September 1, 2011
SUBJECT:
MID-CYCLE LETTER FOR MONTICELLO NUCLEAR GENERATING PLANT; 05000263/2011-006
Dear Mr. OConnor:
On August 10, 2011, the NRC completed its mid-cycle performance review of the Monticello Nuclear Generating Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined the performance at the Monticello Nuclear Generating Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance and all PIs indicated that your performance was within the normal, expected range (i.e.,green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2012. Routine resident inspections are not included in the inspection plan. In addition to the ROP baseline inspections, the NRC will be conducting the following additional inspection at your facility: IP 60855.1, Operation of an Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
T. O'Connor
-2-
In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here:
http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (630) 829-9628 with any questions you may have regarding this letter.
Sincerely,
/RA/
Kenneth Riemer, Branch Chief Branch 2 Division of Reactor Projects
Docket No. 50-263 License No. DPR-22
Enclosure: Monticello Nuclear Generating Plant Inspection/Activity Plan
cc w/encl: Distribution via ListServe
T. O'Connor
-2-
In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here:
http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (630) 829-9628 with any questions you may have regarding this letter.
Sincerely,
/RA/
Kenneth Riemer, Branch Chief Branch 2 Division of Reactor Projects
Docket No. 50-263 License No. DPR-22
Enclosure: Monticello Nuclear Generating Plant Inspection/Activity Plan cc w/encl: Distribution via ListServe DISTRIBUTION:
See next page DOCUMENT NAME: G:\\DRPIII\\1-Secy\\1-Work In Progress\\2011 MOC Letters\\Monticello MOC Letter 2011.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl
"E" = Copy with attach/encl "N" = No copy OFFICE RIII
RIII N RIII
RIII
NAME MZiolkowski KRiemer:cs
DATE 08/19/11 08/22/11
OFFICIAL RECORD COPY
Letter to T. O'Connor from K. Riemer dated Septemer 1, 2011
SUBJECT:
MID-CYCLE LETTER FOR MONTICELLO NUCLEAR GENERATING PLANT; 05000263/2011-006
DISTRIBUTION:
Daniel Merzke RidsNrrDorlLpl3-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov
Inspection / Activity Plan 09/01/2011 - 12/31/2012 Planned Dates Start End Inspection Activity Title No. of Staff on Site Monticello ISFSI
- ISFSI INSPECTION - SCHEDULE DEPENDENT
IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 09/01/2011 11/30/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 09/12/2011 09/16/2011 BI OLRQ
- BIENNIAL REQUAL PROGRAM EVAL
IP Licensed Operator Requalification Program 7111111B 10/03/2011 10/07/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 10/31/2011 11/04/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Occupational ALARA Planning and Controls 71124.02 11/14/2011 11/18/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Radiological Hazard Assessment and Exposure Controls 71124.01 01/23/2012 01/27/2012 IP Radiation Monitoring Instrumentation 71124.05 01/23/2012 01/27/2012 IP Performance Indicator Verification 71151 01/23/2012 01/27/2012 BI CDBI
- COMPONENT DESIGN BASIS INSP. & TI-177
IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 03/26/2012 04/27/2012 IP Component Design Bases Inspection 7111121 03/26/2012 04/27/2012 BI EPR
- EP ROUTINE INSPECTION / PI VERIFICATION
IP Alert and Notification System Testing 7111402 06/04/2012 06/08/2012 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 06/04/2012 06/08/2012 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 06/04/2012 06/08/2012 IP Performance Indicator Verification 71151 06/04/2012 06/08/2012 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 08/13/2012 08/17/2012 BI PI&R
- BIENNIAL PI&R INSPECTION
IP Problem Identification and Resolution 71152B 09/10/2012 09/28/2012 BI RP
- RADIATION PROTECTION BASELINE INSPECTION
IP Occupational ALARA Planning and Controls 71124.02 10/22/2012 10/26/2012 OL PREP
- INITIAL EXAM - 01/2013