NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066)
ML22291A370
Person / Time
Site: Salem PSEG icon.png
Issue date: 10/18/2022
From: James Kim
NRC/NRR/DORL/LPL1
To: Bernard Thomas
Public Service Enterprise Group
References
L-2022-LLR-0066
Download: ML22291A370 (2)


Text

From: James Kim Sent: Tuesday, October 18, 2022 1:20 PM To: Thomas, Brian J.

Cc: Montgomery, Richard; Hipo Gonzalez

Subject:

Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066)

Mr. Thomas, By letter dated September 27, 2022 (Agencywide Documents and Access Management System (ADAMS) Accession No. ML22270A326), PSEG Nuclear LLC (the licensee) requested NRC approval of the relief request that addresses limitations for examinations performed in accordance with the requirements of the American Society of Mechanical Engineers (ASME)

Boiler and Pressure Vessel Code,Section XI, "Rules for lnservice Inspection of Nuclear Power Plant Components, for Class 1 components for the fourth 10-year ISI interval for the Salem Generating Station Unit 2 which ended on December 31, 2021.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 220 hours0.00255 days <br />0.0611 hours <br />3.637566e-4 weeks <br />8.371e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is October 18, 2023. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any question, please contact me, James Kim, at James.Kim@nrc.gov or 301-415-4125.

James Kim, Project Manager Branch 1, Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission

Hearing Identifier: NRR_DRMA Email Number: 1813 Mail Envelope Properties (DM6PR09MB47116CD83E0499BCEDF98AB2E4289)

Subject:

Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066)

Sent Date: 10/18/2022 1:19:43 PM Received Date: 10/18/2022 1:19:00 PM From: James Kim Created By: James.Kim@nrc.gov Recipients:

"Montgomery, Richard" <Richard.Montgomery@pseg.com>

Tracking Status: None "Hipo Gonzalez" <Hipolito.Gonzalez@nrc.gov>

Tracking Status: None "Thomas, Brian J." <Brian.Thomas@pseg.com>

Tracking Status: None Post Office: DM6PR09MB4711.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2616 10/18/2022 1:19:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: