MONTHYEARML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22123A1812022-05-0303 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577 ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22081A2222022-03-22022 March 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 1, License Amendment Request to Revise Allowable Value for TS Table 3.3.2-1, Function 6.e(1) ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML22131A1902022-02-23023 February 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Request to Revise the Reactor Vessel Surveillance Capsule Withdrawal Schedule ML22046A0392022-02-15015 February 2022 NRR E-mail Capture - Request for Confirmation of Information Regarding the Watts Bar Nuclear Plant, Unit 2, Cycle 4 Mid-Cycle Outage Generic Letter 95-05 Final Report ML22038A1882022-02-0404 February 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Revise the TVA Radiological Emergency Plan ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22011A0382022-01-10010 January 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-205-A, Rev. 3 and TSTF-563-A ML21306A2452021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21252A0912021-09-0909 September 2021 NRR E-mail Capture - Request for Comments on Proposed Issuance of Amendments to Watts Bar Nuclear Plant, Unit 2 - Revise Steam Generator Secondary Side Water Level ML21223A2592021-08-11011 August 2021 Affidavit - Prop Slides - Partially Closed Meeting with TVA Potential Watts Bar, Unit 2 Tube Locking LAR ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21215A1152021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21215A1142021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21197A0452021-07-15015 July 2021 WBN U1 Isi/Sgisi Request for Information (RFI) Letter ML21193A2422021-07-12012 July 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 2 Technical Specifications Related to Steam Generator Inspection/Repair Program Provisions ML21189A0202021-06-29029 June 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specifications 3.3.6 and 3.3.7 Re Radiation Monitor Redundant Unit of Measure 2024-01-22
[Table view] |
Text
1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
Sent: Monday, October 24, 2011 12:04 PM To: Epperson, Dan; Poole, Justin; Raghavan, Rags; Milano, Patrick; Campbell, Stephen Cc: Arent, Gordon; Hamill, Carol L; Boyd, Desiree L
Subject:
TVA letter to NRC_10-24-11_Response to SSER23 - RA 71 Attachments:
10-24-11_Response to SSER23 - RA 71_Final.pdfPlease see attached TVA letter that was sent to the NRC today.
Thank You, ~*~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services
dlboyd@tva.gov 423-365-8764
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 579 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF247FDF85)
Subject:
TVA letter to NRC_10-24-11_Response to SSER23 - RA 71 Sent Date: 10/24/2011 12:03:58 PM Received Date: 10/24/2011 12:04:04 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: "Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>
Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov> Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov> Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Raghavan, Rags" <Rags.Raghavan@nrc.gov> Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov> Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 291 10/24/2011 12:04:04 PM 10-24-11_Response to SSER23 - RA 71_Final.pdf 102814 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000
October 24, 2011
10 CFR 50.34 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Safety Evaluation Report Supplement 23 (SSER23) - Response to NRC Required Action Item 71
References:
- 1. TVA letter dated June 28, 2010, Watts Bar Nuclear Plant (WBN) Unit 2 -
Request for Additional Information (RAI) Regarding Licensees Final Safety Analysis Report Amendment Related to Section 4.2.2, Reactor Vessel
Internal Components (TAC No. ME2731) 2. TVA letter to NRC dated April 21, 2011, Watts Bar Nuclear Plant (WBN) Unit 2 - Withdrawal of a Previous Commitment 3. Westinghouse Electric Company letter dated October 14, 2011, Watts Bar Unit 2 Reactor Internals Clevis Bolts Information for Response to U. S. NRC, (Letter number LTR-RIDA-11247, Rev. 1)
Open Item 71 from Appendix HH of SSER23 reads as follows:
By letter dated April 21, 2011 (ADAMS Accession No. ML111110513, TVA withdrew its commitment to replace the Unit 2 clevis insert bolts. TVA should provide further justification for the decision to not replace the bolts to the NRC staff. (SSER23, Section 3.9.5, PG 3-2/3)
In Reference 1, TVA committed to replace, prior to Unit 2 operation, the current Unit 2 clevis insert bolts with a design which uses X-750 alloy with a high temperature heat (HTH) treatment, rolled threads, and a larger radius on the undercut of the cap screw head.
U.S. Nuclear Regulatory Commission Page 3 October 24, 2011
bcc (Enclosure):
Stephen Campbell U.S. Nuclear Regulatory Commission MS 08H4A One White Flint North
11555 Rockville Pike
Rockville, Maryland 20852-2738
Patricia Holahan, Acting Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission
Region II Marquis One Tower
245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
Westinghouse Non-Proprietary Class 3 Enclosure Information Relative to Clevis Insert Bolt Failures To date, D. C. Cook Unit 1 is the only occurrence of such indications of a bolt failure found during inspection. Within the past five years, Westinghouse has performed inspections, has
received positive feedback from, or has reviewed videos from past inspections at the following plants and has found no indications of clevis insert bolt failures: Ginna (Spring 2011) D.C. Cook Unit 2 (Fall 2010) McGuire Unit 1 (Spring 2010) Surry Unit 1 (Fall 2010) Seabrook Unit 1 (Fall 2009) Indian Point Unit 2 (Spring 2006) Indian Point Unit 3 (Spring 2009) Farley Unit 2 (Spring 2010)
Furthermore, Westinghouse records indicate that the following additional Westinghouse plants in the U.S. would have conducted a 10-year in-service inspection (ISI) in the past 5 years from which there have been no reports on clevis insert bolt failures: South Texas Unit 1 (Fall 2009) South Texas Unit 2 (Spring 2010) North Anna Unit 1 (Spring 2009) North Anna Unit 2 (Spring 2010) Comanche Peak Unit 2 (Fall 2009) Point Beach Unit 1 (Fall 2008) Point Beach Unit 2 (Spring 2008) Braidwood Unit 1 (Fall 2007) Braidwood Unit 2 (Spring 2008) Farley Unit 1 (Fall 2007) Vogtle Unit 1 (Fall 2006) Vogtle Unit 2 (Spring 2007)
It should be pointed out that all Westinghouse plants, with the possible exception of Sizewell B, use a heat treatment of X-750 similar to that used at Cook Unit 1 for the clevis insert bolts, which is a lower temperature heat treatment than the high temperature heat treatment (HTH condition). Also, from a review of pictures, it appears the locking bar was impacted by the bolt head due to some type of movement. It has been hypothesized that the wear of the lock bar is caused by flow-induced vibration of a loose bolt head against a lock bar, which has relatively lower hardness. It is postulated that the head fractured from the bolt shank prior to the start of this wear mechanism.