Letter Sequence Approval | |
---|---|
EPID:L-2021-LLA-0011, Proposed License Amendment Request: Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A, Revision 1 (Approved, Closed) | |
Initiation Administration Questions
| |
MONTHYEARML20274A3292020-09-30030 September 2020
[Table View]Proposed License Amendment Request: Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A, Revision 1 Project stage: Request ML21007A2642021-01-0707 January 2021 Proposed License Amendment Request Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A, Revision 1 Project stage: Request ML21040A3872021-02-0808 February 2021 NRR E-mail Capture - Acceptance Review for Battery Resistance LAR Project stage: Acceptance Review ML21321A2622021-11-16016 November 2021 License Amendment Request to Revise Reactor Core Safety Limit Supplemental Information Project stage: Supplement ML21323A1742021-12-22022 December 2021 Issuance of Amendment Nos. 289 and 272 to Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A Project stage: Approval 2021-11-16 |
ML21323A174 | |
Person / Time | |
---|---|
Site: | North Anna |
Issue date: | 12/22/2021 |
From: | Geoffrey Miller Plant Licensing Branch II |
To: | Stoddard D Southern Nuclear Operating Co |
Miller G | |
References | |
EPID L-2021-LLA-0011, WCAP-17642-P-A | |
Download: ML21323A174 (16) | |
Similar Documents at North Anna | |
---|---|
Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024
[Table view]Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01 Category:License-Operating (New/Renewal/Amendments) DKT 50 MONTHYEARML23181A1352023-08-22022 August 2023
[Table view]Issuance of Amendment Nos. 295 and 278 License Amendment Request to Remove the Refueling Water Chemical Addition Tank and Change the Containment Sump Ph Buffer ML23072A0892023-05-0101 May 2023 (Amendments 346 & 286), North Anna 1 & 2 (Amnds 294 & 277), Surry 1 & 2 (Amnds 311 & 311), and Summer 1 (Amd 225) - Issuance of Amendments to Revise TSs to Adopt TSTF-554 Revise Reactor Coolant Leakage Requirements ML22095A1072022-07-11011 July 2022 Issuance of Amendment Nos. 120, 344, & 284, 293 & 276, & 307 & 307 to Relocate Requirements to the QAPD ML22068A0712022-03-22022 March 2022 Issuance of Amendment Nos. 292 and 275 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22041A0102022-03-0101 March 2022 V.C. Summer 1, Issuance of Amendment Nos. 283 (Millstone), 291 and 274 (North Anna), and 221 (Summer) to Revise TSs to Adopt TSTF-569 Revision of Response Time Testing Definition ML21323A1742021-12-22022 December 2021 Issuance of Amendment Nos. 289 and 272 to Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A ML21232A2172021-10-19019 October 2021 Issuance of Amendment Nos. 288 and 271 to Revise Technical Specifications Battery Surveillance Testing ML20325A0952021-03-19019 March 2021 Issuance of Amendment to Revise Technical Specifications to Allow Usage of a Small Break Loss of Coolant Accident Methodology (Non-Proprietary) ML20302A1792020-10-29029 October 2020 Non-Proprietary, Issuance of Amendment Nos. 286 and 269 to Revise Technical Specifications to Allow Usage of a Full Spectrum Loss of Coolant Accident Methodology ML20099F8732020-04-17017 April 2020 Audit Proposed License Amendment Request for the Addition of Westinghouse Topical Report WCAP-16996-P-A, Revision 1 (EPID L-2019-LLA-0243 and EPID L-2019-LLA-0236 ML19319A5832020-01-17017 January 2020 Issuance of Amendment Nos. 285 and 268 to Revise Technical Specifications Regarding Emergency Diesel Generator Maximum Voltage Limits ML19305D2482019-12-31031 December 2019 Issuance of Amendments Adoption of Emergency Action Level Schemes Per NEI 99-01, Rev. 6 ML19274C9982019-11-13013 November 2019 Issuance of Amendments Regarding Installation of Water Headers in Flood Protection Dike ML19238A1272019-09-12012 September 2019 Issuance of Amendment Nos. 282 and 265 to Revise Technical Specifications Regarding Open Phase Protection ML19031B2272019-02-27027 February 2019 Issuance of Amendment Nos. 281, 264, 294, and 294 to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes ML18290A8522018-11-27027 November 2018 Issuance of Amendments 280, 263 to Revise Technical Specifications Regarding Ventilation System Surveillance Requirements in Accordance with TSTF-522 ML18180A1972018-07-27027 July 2018 Issuance of Amendments to Revise Technical Specifications Regarding New and Spent Fuel Storage (CAC Nos. MF9712 and MF9713, EPID L-2017-LLA-0240) ML16252A4782016-10-17017 October 2016 Issuance of Amendments Revising Technical Specifications to Address the Issue Identified in Westinghouse NSAL-09-5, Revision 1, and NSAL-15-1, Revision 0 ML16013A4442016-02-22022 February 2016 (NAPS) - Issuance of Amendment for Changes to Technical Specification (TS) 3.8.1 - AC Sources, Operating Revised Surveillance Requirement ML15307A3002016-02-0202 February 2016 (NAPS) - Issuance of Amendments for Changes to the Emergency Action Level Revisions - Correction of Equipment Mark Number ML15245A4822015-10-0707 October 2015 Millstone Power Station, Surry Power Station, and North Anna Power Station - Issuance of Amendments to Revise the Cyber Security Milestone 8 Completion Date in the Renewed Facility Operating Licenses ML15187A4242015-07-27027 July 2015 Issuance of Amendments to Change the Reactor Coolant System Pressure and Temperature Limits Regarding Vacuum Fill Operations ML15133A3812015-06-16016 June 2015 Issuance of Amendments to Extended Type a Test Frequency to 15 Years ML15083A4362015-05-14014 May 2015 Issuance of Amendments Regarding Alternate Control Rod Position Monitoring ML14188C4532014-08-27027 August 2014 Issuance of Amendments Regarding Modification of Control Bank Sequence and Overlap Technical Specifications ML14169A3592014-08-12012 August 2014 Stations, Units 1 and 2, Issuance of Amendments Regarding Addition of an Analytical Methodology to the Core Operating Limits Reports and an Increase to the Surry Minimum Temperature for Criticality ML13186A1972013-09-25025 September 2013 Independent Spent Fuel Storage Installations - Issuance of Amendments for Changes to the Emergency Action Level Revisions ML13032A1542013-02-14014 February 2013 Issuance of Amendment for Temporary Change to Allow Two Inoperable Demand Position Indicators Per Control Bank ML13018A1402013-01-28028 January 2013 Issuance of Amendments to Adopt Technical Specification Task Force 510, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection ML12249A2992012-11-20020 November 2012 Issuance of Amendments to Eliminate the Steam Generator Water Level Low Coincident with Steam Flow/Feedwater Flow Mismatch Reactor Trip ML12054A1622012-02-29029 February 2012 Issuance of Amendments Regarding Addition of Analytical Methodology to Core Operating Limits Reports for the Critical Heat Flux Correlation (TACs ME4262 and ME4263) ML12054A1682012-02-29029 February 2012 Issuance of Amendments 267 & 248 Regarding Addition of Analytical Methodology to Core Operating Limits Report for Best Estimate Large Break Loss-of-Coolant Accident (TAC Nos. ME4933 and ME4934) ML11229A0632011-09-28028 September 2011 Issuance of Amendments Regarding Revision of Operability Requirements and Actions for Reactor Coolant System Leakage Detection Instrumentation ML11192A2492011-08-31031 August 2011 Issuance of Amendment Regarding Cyber Security to Dominion Plants ML1106011962011-04-14014 April 2011 Issuance of Amendments Regarding the Use of Optimized Zirlo Fuel Rod Cladding ML1031406572011-01-31031 January 2011 Issuance of Amendments to Adopt Technical Specification Task Force (TSTF) 425, Revision 3 for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program ML1032201142011-01-26026 January 2011 License Amendments, the Amendment Provides Authorization to Upgrade Selected Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Methodology for Development of Emergency Action Levels, Rev. 5... ML1010202472010-05-0404 May 2010 Issuance of Amendments to Adopt TSTF-427, Revision 2, to Add New Limiting Condition for Operation 3.0.9 Regarding Unavailability of Barriers ML0935004002010-03-0303 March 2010 Issuance of Amendments to Adopt TSTF-490, Revision 0, Regarding Deletion of E Bar Definition and Revision to Reactor Coolant System Specific Activity Using the Consolidated Line Item Improvement Process ML0922506162009-10-22022 October 2009 Units, 1 and 2, Issuance of Amendments 257 & 238 Regarding Measurement Uncertainty Recapture Power Uprate ML0919000072009-07-29029 July 2009 Issuance of Amendment to Eliminate Working Hour Restrictions from Technical Specifications to Support Compliance with 10 CFR Part 26, TSTF-511 ML0826201812008-10-0909 October 2008 Issuance of Amendments Nos. 253 & 234 Regarding LCO 3.8.7 and 3.8.9, Shared Components ML0815105622008-06-30030 June 2008 Issuance of Amendment Regarding One-Time 5-Year Extension to Type a Test Interval ML0726809452007-10-31031 October 2007 Issuance of License Amendments 252 and 232 Control Room Habitability, Using the Technical Specification Task Force Traveler, TSTF-448, Revision 3 ML0721902592007-10-17017 October 2007 Issuance of License Amendments 251 and 231 Technical Specification Change to Add Limiting Condition for Operation 3.0.8 on the Inoperability of Snubbers, Using the Consolidated Line Item Improvement Process, TSTF-372, Rev 4 ML0721400162007-08-0202 August 2007 Revised Pages of Facility Operating License Nos. NPF-4 and NPF-7 ML0707200432007-03-13013 March 2007 Units, 1 and 2, Issuance of License Amendments 250 and 230 Regarding Technical Specification Changes Per Generic Safety Issue (GSI) 191 ML0636000332006-12-28028 December 2006 Issuance of Corrected Page for Amendment Nos. 248 and 228 ML0634003072006-12-11011 December 2006 License Amendments 249 and 229 Regarding Diesel Fuel Oil Testing Program ML0629004582006-10-16016 October 2006 License Amendments 248 and 228 Regarding Consolidated Line Item Improvement Process for the Steam Generator Tube Integrity 2023-08-22 Category:Safety Evaluation MONTHYEARML23283A3052023-12-20020 December 2023
[Table view]Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23181A1352023-08-22022 August 2023 Issuance of Amendment Nos. 295 and 278 License Amendment Request to Remove the Refueling Water Chemical Addition Tank and Change the Containment Sump Ph Buffer ML23072A0892023-05-0101 May 2023 (Amendments 346 & 286), North Anna 1 & 2 (Amnds 294 & 277), Surry 1 & 2 (Amnds 311 & 311), and Summer 1 (Amd 225) - Issuance of Amendments to Revise TSs to Adopt TSTF-554 Revise Reactor Coolant Leakage Requirements ML21320A0072022-09-0707 September 2022 Review of Appendix E to DOM-NAF-2, Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code (EPID L-2021-LLT-0000) (Non-Proprietary) ML22196A1972022-07-28028 July 2022 Request for Relief Request N2-I4-LMT-004 Inservice Inspection Limitations ML22095A1072022-07-11011 July 2022 Issuance of Amendment Nos. 120, 344, & 284, 293 & 276, & 307 & 307 to Relocate Requirements to the QAPD ML22068A0712022-03-22022 March 2022 Issuance of Amendment Nos. 292 and 275 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22019A0022022-03-0808 March 2022 Regarding Request to Utilize Code Case OMN-28 ML22041A0102022-03-0101 March 2022 V.C. Summer 1, Issuance of Amendment Nos. 283 (Millstone), 291 and 274 (North Anna), and 221 (Summer) to Revise TSs to Adopt TSTF-569 Revision of Response Time Testing Definition ML21323A1742021-12-22022 December 2021 Issuance of Amendment Nos. 289 and 272 to Revise Reactor Core Safety Limit to Reflect WCAP-17642-P-A ML21232A2172021-10-19019 October 2021 Issuance of Amendment Nos. 288 and 271 to Revise Technical Specifications Battery Surveillance Testing ML21264A0112021-10-18018 October 2021 Safety Evaluation Report Related to the Subsequent License Renewal of North Anna Power Station, Units 1 and 2 ML21075A0452021-03-26026 March 2021 Request to Utilize Code Case N-885 ML20325A0952021-03-19019 March 2021 Issuance of Amendment to Revise Technical Specifications to Allow Usage of a Small Break Loss of Coolant Accident Methodology (Non-Proprietary) ML20364A0402021-01-15015 January 2021 Request for Relief Request N1-I4-LMT-003 Inservice Inspection Limitations ML20350B8062020-12-28028 December 2020 Request for Relief Request N1-I5-NDE-002 Inservice Inspection Alternative ML20302A1792020-10-29029 October 2020 Non-Proprietary, Issuance of Amendment Nos. 286 and 269 to Revise Technical Specifications to Allow Usage of a Full Spectrum Loss of Coolant Accident Methodology ML20253A3292020-09-30030 September 2020 Revised License Renewal Commitment Pressurizer Surge Line Weld Inspection Frequency ML20252A0042020-09-23023 September 2020 Request for Relief Request Fifth 10-Year Interval ML20252A0072020-09-15015 September 2020 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI ML20031E7842020-02-19019 February 2020 Request for Relief Request P-9 to Defer Performance of Comprehensive Pump Test ML19319A5832020-01-17017 January 2020 Issuance of Amendment Nos. 285 and 268 to Revise Technical Specifications Regarding Emergency Diesel Generator Maximum Voltage Limits ML19305D2482019-12-31031 December 2019 Issuance of Amendments Adoption of Emergency Action Level Schemes Per NEI 99-01, Rev. 6 ML19274C9982019-11-13013 November 2019 Issuance of Amendments Regarding Installation of Water Headers in Flood Protection Dike ML19238A1272019-09-12012 September 2019 Issuance of Amendment Nos. 282 and 265 to Revise Technical Specifications Regarding Open Phase Protection ML19143A3422019-05-29029 May 2019 Inservice Inspection Alternative Request N2-I4-LMT-003 ML19140A2882019-05-28028 May 2019 Inservice Inspection Alternative Requests N1-I5-CMP-001 and N2-I5-CMP-001 ML19135A3242019-05-21021 May 2019 Inservice Inspection Alternative Request N1-I4-CS-002 ML19093B2742019-04-15015 April 2019 Inservice Inspection Alternative Requests N1-I5-SPT-001 and N2 I5 Spt 001 ML19092A4172019-04-15015 April 2019 Unit Nos.1 and 2 Inservice Inspection Alternative Requests N1-I5-NDE-001 and N2 I5 NDE 001 ML19031B2272019-02-27027 February 2019 Issuance of Amendment Nos. 281, 264, 294, and 294 to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes ML19039A2362019-02-14014 February 2019 Inservice Inspection Alternative N2-I4-NDE-007 ML18290A8522018-11-27027 November 2018 Issuance of Amendments 280, 263 to Revise Technical Specifications Regarding Ventilation System Surveillance Requirements in Accordance with TSTF-522 ML18225A0202018-08-29029 August 2018 ISFSI; North Anna 1 & 2 Isfsls, and Unit 3; Surry Power 1 & 2, and Isfsls); Dominion Energy Kewaunee, Inc. (Kewaunee Power Station and Isfsi): Request for Threshold Determination Under 10 CFR 50.80 ML18180A1972018-07-27027 July 2018 Issuance of Amendments to Revise Technical Specifications Regarding New and Spent Fuel Storage (CAC Nos. MF9712 and MF9713, EPID L-2017-LLA-0240) ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) ML18029A1842018-02-0202 February 2018 Proposed Inservice Inspection Alternatives N1-I4-NDE-010 and N2-I4-NDE-005 (CAC Nos. MF9534 and MF9535; EPID L-2017-LLR-0029) ML18019A1952018-01-24024 January 2018 Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination (CAC Nos. MF9923, MF9924, MF9925, MF9926, MF9927, and MF9928; EPID L-2017-LLR-0060) ML18005A1092018-01-10010 January 2018 Relief Request (RR) N1-I4-LMT-002, Limited Coverage Examinations for the Fourth Ten-Year Inspection Interval (CAC No. MF9689; EPID L-2017-LLR-0024) ML17332A0782017-12-12012 December 2017 ISFSI; Millstone and ISFSI; North Anna and ISFSI; Surry and ISFSI - Request for Approval of Revision 24 of the Nuclear Facility Quality Assurance Program Description Topical Report, DOM-QA-1 (CAC Nos. MF9732-MF9739; EPID L-2017-LLQ-0001) ML17332A6632017-12-0606 December 2017 Proposed Inservice Inspection Alternatives N1-I4-NDE-009 and N2-I4-NDE-004 (CAC Nos. MF9298 and MF9299; EPID L-2016-LLR-0018) ML17221A2522017-08-17017 August 2017 Proposed Alternative to Implement Code Case N-839 ML17053A2432017-07-21021 July 2017 Relief Request (RR) N1-I4-NDE-008, and N2-I4-NDE-003 Inservice Inspection Program ML17046A3162017-04-0606 April 2017 Connecticut, Virginia, Millstone, North Anna, Surry, Submission of Revision 21 of the Quality Assurance Topical Report for NRC Approval and Submission Revision 22 for Information Only (CAC Nos. MF8128 - MF8234) ML16252A4782016-10-17017 October 2016 Issuance of Amendments Revising Technical Specifications to Address the Issue Identified in Westinghouse NSAL-09-5, Revision 1, and NSAL-15-1, Revision 0 ML16209A4132016-07-27027 July 2016 Safety Evaluation For North Anna Power Station, Units 1 And 2, Proposed License Amendment To Revise The Technical Specifications To Address The Issue Identified In Westinghouse Documents NSAL-09-5. Rev. 1 and NSAL-15-I (TAC No. MF7186 and MF7187) ML16028A4342016-03-0101 March 2016 Relief Request (RR) N1-I4-SPT-006, Inservice Inspection Program ML16013A4442016-02-22022 February 2016 (NAPS) - Issuance of Amendment for Changes to Technical Specification (TS) 3.8.1 - AC Sources, Operating Revised Surveillance Requirement ML15307A3002016-02-0202 February 2016 (NAPS) - Issuance of Amendments for Changes to the Emergency Action Level Revisions - Correction of Equipment Mark Number 2023-08-22 |