ML11297A033
From kanterella
Revision as of 10:01, 3 March 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Letter Sequence Request | |
---|---|
TAC:ME5287, (Approved, Closed) | |
Initiation Administration | |
MONTHYEARML1101002912011-01-0505 January 2011
[Table View]Cooper - License Amendment Request for Reducing the Number of Technical Specification 3.4.3 Required Safety Relief Valves Project stage: Request ML1104202012011-02-11011 February 2011 Acceptance Review Email, License Amendment Request, Revise Technical Specification 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs), to Reduce Number of Required SRVs for Overpressure Protection Project stage: Acceptance Review ML1114307042011-06-0303 June 2011 Request for Additional Information, License Amendment Request, Revise Technical Specification 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs), to Reduce Number of Required SRVs for Overpressure Protection Project stage: RAI ML1118100852011-06-30030 June 2011 Notice of Meeting with Nebraska Public Power District to Discuss Cooper'S Request to Revise TS 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs), to Reduce Number of Required SRVs for Overpressure Protection Project stage: Meeting ML1121401792011-07-11011 July 2011 Licensee Slides from Conference Call with Nebraska Public Power District Project stage: Other ML1121700812011-08-18018 August 2011 7/12/11 - Summary of Teleconference with Nebraska Public Power District to Discuss Cooper'S Request to Revise TS 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs) at Cooper Nuclear Station Project stage: Meeting NLS2011086, Supplement to License Amendment Request for Reducing the Number of Technical Specification 3.4.3 Required Safety Relief Valves2011-10-0606 October 2011 Supplement to License Amendment Request for Reducing the Number of Technical Specification 3.4.3 Required Safety Relief Valves Project stage: Supplement NLS2011088, Response to Nuclear Regulatory Commission Request for Additional Information for Reducing the Number of Technical Specification 3.4.3 Required Safety Relief Valves2011-10-18018 October 2011 Response to Nuclear Regulatory Commission Request for Additional Information for Reducing the Number of Technical Specification 3.4.3 Required Safety Relief Valves Project stage: Request ML1104808522011-11-0101 November 2011 Request for Withholding Information from Public Disclosure, 2/18/11 Affidavit Executed by J. Harrison, GE Hitachi Nuclear Energy, NEDC-33543P, Revision 0 Project stage: Withholding Request Acceptance ML1136302582012-01-31031 January 2012 Issuance of Amendment No. 240, Revise Technical Specification 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs), to Reduce Number of Required SRVs for Overpressure Protection Project stage: Approval 2011-02-11 |
ML11297A033 | |
Person / Time | |
---|---|
Site: | Cooper |
Issue date: | 10/18/2011 |
From: | Willis D L Nebraska Public Power District (NPPD) |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
NLS2011088, TAC ME5287 | |
Download: ML11297A033 (6) | |
Similar Documents at Cooper | |
---|---|
Category:Letter
MONTHYEARML24227A0822024-09-0303 September 2024
[Table view]Summary of Regulatory Audit in Support of License Amendment Request to Modify the High Pressure Coolant Injection Low Flow Value IR 05000298/20240052024-08-22022 August 2024 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2024005) IR 05000298/20240022024-07-25025 July 2024 Integrated Inspection Report 05000298/2024002 ML24183A1722024-07-17017 July 2024 Issuance of Amendment No. 277 to Adopt TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil ML24197A1462024-07-15015 July 2024 NRC Region IV Ltr to Cooper Nuclear Station Re FEMA Level 1 Finding IR 05000298/20243012024-07-12012 July 2024 NRC Examination Report 05000298/2024301 ML24134A1782024-07-0303 July 2024 Issuance of Amendment No. 276 Revision to Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air, to Allow for Cleaning, Inspection and Any Needed Repairs During Refuel Outage 33 ML24197A0682024-06-24024 June 2024 FEMA Ltr to Missouri State Emergency Management Agency - Level 1 Finding, 24 June 2024 ML24192A0112024-06-13013 June 2024 2024-06-Post Exam Comments IR 05000298/20244012024-06-0404 June 2024 Security Baseline Inspection Report 05000298/2024401 ML24151A1082024-05-30030 May 2024 NRC Initial Operator Licensing Examination Approval 05000298/2024301 ML24137A0942024-05-17017 May 2024 Regulatory Audit Plan in Support of License Amendment Request to Modify Allowable Value Regarding Technical Specification for High Pressure Coolant Injection Pump Discharge Low Flow IR 05000298/20240012024-05-0303 May 2024 Integrated Inspection Report 05000298/2024001 ML24129A0952024-04-25025 April 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000298/20240102024-04-24024 April 2024 Comprehensive Engineering Team Inspection Report 05000298/2024010 ML24096A1202024-04-0505 April 2024 Issuance of Amendment No. 275 Revision to Technical Specification 3.3.1.1 (Emergency Circumstances) ML24093A2282024-04-0202 April 2024 Notice of Enforcement Discretion for Cooper Nuclear Station IR 05000298/20240902024-04-0101 April 2024 – Notice of Violation, NRC Inspection Report 05000298/2024090 IR 05000298/20230062024-02-28028 February 2024 Annual Assessment Letter for Cooper Nuclear Station - Report 05000298/2023006 IR 05000298/20230042024-02-12012 February 2024 Integrated Inspection Report 05000298/2023004 ML24033A3092024-02-12012 February 2024 Summary of Regulatory Audit Regarding the Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20230122024-02-12012 February 2024 NRC Inspection Report 05000298/2023012 ML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A1122023-11-0909 November 2023 Project Manager Assignment IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report ML23102A0282023-04-19019 April 2023 U.S. Nuclear Regulatory Commission Presentation at the May 8, 2023, Brownville Village Meeting IR 05000298/20230012023-04-17017 April 2023 Integrated Inspection Report 05000298/2023001 ML23060A1582023-03-0808 March 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000298/2023001 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 ML23041A1622023-02-10010 February 2023 Licensed Operator Positive Fitness-for-Duty Test Request for Additional Information IR 05000298/20220042023-01-30030 January 2023 Integrated Inspection Report 05000298/2022004 IR 05000298/20220112022-12-23023 December 2022 License Renewal Phase 4 Inspection Report 05000298/2022011 ML22286A2072022-11-30030 November 2022 Issuance of Amendment No. 272 Revision to Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements IR 05000298/20220032022-10-27027 October 2022 Integrated Inspection Report 05000298/2022003 ML22304A0052022-10-26026 October 2022 Surveillance Capsule Location (Re-insertion Into the Reactor Vessel) IR 05000298/20223022022-10-20020 October 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022302 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information 2024-09-03 |
Retrieved from "https://kanterella.com/w/index.php?title=ML11297A033&oldid=463170"