MONTHYEARML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks ML23235A0602023-07-17017 July 2023 LTR-23-0194 Dwaine Perry, Chief, Ramapo Munsee Nation, Ltr Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23194A0442023-07-11011 July 2023 Clarification for Indian Point Energy Center License Amendment Request, Independent Spent Fuel Storage Installation Physical Security Plan ML23192A1002023-07-11011 July 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme ML23171B0432023-06-23023 June 2023 Letter - Indian Point Energy Center - Request for Additional Information for Independent Spent Fuel Storage Installation Facility-Only Emergency Plan License Amendment ML23118A0972023-06-0606 June 2023 06-06-23 Letter to the Honorable Michael V. Lawler, Et Al., from Chair Hanson Regarding Holtec'S Announcement to Expedite Plans to Release Over 500,000 Gallons of Radioactive Wastewater from Indian Point Energy Center Into the Hudson River ML23144A3512023-05-25025 May 2023 Clementina Bartolotta of Pearl River, New York Email Against Treated Water Release from Indian Point Site ML23144A3522023-05-25025 May 2023 Loredana Bidmead of New York E-Mail Against Treated Water Release from Indian Point Site ML23144A3412023-05-25025 May 2023 Dianne Schirripa of Rockland County, New York Email Against Treated Water Release from Indian Point Site ML23144A3472023-05-25025 May 2023 David Mart of Blauvelt, New York Email Against Treated Water Release from Indian Point Site ML23144A3402023-05-25025 May 2023 Melvin Israel of New York Email Against Treated Water Release from Indian Point Site ML23144A3542023-05-25025 May 2023 Terri Thal of New City, New York Email Against Treated Water Release from Indian Point Site ML23144A3532023-05-25025 May 2023 John Shaw of New York Email Against Treated Water Release from Indian Point Site 2024-01-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 May 13, 2021 Mr. Anthony J. Vitale Site Vice President Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, General Services Building P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
TERMINATION OF REACTOR OVERSIGHT PROCESS FOR INDIAN POINT NUCLEAR GENERATING UNIT 3 AND COMMENCEMENT OF DECOMMISSIONING INSPECTION PROGRAM
Dear Mr. Vitale:
This letter is to inform you that oversight activities by the U.S. Nuclear Regulatory Commission (NRC) at the Indian Point Nuclear Generating Unit 3 (IP-3) will no longer be performed in accordance with our operating power reactor inspection program. The NRCs oversight of your future activities at IP-3 will be conducted in accordance with our decommissioning power reactor inspection program and will be led by our Region I Division of Radiological Safety and Security (DRSS).
On February 8, 2017, Entergy Nuclear Operations, Inc. (Entergy) notified the NRC of its intent to permanently cease power operations at IP-3 by April 30, 2021 subject to operating extensions through, but not beyond 2025 (ADAMS Accession Number: ML17044A004). On May 11, 2021, Entergy notified the NRC of its certification of cessation of power operations and the permanent removal of fuel from the IP-3 reactor vessel (ADAMS Accession Number: ML21131A157). This letter is to notify you that the NRC will no longer use Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, IMC 0608, Performance Indicator Program, and IMC 2515, Light-Water Reactor Inspection Program - Operations Phase when conducting oversight activities and assessing site performance at IP-3. Therefore, it is also no longer necessary to report Reactor Oversight Process performance indicator data for IP-3. The results of inspection activities completed under IMC 2515 will be provided in future correspondence.
The NRCs oversight of your licensed activities as you progress through decommissioning will be conducted under the provisions outlined in IMC 2561, Decommissioning Power Reactor Inspection Program. The objectives of the decommissioning inspection program are to verify that decommissioning activities are being conducted safely, that spent fuel is safely being stored, and that site operations and license termination activities are in conformance with applicable regulatory requirements, licensee commitments, and management controls.
As defined in IMC 2561, IP-3 is currently in the Post-Operation Transition Phase of decommissioning and the inspections as detailed in IMC 2561, Appendix A, Core Inspection Procedures for that phase will be conducted at IP-3. In addition, the inspection procedures
A. Vitale 2 listed in IMC 2561, Appendix B, Discretionary Inspection Documents for Decommissioning Power Reactors could be performed based on site activities and conditions.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-6953 or Katherine Warner, Senior Health Physicist, at (610) 337-5389 with any questions you may have regarding this letter.
Sincerely, Digitally signed by Anthony M. Anthony M.
Dimitriadis Dimitriadis Date: 2021.05.13 11:19:51 -04'00' Anthony Dimitriadis, Chief Decommissioning, ISFSI, and Reactor HP Branch Division of Radiological Safety and Security Docket No: 05000286 License No: DPR-64 cc w/encl: Distribution via ListServ
3 TERMINATION OF REACTOR OVERSIGHT PROCESS FOR INDIAN POINT NUCLEAR GENERATING UNIT 3 AND COMMENCEMENT OF DECOMMISSIONING INSPECTION PROGRAM DATED MAY 13, 2021.
DOCUMENT NAME: https://usnrc.sharepoint.com/teams/Region-I-Decommissioning-Branch/Inspection Reports/Inspection Reports - Draft/Indian Point Unit 3 Transition Letter.docx SUNSI Review Complete: KWarner After declaring this document An Official Agency Record it will be released to the Public. ML21132A069 To receive a copy of this document, indicate in the box: C = Copy w/o attach/encl E = Copy w/ attach/encl N = No copy OFFICE DRSS/RI DORS/RI DRSS/RI NAME KWarner/kw DSchroeder/ds ADimitriadis /ad DATE 05/12/21 05/12/21 05/13/21 OFFICIAL RECORD COPY