Email from J. Rikhoff, NRR to C. Eccleston, NRR Salem/Hope Creek Audit Plan & Schedule
ML11259A257
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 02/23/2010
From: Rikhoff J J
Division of License Renewal
To: Eccleston C H
Office of Nuclear Reactor Regulation
References
FOIA/PA-2011-0113
Download: ML11259A257 (2)


Text

r÷.Rikhoff, Jeffrey From: Je'ffreyf Sent: Tuesday, February 23, 2010 9:02 AM To: Ec-cleston C Charles Cc: Imboden, Andy; Pham, Bo; Beissel, Dennis; Logan, Dennis; Klementowicz, Stephen; Travers, Allison; Bacuta, George; Bulavinetz, Richard

Subject:

RE: Salem/Hope Creek Audit Plan & Schedule Charles, Thank you for the opportunity to review the site visit schedule and plan. My comments are listed below.Schedule: 1. I strongly recommend moving Presentation

  1. 3 (New Plant Early Site Permit) to the beginning of the week (Tuesday rather than Thursday) since the information provided in this presentation will have a bearing in all interviews for all resource areas.2. Add Rikhoff to Tour #2, Archaeological/Historical Resources.
3. Tuesday, someone from NRC (Klementowicz?)

needs to go on Tour #4.4. Tuesday, correct the spelling of my last name to Rikhoff.5. Wednesday, someone from NRC (Logan?) needs to go on Tours #5 and #6.6. Thursday, not everyone needs to go on the boat tour or Presentation

  1. 2 (Estuary Enhancement Program).Perhaps Presentation
  1. 2 should be moved to the beginning of the week along with Presentation
  1. 3. The information provided in Presentation
  1. 2 would have a bearing in the Aquatic recourses interview.

Plan: 1. Interview

  1. 1 has Archaeological

& historical resources and Socioeconomics combined.

Delete from Taxes to Justice under NRC Description.

2. Remove Dillard's name from the Archaeological

& historical resources interview.

He's a biologist.

Goodwin is the Archaeologist.

3. List A. Travis and J. Rikhoff under NRC for Tour #2, Archaeological/Historical Resources.

Let me know if you have any questions.

Thanks, jeff Jeffrey Rikhoff Senior Environmental Scientist Environmental Review Branch Division of License Renewal, NRR U.S. Nuclear Regulatory Commission 301/415-1090 Jeffrey. Rikhoff(cnrc.qov From: Eccleston, Charles Sent: Monday, February 22, 2010 8:11 PM To: Bacuta, George; Beissel, Dennis; Bulavinetz, Richard; Imboden, Andy; Klementowicz, Stephen; Logan, Dennis;Rikhoff, Jeffrey; Travers, Allison; Pham, Bo Cc: Eccleston, Charles

Subject:

Salem/Hope Creek Audit Plan & Schedule 1 Staff, Attached is the draft Salem/Hope Creek Schedule and Audit Plan. Please review this and return any comments to me by COB Wendesday 24th.& H.W'4 scceato, Charles H. Eccleston Nuclear Reactor Regulation Licensing Renewal, Project Manager 301.415.8537 charles.ecclestonwnrc.gov 2