MONTHYEARL-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations ML24120A1992024-04-29029 April 2024 Ile Form 5.1-1 Postexamination Check Sheet ML24120A2002024-04-0505 April 2024 Ile IP 21 Operator Licensing Exam Schedule ML24120A1982024-04-0505 April 2024 Ile Form 2.1-1 Examination Prep Checklist ML24120A1972024-04-0505 April 2024 Ile Form 1.3-1 Exam Security Agreement NRC 2024-0007, Ile Post-Exam Submittal Letter2024-03-18018 March 2024 Ile Post-Exam Submittal Letter ML24120A1572024-03-18018 March 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final ML24120A1702024-02-23023 February 2024 Ile Form 2.3-4 Written Examination Quality Checklist ML24120A1692024-02-23023 February 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 NRC-2024-0026, Ile Proposed Exam Submittal Letter2023-12-20020 December 2023 Ile Proposed Exam Submittal Letter ML24120A1552023-10-23023 October 2023 Ile Form 2.3-1 Outline Quality Checklist ML24120A1582023-10-0606 October 2023 Ile Proposed Outline Submittal Letter ML24120A1562023-10-0606 October 2023 Ile Form 3.4-1 Events and Evolutions Checklist - Draft ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 IR 05000266/20233012023-03-28028 March 2023 NRC Initial Examination Report 05000266/2023301 and 05000301/2023301 ML23038A2472023-03-24024 March 2023 Form 2.1-1 Point Beach February 13 2023 Exam Prep Checklist ML23199A2052023-03-24024 March 2023 Form 1.3-1 Examination Security Agreements NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter ML23199A1532023-02-0303 February 2023 Form 2.3-2 Operating Test Quality Checklist ML23199A1242023-02-0303 February 2023 Form 2.3-1 Examination Outline Quality Checklist ML23199A1552023-02-0303 February 2023 Form 2.3-4 Written Examination Quality Checklist ML23199A1282023-02-0303 February 2023 Form 3.4-1 Events and Evolutions Checklist ML23032A3232023-02-0202 February 2023 Operator Licensing Examination Approval - Point Beach Nuclear Plant, February 2023 ML22200A0282022-07-19019 July 2022 Confirmation of Initial License License Examination L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment ML21281A1202021-10-0808 October 2021 GFE Results, September 2021 IR 05000266/20213012021-09-14014 September 2021 NRC Initial License Examination Report 05000266/2021301; 05000301/2021301, and 07200005/2021301 ML21298A2202021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-403-1 ML21256A1322021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-201-2 ML21298A2212021-08-12012 August 2021 2021 Point Beach Initial License Exam Post-Exam Letter ML21256A1752021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-301-2 ML21293A3302021-08-12012 August 2021 2021 Point Beach Initial License Exam As-Administered Scenarios ML21264A1432021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-6 ML21293A3282021-08-12012 August 2021 2021 Point Beach Initial License Exam As-Administered JPMs ML21264A4612021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed Scenarios ML21264A1372021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-4 ML21264A1462021-08-12012 August 2021 2021 Point Beach Initial License Exam License Exam Submittal Letter ML21256A1802021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-D-1 ML21256A1392021-08-12012 August 2021 2021 Point Beach Initial License Exam Form Exam Outline Submittal Letter NRC 2021-0008 ML21293A3312021-08-12012 August 2021 2021 Point Beach Initial License Exam As-Administered Written Exam ML21298A1472021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-401-4 ML21264A4682021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed Written Exam Key ML21264A4072021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed JPMs ML21256A1572021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-301-1 ML21264A3562021-08-12012 August 2021 2021 Point Beach Initial License Exam ES-401-6 Written Examination Quality Checklist ML21298A2122021-08-12012 August 2021 2021 Point Beach Initial License Exam Exam Security Agreements ML21298A1552021-08-12012 August 2021 2021 Point Beach Initial License Exam Outline Review Comments and Resolutions ML21256A1672021-08-12012 August 2021 2021 Point Beach Initial License Exam ES-401-2 and ES-401-3 Outlines ML21298A1462021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-7 2024-07-11
[Table view] Category:Part 55 Examination Related Material
MONTHYEARL-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations ML24120A1992024-04-29029 April 2024 Ile Form 5.1-1 Postexamination Check Sheet ML24120A1982024-04-0505 April 2024 Ile Form 2.1-1 Examination Prep Checklist ML24120A2002024-04-0505 April 2024 Ile IP 21 Operator Licensing Exam Schedule ML24120A1972024-04-0505 April 2024 Ile Form 1.3-1 Exam Security Agreement NRC 2024-0007, Ile Post-Exam Submittal Letter2024-03-18018 March 2024 Ile Post-Exam Submittal Letter ML24120A1572024-03-18018 March 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final ML24120A1692024-02-23023 February 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24120A1702024-02-23023 February 2024 Ile Form 2.3-4 Written Examination Quality Checklist ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 NRC-2024-0026, Ile Proposed Exam Submittal Letter2023-12-20020 December 2023 Ile Proposed Exam Submittal Letter ML24120A1552023-10-23023 October 2023 Ile Form 2.3-1 Outline Quality Checklist ML24120A1582023-10-0606 October 2023 Ile Proposed Outline Submittal Letter ML24120A1562023-10-0606 October 2023 Ile Form 3.4-1 Events and Evolutions Checklist - Draft ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 IR 05000266/20233012023-03-28028 March 2023 NRC Initial Examination Report 05000266/2023301 and 05000301/2023301 ML23038A2472023-03-24024 March 2023 Form 2.1-1 Point Beach February 13 2023 Exam Prep Checklist ML23199A2052023-03-24024 March 2023 Form 1.3-1 Examination Security Agreements NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter ML23199A1282023-02-0303 February 2023 Form 3.4-1 Events and Evolutions Checklist ML23199A1242023-02-0303 February 2023 Form 2.3-1 Examination Outline Quality Checklist ML23199A1552023-02-0303 February 2023 Form 2.3-4 Written Examination Quality Checklist ML23199A1532023-02-0303 February 2023 Form 2.3-2 Operating Test Quality Checklist ML23032A3232023-02-0202 February 2023 Operator Licensing Examination Approval - Point Beach Nuclear Plant, February 2023 ML22200A0282022-07-19019 July 2022 Confirmation of Initial License License Examination L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment IR 05000266/20213012021-09-14014 September 2021 NRC Initial License Examination Report 05000266/2021301; 05000301/2021301, and 07200005/2021301 ML21298A1552021-08-12012 August 2021 2021 Point Beach Initial License Exam Outline Review Comments and Resolutions ML21293A3282021-08-12012 August 2021 2021 Point Beach Initial License Exam As-Administered JPMs ML21256A1322021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-201-2 ML21293A3302021-08-12012 August 2021 2021 Point Beach Initial License Exam As-Administered Scenarios ML21264A1462021-08-12012 August 2021 2021 Point Beach Initial License Exam License Exam Submittal Letter ML21264A4682021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed Written Exam Key ML21256A1752021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-301-2 ML21298A1472021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-401-4 ML21264A1292021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-3 ML21264A1372021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-4 ML21298A2122021-08-12012 August 2021 2021 Point Beach Initial License Exam Exam Security Agreements ML21264A1432021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-6 ML21298A2212021-08-12012 August 2021 2021 Point Beach Initial License Exam Post-Exam Letter ML21298A2142021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-201-1 ML21298A2202021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-403-1 ML21298A1462021-08-12012 August 2021 2021 Point Beach Initial License Exam Form ES-301-7 ML21264A4612021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed Scenarios ML21256A1572021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-301-1 ML21264A3562021-08-12012 August 2021 2021 Point Beach Initial License Exam ES-401-6 Written Examination Quality Checklist ML21264A4072021-08-12012 August 2021 2021 Point Beach Initial License Exam Proposed JPMs ML21256A1672021-08-12012 August 2021 2021 Point Beach Initial License Exam ES-401-2 and ES-401-3 Outlines ML21256A1802021-08-12012 August 2021 2021 Point Beach Initial License Exam Forms ES-D-1 ML21256A1392021-08-12012 August 2021 2021 Point Beach Initial License Exam Form Exam Outline Submittal Letter NRC 2021-0008 2024-07-11
[Table view] |
Text
Appendix D Scenario Outline Form ES-D-1 Facility: __Point Beach___ Scenario No.: ______1______ Op-Test No.: __2021__
Examiners: ___________________________ Operators: _____________________________
Initial Conditions: _Reactor power is 28% for flux mapping. G03, EDG is out of service due to ____
_to maintenance with G04, EDG aligned. 1LT-426, PZR Level transmitter (Red) removed from____
_service.________________________________________________________________________
Turnover:_Raise power to 50% at 15% per hour per OP 1C, Startup to Power Operations.________
Critical Tasks:_CT-24, Energize At Least One Emergency Bus _____________________________
_CT-25, Manually Start SW Pump For EDG Cooling______________________________________
Event Malf. Event Event No. No. Type* Description R-RO Normal Up Power 1 N-BOP N-SRO C-RO Single Dropped Rod 2 C-SRO TS-SRO 2019 Repeat C-BOP 1HC-478, SG B Atmospheric Steam Dump controller fails in auto, C-SRO valve fully opens, in manual will only close to 50%, requiring local 3 TS-SRO manual isolation valve operation New M-ALL Loss of All AC Power 4 A Train EDG success path C-BOP P-32A/B SW Pumps do not Auto Start after Restoration of 'A' Train C-SRO EDG 5
New C-RO Multiple (4) Stuck Rods Post Trip, requires boration 6 C-SRO 2017 Repeat
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor
Appendix D Scenario Outline Form ES-D-1 Facility: __Point Beach___ Scenario No.: ______2______ Op-Test No.: __2021__
Examiners: ___________________________ Operators: _____________________________
Initial Conditions: _0% power Mode 2. G02, EDG is OOS with G01, EDG is aligned, 1W-3A, ______
_Containment Shroud Fan OOS, 1PT-949, Containment Pressure transmitter removed from service.
Turnover:_A plant up power to the POAH is planned per OP 1B, Reactor Startup ________________
Critical Tasks:_CT-5, Manually Start At Least One Low-Head ECCS Pump _____________________
_CT-36, Transfer to Cold Leg Recirculation ______________________________________________
Event Malf. Event Event No. No. Type* Description R-RO Raise Power to POAH 1 N-BOP N-SRO C-BOP 1A06, 4160 Safeguards Bus Feeder Breaker trip - Does NOT auto C-SRO restore, needs to be manually restored.
2 TS-SRO NEW C-RO 1P-1B RCP thrust bearing failure/vibrations requiring manual C-SRO reactor trip (degradation of flow or a trip of the pump) 3 TS-SRO NEW C-RO Reactor Trip breakers fail to auto open and buttons on 1C04 are C-SRO unsuccessful (C01 still works) 4 2017 Repeat 5 M-ALL Design Basis LBLOCA C-RO 1P-10B RHR pump trips, 1P-10A RHR pump fails to auto start 6 C-SRO 2017 Repeat
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor
Appendix D Scenario Outline Form ES-D-1 Facility: __Point Beach___ Scenario No.: ______4______ Op-Test No.: __2021__
Examiners: ___________________________ Operators: _____________________________
Initial Conditions: _Reactor power is 47%. G03, EDG is out of service due to maintenance with ____
_G04, EDG aligned. 1LT-426, PZR Level transmitter (Red) removed from service _______________
Turnover:_Conduct an up power to 100% power at 15% per hour per OP 1C, Startup to Power_____
_Operations_______________________________________________________________________
Critical Tasks:_CT-3, Manually Actuate Containment Cooling ________________________________
_CT-17, Isolate Faulted SG___________________________________________________________
Event Malf. Event Event No. No. Type* Description C-RO Letdown inadvertently isolates, needs to be re-established 1 C-SRO NEW R-RO Inadvertent Turbine trip with no reactor trip 2 C-BOP R-SRO NEW C-RO Seismic event C-SRO 1P-11A, CCW pumps failure due to a mechanical failure requiring 3 TS-SRO pump shift 2019 Repeat M-ALL Seismic event causes multiple dropped rods, without an automatic 4 RX Trip C-BOP Steam Generator fault in containment upstream of the orifice 5 C-SRO NEW C-BOP Containment Spray fails to actuate 6 C-SRO 2017 Repeat
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor