Global Nuclear Fuel – Americas, L.L.C. – Inspection Schedule for Calendar Year 2025
ML24176A274
Person / Time
Site: 07001113
Issue date: 06/25/2024
From: Williamson R
NRC/RGN-II/DFFI/FFB1
To: Huth R
Global Nuclear Fuel
References
Download: ML24176A274 (3)


Text

Ryan Huth Facility Manager Global Nuclear Fuel - Americas, L.L.C.

P.O. Box 780, Mail Code J20 Wilmington, NC 28402

SUBJECT:

GLOBAL NUCLEAR FUEL - AMERICAS, L.L.C. - INSPECTION SCHEDULE FOR CALENDAR YEAR 2025 Ryan Huth:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Global Nuclear Fuel - Americas facility in calendar year 2025. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative or reactive inspections are not included in the schedule.

If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Leonard Pitts at (404) 997-4708 with any questions or concerns you may have regarding this letter or the inspection schedule.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert E. Williams, Jr., Chief Projects Branch 1 Division of Fuel Facility Inspection Docket No. 07001113 License No. SNM-1097

Enclosure:

As stated cc w/ encl: Distribution via LISTSERVJune 25, 2024 Signed by Williams, Robert on 06/25/24

ML24176A274 X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available

OFFICE RII/DFFI RII/DFFI RII/DFFI

NAME L. Pitts T. Vukovinsky R. Williams DATE 6/25/2024 6/25/2024 6/25/2024

2025 U.S. NUCLEAR REGULATORY COMMISSION INSPECTION/ACTIVITY PLAN FOR GLOBAL NUCLEAR FUEL - AMERICAS, L.L.C.

Dates Number of Description/Inspection Procedures (IPs)

Inspectors February 10 - 14 3 Nuclear Criticality Safety 1 (IP 88015)

Fire Protection (IP 88055)

TBD 1 Material Control and Accountability (MC&A)

Observation (Various IPs)

May 12 - 16 2 Operational Safety 1 (IP 88020)

July 14 - 18 2 MC&A (Various IPs)

July 21 - 25 2 Nuclear Criticality Safety 2 (IP 88015)

Environmental Protection (IP 88045)

October 6 - 10 2 Physical Security (Various IPs)

December 8 - 12 3 Operational Safety 2 (IP 88020)

Plant Modifications - Annual (IP 88070)

TBD 3 Emergency Exercise (88051)

Enclosure