|
---|
Category:Letter
MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 IR 05000318/20240072024-11-0606 November 2024 Assessment Follow-Up Letter for Calvert Cliffs Nuclear Power Plant, Unit 2 (Report 05000318/2024007) ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 ML24177A1832024-06-25025 June 2024 Inservice Inspection Report RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24136A1962024-05-15015 May 2024 Independent Spent Fuel Storage Installation - Annual Radiological Environmental Operating Report IR 05000317/20240012024-05-0707 May 2024 Integrated Inspection Report 05000317/2024001 and 05000318/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000317/LER-2024-002, Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus2024-04-29029 April 2024 Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus 05000318/LER-2024-001, Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip2024-04-24024 April 2024 Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 ML24114A0182024-04-18018 April 2024 Electronic Reporting of Occupational Exposure Reporting 05000318/LER-2023-004-01, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-04-12012 April 2024 Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240402024-04-11011 April 2024 95001 Supplemental Inspection Report 05000317/2024040 and Follow-Up Assessment Letter RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24078A1152024-03-18018 March 2024 10 CFR 50.46 Annual Report ML24059A0632024-03-15015 March 2024 Authorization and Safety Evaluation for Alternative Request ISI-05-021 (EPID L-2023-LLR-0006) - Non-Proprietary IR 05000317/20230062024-02-28028 February 2024 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, (Reports 05000317/2023006 and 05000318/2023006 ML24052A0072024-02-14014 February 2024 Core Operating Limits Report for Unit 1, Cycle 27, Revision 0 ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank 2024-09-06
[Table view] Category:License-Operator Examination Report
MONTHYEARML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20223012022-08-16016 August 2022 Initial Operator Licensing Examination Report 05000317/2022301 and 05000318/2022301 IR 05000317/20213012021-07-26026 July 2021 Initial Operator Licensing Examination Report 05000317/2021301 and 05000318/2021301 IR 05000317/20203012020-03-23023 March 2020 Initial Operator Licensing Examination Report 05000317/2020301 and 05000318/2020301 IR 05000317/20193012019-05-0606 May 2019 NRC Initial and Retake Operator Licensing Examination Report Er 05000317/2019301 and 05000318/2019301 IR 05000317/20183012019-01-25025 January 2019 Initial Operator Licensing Examination Report, Er 05000317/2018301; 05000318/2018301; 8/6-8/15 2018 IR 05000317/20163012016-08-18018 August 2016 Initial Operator Licensing Examination Report 05000317/2016301 and 05000318/2016301 RS-14-164, (EGC) Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations2014-05-29029 May 2014 (EGC) Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations IR 05000317/20123012012-10-16016 October 2012 Er 05000317-12-301; 05000318-12-301; August 13-23, 2012; Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report ML11192A2052011-07-0707 July 2011 Response to NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations IR 05000317/20083022009-01-22022 January 2009 Er 05000317/08-302 & 05000318/08-302 on 12/10/08 for Calvert Cliffs, Units 1 and 2 ML0834306022008-12-0808 December 2008 Operator Licensing Retake Written Examination Approval (Calvert Cliffs Units 1 and 2) IR 05000317/20023012002-08-30030 August 2002 IR 05000317-02-301 and 05000318-02-301, on July 12-18, 2002, Calvert Cliffs Nuclear Power Plant, Initial Operator Licensing Examinations 2024-10-09
[Table view] |
Text
October 9, 2024 David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer (CNO)
Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 - SENIOR REACTOR AND REACTOR OPERATOR INITIAL LICENSE EXAMINATIONS
Dear David Rhoades:
In a telephone conversation on October 1, 2024, between T. Setzer, Chief Examiner; B. Dyke, Operations Engineer; M. Parlett, Exam Author; K. Swiger, Exam Author; and C. Burkhart, Corporate Exam Expert, arrangements were made for the administration of licensing examinations at Calvert Cliffs Nuclear Power Plant, Units 1 and 2, during the week of June 23, 2025. In addition, the U.S. Nuclear Regulatory Commission (NRC) will make an examination validation visit to your facility the week of May 27, 2025.
As agreed upon during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 12, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by January 24, 2025. The written examination outline was provided to your staff on July 2, 2024. The written examinations, operating tests, and supporting reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by April 9, 2025. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 55.40(b)(3), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready to use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.
To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests," your staff should retain the original simulator performance data (e.g., system pressures, temperatures,
D. Rhoades 2
and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) control number 3150-0090) at least 60 days before the first examination date (if possible). Contact T. Setzer, Chief Examiner, to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150-0090) and medical certifications (OMB control number 3150-0024) should be submitted at least 30 days before the first examination date. If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for receiving waiver or excusal requests call for at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by T. Setzer when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.
The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M), U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by email to Infocollects.Resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150-0018), Attn:
Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC, 20503; email: oira_submission@omb.eop.gov.
Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB control number.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the agencys Rules of Practice, a copy of this letter will be available electronically for public
D. Rhoades 3
inspection through the Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible on the NRCs website at http://www.nrc.gov/reading-rm/adams.html.
After you have been notified by the NRC Chief Examiner or Branch Chief that operator licenses have been issued, please direct any inquiries concerning a formal presentation of certificates to this office. Our goal is to have the operator certificates available for your celebration. At least one-month advance notice of your celebration arrangements would be appreciated to plan our senior manager attendance and process the certificates.
Thank you for your cooperation in this matter. M. Parlett and K. Swiger have been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact T. Setzer at (610) 337-5165 or me at (610) 337-5306.
Sincerely, Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety Docket Nos.
05000317 and 05000318 License Nos. DPR-53 and DPR-69 cc: Distribution via ListServ DONALD JACKSON Digitally signed by DONALD JACKSON Date: 2024.10.09 07:04:57 -04'00'
ML24283A001 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DORS/OB:CE RI/DORS/OB:OE RI/DORS/OB:BC NAME TSetzer/TCS BDyke/BD DEJackson/DEJ DATE 10/8/2024 10/8/2024 10/8/2024