Letter Sequence Supplement |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement
|
MONTHYEARML21057A0462021-02-19019 February 2021 License Amendment Request Decommissioning Technical Specifications Project stage: Request ML21084A2292021-03-17017 March 2021 Notification of Amended Post-Shutdown Decommissioning Activities Report Accordance with 10 CFR 50.82(a)(7), Revision 4 Project stage: Request ML21279A2782021-10-0505 October 2021 (TMl-2) - Request for Exemption from Record Retention Requirements Project stage: Request ML21354A0272021-12-15015 December 2021 Supplemental Letter to Three Mile Island Nuclear Station, Unit 2 (TMl-2) - Request for Exemption from Record Retention Requirements Project stage: Supplement ML21349A9102021-12-15015 December 2021 Registration of Use of Casks to Store Spent Fuel Project stage: Request ML22034A5592022-01-13013 January 2022 Response to Fort Calhoun Station, Unit No. 1 - Acceptance Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Supplemental Information (EPID L-2021-LIT-OOOO) Ml21350A02 Project stage: Supplement ML22038A9252022-02-0707 February 2022 TMI2 Accident Analysis Questions Project stage: Request ML22101A0792022-03-23023 March 2022 TMI2-EN-RPT-0001, Revision 1, Determination of the Safe Fuel Mass Limit for Decommissioning Project stage: Request ML22096A2212022-04-0606 April 2022 Application for Technical Specification Change Regarding Mode Change Limitations Using the Consolidated Line Item Improvement Process Project stage: Request ML22074A0242022-04-0707 April 2022 ISFSI Only Emergency Plan and Emergency Action Level Scheme Amendment No. 303 Project stage: Request ML22081A2292022-04-19019 April 2022 Issuance of Amendment 304 to Revise License Conditions and the Permanently Defueled Technical Specifications to Align Rqts for Permanent Removal of Spent Fuel from Spent Fuel Pool Project stage: Request RS-22-061, Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves2022-05-24024 May 2022 Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves Project stage: Request ML22167A0592022-06-16016 June 2022 Acceptance and Review Schedule Request Regarding Partial Exemption from Certain Record Retention Requirements Project stage: Other ML22199A2772022-07-15015 July 2022 E-mail Attachment: Federal Register Notice - Volume 87 Project stage: Other ML22199A2782022-07-15015 July 2022, 18 July 2022 State Consultation Proposed Conforming Amendment Related to Proposed Exemption Request from Certain Record Retention Requirements Project stage: Request ML22199A2762022-07-18018 July 2022 E-mail from A. Snyder, NRC, to B. Werner, PDEP, Regarding State Consultation Proposed Conforming Amendment Related to Proposed Exemption Request from Certain Record Retention Requirements Project stage: Other ML22196A3972022-09-16016 September 2022 Enclosure 3 - TMI-2 - Safety Evaluation Report for Partial Exemptions and Conforming Amendment from Certain Record Retention Requirements Project stage: Approval ML22196A3932022-09-16016 September 2022 Partial Exemption from Certain Record Retention Requirements and Conforming Amendment Project stage: Request ML22196A3952022-09-16016 September 2022 Enclosure 1 - Three Mile Island, Unit 2 - Partial Exemptions and Conforming Amendment from Certain Record Retention Requirements Project stage: Other ML22196A3942022-09-16016 September 2022 Letter - Letter to J. Sauger, TMI-2 Solutions, LLC, from A. Snyder, NRC - TMI-2 - Partial Exemption from Certain Record Retention Requirements and Conforming Amendment Project stage: Approval 2022-04-19
[Table View] |
|
---|
Category:Letter
MONTHYEARLIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24255A0962024-09-12012 September 2024 License Amendment Request to Revise the License Termination Plan - Request Supplemental Information (License No. DPR-40, Docket No. 50-285) ML24243A1042024-09-12012 September 2024 Proposed Revision to the OPPD FCS DQAP - Request for Additional Information (License No. DPR-40, Docket Nos. 50-285, 72-054, and 71-0256) IR 05000285/20240022024-08-21021 August 2024 NRC Inspection Report 05000285/2024002 ML24235A0822024-08-10010 August 2024 Response to Fort Calhoun Station, Unit No. 1 - Phase 1 Final Status Survey Report to Support Approved License Termination Plan - Request for Additional Information - Request for Additional Information (EPID L-2024-DFR-0002) July 8, 2024 ML24180A2082024-07-0808 July 2024 Phase 1 Final Status Survey Reports Request for Additional Information Letter ML24183A3222024-07-0808 July 2024 Proposed Revision to the Omaha Public Power District Fort Calhoun Station Decommissioning Quality Assurance Plan - Acceptance Review LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) IR 05000285/20240012024-06-0505 June 2024 NRC Inspection Report 05000285/2024001 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan ML24079A1702024-03-10010 March 2024 ISFSI, Unit 1 - 10 CFR 50.59 Report, Quality Assurance (QA) Program Changes, Technical Specification Basis Changes, 10 CFR 71.106 Quality Assurance Program Approval, Aging Management Review, Commitment Revisions and Revision of Updated Safe LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report ML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 ML23151A0032023-06-0505 June 2023 Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, Shpo; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commission'S Analysis of Omaha Public Power District'S Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1242022-08-0303 August 2022 Letter to Mr. Reggie Wassana, Governor, Cheyenne and Arapaho Tribes, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22101A1092022-08-0303 August 2022 Letter to Mr. Durell Cooper, Chairman, Apache Tribe of Oklahoma; Re., Ft Calhoun LTP Section 106 ML22138A1212022-08-0303 August 2022 Letter to Mr. Edgar Kent, Chairman, Iowa Tribe of Oklahoma, Re., Ft Calhoun LTP Section 106 2024-09-18
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML24289A2042024-10-0909 October 2024 Clarification Responses LIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 ML24235A0822024-08-10010 August 2024 Response to Fort Calhoun Station, Unit No. 1 - Phase 1 Final Status Survey Report to Support Approved License Termination Plan - Request for Additional Information - Request for Additional Information (EPID L-2024-DFR-0002) July 8, 2024 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information ML22034A5592022-01-13013 January 2022 Response to Fort Calhoun Station, Unit No. 1 - Acceptance Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Supplemental Information (EPID L-2021-LIT-OOOO) Ml21350A02 ML20202A6542020-07-16016 July 2020 Response for Fort Calhoun Station Fort Calhoun Station, Unit No. 1, Revised Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-18-0018, Independent Spent Fuel Storage Installation - Emergency Plan Update2018-04-18018 April 2018 Independent Spent Fuel Storage Installation - Emergency Plan Update ML18088B3782018-03-29029 March 2018 Response to Request for Additional Information Regarding Omaha Public Power District'S Decommissioning Funding Plan Update for Fort Calhoun Station Independent Spent Fuel Storage Installation ML17348A6232017-12-14014 December 2017 Response for Fort Calhoun Station Specific Questions and Concerns Regarding Omaha Public Power District'S Post-Shutdown Decommissioning Activities Report (PSDAR) LIC-17-0068, Reply to Final Request for Additional Information (RAI) for Fort Calhoun Exemption from 10 CFR 140.11 (a)(4), Off-site Primary and Secondary Liability Insurance (MF9664)2017-10-0404 October 2017 Reply to Final Request for Additional Information (RAI) for Fort Calhoun Exemption from 10 CFR 140.11 (a)(4), Off-site Primary and Secondary Liability Insurance (MF9664) LIC-17-0065, Submittal of Response to Request for Additional Information Re Fort Calhoun Request to Revise Their Technical Specifications to Align to Those Requirements for Decommissioning2017-09-26026 September 2017 Submittal of Response to Request for Additional Information Re Fort Calhoun Request to Revise Their Technical Specifications to Align to Those Requirements for Decommissioning ML17268A2212017-09-25025 September 2017 Response to Request for Additional Information (RAI) Regarding License Amendment Request 16-04 Revising Current Licensing Basis to Use Aci Ultimate Strength Requirements ML17264A7502017-09-21021 September 2017 Response to Request for Additional Information (RAI) License Amendment Request Regarding Removal of Dry Cask Loading Limits Fort Calhoun Station, Unit 1 Docket No.: 50-285 (MF9831) LIC-17-0054, Submission of Corrected Pages for Response to Request for Additional Information, Fort Calhoun Station, Unit No. 1 - Request for Additional Information Certified Fuel Handler Training Program2017-06-0606 June 2017 Submission of Corrected Pages for Response to Request for Additional Information, Fort Calhoun Station, Unit No. 1 - Request for Additional Information Certified Fuel Handler Training Program LIC-17-0047, Final Request for Additional Information Concerning License Amendment Request 16-07: Revise the Emergency Plan to the Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2017-05-15015 May 2017 Final Request for Additional Information Concerning License Amendment Request 16-07: Revise the Emergency Plan to the Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme LIC-17-0048, Response to Request for Additional Information Regarding the Fort Calhoun Station Request to Revise Technical Specifications to Align Staffing Requirements for Permanently Defueled Condition2017-04-27027 April 2017 Response to Request for Additional Information Regarding the Fort Calhoun Station Request to Revise Technical Specifications to Align Staffing Requirements for Permanently Defueled Condition LIC-17-0045, Response to Request for Additional Information Defueled Emergency Plan Exemption Request2017-04-20020 April 2017 Response to Request for Additional Information Defueled Emergency Plan Exemption Request LIC-17-0037, Response to Request for Additional Information, Fort Calhoun Station, Unit No.1 - Final Request for Additional Information Concerning Exemption from the Requirements of 10 CFR 50.47 and Appendix E2017-04-14014 April 2017 Response to Request for Additional Information, Fort Calhoun Station, Unit No.1 - Final Request for Additional Information Concerning Exemption from the Requirements of 10 CFR 50.47 and Appendix E LIC-17-0036, Supplemental Response to Request for Additional Information - Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment2017-04-0505 April 2017 Supplemental Response to Request for Additional Information - Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment ML17089A5442017-03-30030 March 2017 Response to Request for Additional Information Certified Fuel Handler Training Program LIC-17-0020, Response to Request for Additional Information, Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment2017-03-0303 March 2017 Response to Request for Additional Information, Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment ML17041A4442017-02-10010 February 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Fort Calhoun Station Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E (CAC No. MF9067). (Non-Proprietary)(Part 2 of 4) ML17041A4432017-02-10010 February 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Fort Calhoun Station Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E (CAC No. MF9067). (Non-Proprietary)(Part 1 of 4) LIC-17-0024, Supplemental Information Needed for Acceptance of Requested Licensing Action Fort Calhoun Station Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E (CAC No. MF9067). (Non-Proprietary)(Part 4 of 4)2017-02-10010 February 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Fort Calhoun Station Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E (CAC No. MF9067). (Non-Proprietary)(Part 4 of 4) LIC-16-0107, Final Response to the Request for Information, Per 10CFR50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident and Corresponding Commitments2016-11-18018 November 2016 Final Response to the Request for Information, Per 10CFR50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident and Corresponding Commitments LIC-16-0090, Response to Request for Additional Information Regarding Certified Fuel Handler Training Program2016-10-0707 October 2016 Response to Request for Additional Information Regarding Certified Fuel Handler Training Program LIC-16-0078, Revision to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report2016-09-14014 September 2016 Revision to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report ML16165A0282016-06-0909 June 2016 Response to NRC Request for Additional Information Revise Current Licensing Basis to Use American Concrete Institute Ultimate Strength Requirements LIC-16-0044, Calculation FC08499 Evaluation of FCS Concrete Compressive Strength Test Data2016-06-0101 June 2016 Calculation FC08499 Evaluation of FCS Concrete Compressive Strength Test Data LIC-16-0025, Ft. Calhoun, Unit 1 - Response to Request for Additional Information Adoption of TSTF-501, Revision 12016-04-0808 April 2016 Ft. Calhoun, Unit 1 - Response to Request for Additional Information Adoption of TSTF-501, Revision 1 LIC-16-0022, Response to NRC Request for Additional Information Revise Current Licensing Basis to Allow Use of Equipment Classification Methodology from ANSI/ANS-58.14-20112016-04-0808 April 2016 Response to NRC Request for Additional Information Revise Current Licensing Basis to Allow Use of Equipment Classification Methodology from ANSI/ANS-58.14-2011 ML16057A0742016-02-26026 February 2016 Response to Regulatory Information Summary (RIS) 2015-16, Planned Licensing Action Submittals for All Power Reactor Licensees. LIC-16-0001, Response to NRC Request for Additional Information Technical Specification Administrative Changes2016-01-27027 January 2016 Response to NRC Request for Additional Information Technical Specification Administrative Changes LIC-15-0147, Response to NRC Request for Additional Information Fifth Lnservice Testing Interval Relief Requests P-1 and P-22016-01-11011 January 2016 Response to NRC Request for Additional Information Fifth Lnservice Testing Interval Relief Requests P-1 and P-2 LIC-15-0139, ISFSI - Supplemental OPPD Response to NRC Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62015-12-0808 December 2015 ISFSI - Supplemental OPPD Response to NRC Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 ML15350A0182015-11-30030 November 2015 Transmittal of Response to Remaining Questions from NRC Request for Additional Information (RAI) Regarding Reactor Vessel Internal Component Aging Management Program ML15350A0192015-11-30030 November 2015 Enclosure 6, Response to Remaining Questions from NRC Request for Additional Information (RAI) Regarding Reactor Vessel Internal Component Aging Management Program. (Non-Proprietary) LIC-15-0129, Addendum to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report2015-11-0404 November 2015 Addendum to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report LIC-15-0121, ISFSI - Supplemental OPPD Response to NRC Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62015-11-0202 November 2015 ISFSI - Supplemental OPPD Response to NRC Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 LIC-15-0113, Response to Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2015-09-28028 September 2015 Response to Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation LIC-15-0115, ISFSI - Response to NRC Request for Clean Copy of Emergency Action Level Technical Basis Document2015-09-18018 September 2015 ISFSI - Response to NRC Request for Clean Copy of Emergency Action Level Technical Basis Document LIC-15-0102, Response to NRC Request for Additional Information Re License Amendment Request to Adopt Emergency Action Level Scheme Per NEI 99-01, Rev. 62015-09-11011 September 2015 Response to NRC Request for Additional Information Re License Amendment Request to Adopt Emergency Action Level Scheme Per NEI 99-01, Rev. 6 2024-08-10
[Table view] |
Text
~~
10 CFR 50.90 10 CFR 50.82 LIC-22-0001 January 13, 2022 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility License No. DPR-40 NRG Docket No. 50-285
Subject:
Response to Fort Calhoun Station, Unit No. 1 - Acceptance Review Of License Amendment Request To Add License Condition To Include License Termination Plan Requirements - Request For Supplemental Information (EPID L-2021-LIT-OOOO} Ml21350A026.
References:
- 1. Letter from OPPD (M. Fisher) to USNRC (Document Control Desk), "License Amendment Request (LAR) 21-01; Revised Fort Calhoun Station License to Add License Condition 3.0 to include License Termination Plan Requirements," dated August 3, 2021 (LIC-21-0005) (ML21271A178)
- 2. Letter from USNRC to OPPD, "Fort Calhoun Station, Unit No. 1 - Acceptance Review Of License Amendment Request To Add License Condition To Include License Termination Plan Requirements - Request For Supplemental Information (EPID L-2021-LIT-0000)," date December 16, 2021 (ML21350A026)
- 3. Letter from OPPD (T. Burke) to USN RC (Document Control Desk), "Certification of Permanent Removal of Fuel from the Reactor", dated November 13, 2016 (LIC-16-0074) (ML16319A254)
- 4. Letter from OPPD (M. Fisher) to USN RC (Document Control Desk), "Fort Calhoun Station, Unit No. 1, Post-Shutdown Decommissioning Activities Report",
dated March 30, 2017 (LIC-17-0033) (ML17089A759)
- 5. Letter from OPPD (M. Fisher) to USN RC (Document Control Desk),
"Fort Calhoun Station Irradiated Fuel Management Plan", dated March 31, 2017 (LIC-17-0031) (ML17093A594)
By letter dated August 3, 2021 (Reference 1), The Omaha Public Power District (OPPD) proposed an amendment to the 10 CFR Part 50 License for Fort Calhoun Station (FCS), Unit No. 1. The proposed amendment would revise the 10 CFR Part 50 License to reflect the requirements for control of the License Termination Plan (LTP) by adding License Condition 3.0.
By letter on November 13, 2016 (Reference 3), FCS provided certification of the permanent removal of fuel from the Reactor Vessel to the NRG in accordance with 10 CFR Part 50.82(a)(1 )(i) and (ii). On March 30, 2017 (Reference 4), FCS submitted the Post-Shutdown Decommissioning Activities Report (PSDAR) and on March 31, 2017(Reference 5), FCS submitted an updated Irradiated Fuel Management Plan (IFMP). ,A-- 0 D /
- Jtf/4 444 South 16th Street Mall* Omaha, NE 68102-2247
U. S. Nuclear Regulatory Commission LIC-22-0001 Page2 On December 16, 2021 (Reference 2), the NRC provided OPPD with Requests for Supplemental Information (RSI) regarding the proposed changes. Attachment 1 of this letter provides the responses to the RSI. Additionally, a DVD with the requested documents is also being included as an enclosure.
There are no regulatory commitments contained within this letter.
If you should have any questions regarding this submittal or require additional information, please contact Mrs. Andrea K. Barker -Regulatory Assurance and Emergency Planning Manager at (531) 226-6051.
Respectfully, r:DocuSigned by:
~:~~111~,~~
Timothy Uehling, Senior Director - Decommissioning TSU/akb/cac Attachment 1: Response to Request for Supplemental Information Enclosure 1: Reference Disc of Requested Documents c: S.A. Morris, NRC Regional Administrator, Region IV S. Helton, NRC Director, Division of Fuel Management J. D. Parrot, NRC Senior Project Manager C. D. Steely, NRC Health Physicist, Region IV Director of Consumer Health Services, Department of Regulation and Licensure, Nebraska Health and Human Services, State of Nebraska
ATTACHMENT 1 RESPONSE TO REQUEST FOR SUPPLEMENTAL INFORMATION REGARDING THE FORT CALHOUN STATION REQUEST TO ADD LICENSE CONDITION TO INCLUDE LICENSE TERMINATION PLAN REQUIREMENTS
- 1. Document Request- L TP Chapter 6, Reference 1 Chapter 6, Reference 1 is cited as the source of summary information in the L TP for numerical modeling intended to provide support for concentration results from RESRAD-ONSITE for the Basement Fill Model. However, Reference 1 of Chapter 6 - Haley &
Aldrich, "Hydrogeological Conceptual Site Model, Revision 4, Fort Calhoun Station, Blair, NE," 2021, was not a document included in the L TP submittal. Revision 2 of Reference 1 is specifically listed in the text of early parts of Chapter 6 and was December 16, 2021 included in the L TP submittal. Revision 2 contains a brief description of the conceptual site model along with summaries and data from field tests but does not contain any information on the numerical modeling performed using the interface, Groundwater Vistas, for MODFLOW, MODPA TH, and MT3DMS. A more complete description of the numerical modeling than provided in the L TP is needed for NRG staff to better understand the bounds and bases of the RESRAD-ONSITE results for the Basement Fill Model.
RSl-1 OPPD response:
Reference 1 to Chapter 6 of the LTP, which provides a comprehensive description of the numeric modeling utilized in the LTP, is included on the enclosed DVD in support of the FCS LTP. The document, "Hydrogeological Conceptual Site Model, Revision 5, Fort Calhoun Station, Blair, NE," has been revised to include the information the NRC has requested and is now Revision 5. The information is contained in Appendix F of the document. The revision did not result in a change to the LTP. '
- 2. Document Request- L TP Chapter 6, Reference 6 Multiple similarly titled reports on radionuclides of concern are cited in the L TP, with an explanation provided on pages 6-9. Some of these documents were also cited in Chapters 2 and 5. Chapter 6 Reference 6, Omaha Public Power District, "FC-18-002, Potential Radionuclides of Concern During the Decommissioning of Fort Calhoun Nuclear Station," was not a document provided in the submittal. However, two other, more recent, documents were provided along with the L TP submittal:
Chapter 6, Reference 7: Omaha Public Power District, "FC-20-007, Fort Calhoun Station Potential Radionuclides of Concern."
Chapter 6, Reference 8: Radiation Safety and Control Services, "FC-21-043, Radionuclides of Concern in Support of the Fort Calhoun License Termination Plan,"
2021.
Please provide Reference 6 for Chapter 6 or provide an explanation that the information in the latest report contains all the attributed information in the LTP (e.g., details on the suite of radionuclides for the initial sampling for decommissioning in Reference 6 are also included in Reference 8).
RSI 2 OPPD Response:
Reference 6 to chapter 6, "FC-18-002, Potential Radionuclides of Concern During the Decommissioning of Fort Calhoun Nuclear Station," is included on the enclosed DVD in support of the LTP. This document was the initial development of Radionuclides of Concern (ROC) in support of our partial site release in 2019. The other two documents mentioned in RSI #2 are similarly titled. FC-20-007 was developed to include additional ROC to those identified in FC-18-002. The information in the latest report, FC-21-043, is the final list of ROC using data from site characterization and it reflects removal of insignificant contributors. It contains all the attributed information in the LTP. FC-21-043 also provided the basis for DCGL development, as well as other inputs into the LTP.
The ROC referenced in the LTP are the final suite of nuclides to be used in the LTP, and the previous documents do not change the LTP in any way.
- 3. Clarification on Updated or Revised Documents As noted in the above specific examples, multiple revisions of, or similarly titled, reports are cited in the L TP. Clarification is requested on if there are other revisions or updates of referenced documents that the later revisions or updates contain cumulative information from the earlier reports, or only new information.
RSI 3 OPPD Response:
Revisions to the site specific documents referenced in the LTP are cumulative. This is aligned with the interim discussions FCS personnel and the NRC have had relating to this topic. The information contained in the LTP is consistent with the latest version of the similarly titled reports.
- 4. Data File Request - Subsurface Transport Modeling Please provide the input file sets used in Groundwater Vistas modeling to support results from RESRAD-ONSITE modeling for the Basement Backfi/1 Model.
RSI 4 OPPD Response:
The input files for Groundwater Vistas modeling are being sent via the agreed upon electronic method.
- 5. Data Request - Hydrologic Conditions NRG staff requests any historical groundwater level data and river stage measurements from the site that would reflect groundwater elevations near the river. Measurements of groundwater levels from June 2020 are stated in the L TP (pages 6-12) to be reflective of historical conditions at the site. The basis is stated to be the steady river stage levels typically between 10 and 15 feet over the past decade based on measurement stations
upstream (Decatur) and downstream (Omaha) of the site. The groundwater levels at the site are also stated to be in intimate hydraulic connection with the river (e.g., L TP Section 1.3.6). The hydrologic conditions at the site are used to support the representative and conservative groundwater levels and gradients used in RESRAD-ONSITE model. In addition, hydrologic conditions at the site may impact decommissioning activities (e.g.. , excavations, scans, and sampling) thus making the range of conditions expected at the site (e.g., seasonal) a concern given past flooding at the site and concurrent increases in groundwater levels with rising river stages.
RSI 5 OPPD Response:
The requested historical groundwater level data and river stage measurements are included on the enclosed DVD in support of the LTP.