National Legal Scholars Law Firm Department of Public Service 84 East Thetford Rd.
112 State Street - Drawer 20 Lyme, NH 03768 Montpelier, VT 05620-2601 E-mail: aroisman@nationallegalscholars.com E-mail: sarah.hoffman@state.vt.us Matthew Brock Dan MacArthur, Director Assistant Attorney General Town of Marlboro Environmental Protection Division Emergency Management Office of the Attorney General P.O. Box 30 One Ashburton Place, 18th Floor Marlboro, VT 05344 Boston, MA 02108 E-mail: dmacarthur@igc.org E-mail: matthew.brock@state.ma.us Callie B. Newton, Chair Peter C. L. Roth, Esq.
Gail MacArthur Senior Assistant Attorney General Lucy Gratwick State of New Hampshire Town of Marlboro Office of the New Hampshire SelectBoard Attorney General P.O. Box 518 33 Capitol Street Marlboro, VT 05344 Concord, I\IH 03301 E-mail: cbnewton@sover.net E-mail: peter. roth@doj.nh.gov David R. Lewis, Esq. Alan A. Pemberton, Esq.
Matias F. Travieso-Diaz, Esq. Covington & Burling, LLP Elina Teplinsky, Esq. Counsel for Electric Power Research Institute Pillsbury Winthrop Shaw Pittman, LLP 1201 Pennsylvania Avenue, NW 2300 N Street, NW Washington, DC 20004-2401 Washington, DC 20037-1128 E-mail: apemberton@cov.com; E-mail: david.lewis@pillsburylaw.com; matias.travieso-diaz@pillsburylaw.com; Elina.Teplinsky@pilisburylaw.com; Robert L. Stewart Raymond Shadis New England Coalition 37 Shadis Road 229 Kibbee Ext. P.O. Box 98 Brookfield, Vermont 05036 Edgecomb, ME 04556 E-mail: Jakeskis@aol.com E-mail: shadis@prexar.com
3 DOCKET NO. 50-271-LR MEMORANDUM TO THE PARTICIPANTS RE: CHAIRMAN GREGORY B. JACZKO'S UPCOMING TOUR OF THE VERMONT YANKEE NUCLEAR POWER STATION AND ROUND TABLE DISCUSSION Raymond Shad is New England Coalition P.O. Box 545 Brattleboro, VT 05302 E-mail: necnp@necnp.org
~~
Office of the Secretary of the Commission Dated at Rockville, Maryland h
this 1i day of July 2010.