ML20245B694
ML20245B694 | |
Person / Time | |
---|---|
Site: | 05000605 |
Issue date: | 06/16/1989 |
From: | Chris Miller Office of Nuclear Reactor Regulation |
To: | Marriott P GENERAL ELECTRIC CO. |
References | |
2.206, NUDOCS 8906260026 | |
Download: ML20245B694 (3) | |
Text
-_--______
June 16, 1989 !
Docket No. STN 50-605 Mr. Patrick W. Harriott, Manager Licensing & Consulting Services GE Nuclear Energy .
General Electric Company 175 Curtner Avenue San Jose, California 95125
Dear Mr. Marriott:
Enclosed for your information are. copies of a Director's Decision, letter of transmittal 'and Federal Register notice issued by- the Director, Office of Nucle 4r Reactor Regulation (Director) in response to a Petition filed under 10 CFP 2.206 of the Commission's regulations. The Petition was filed by Ms. Susan Hiatt on behalf of the Ohio Citizens for Responsible Energy (OCRE).
The Petitioner expressed concerns regarding the March 9,1989 power oscillation event at LaSalle, Unit 2 and requested that the Director and Commission take ;
specified action with respect to all boiling water reactors. As discussed in .
the enclosed Director's Decision, the Petitioner's request under 10 CFR 2.206 has been denied. However, the Petitioner's request to reopen rulemaking proceedings regarding Anticipated Transients Without Scram (ATWS) is being treated as a petition for rulemaking under 10 CFR 2.802 of the Commission's !
regulations. '
Pleasecontactmeat(301)492-1118 if you have any questions on this issue.
Sincerely, original signed by Charles L. Biller, Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation
Enclosures:
- 1. Letter dated April 27, 1989 to Ms. Susan L. Hiatt
- 2. Director's Decision dated April 27, 1989
- 3. Federal Register Notice dated April 27, 1989 cc w/ enclosures:
See next page DISTRIBUTION:
1DocRet File 3 NRC PDR" rg DScaletti 8906260026 890616 ['
PDSNP Reading paa ADoCK 05000605 j EHylton A PDC ,.
( 74- 3 LA ffP PMP0g(P g D:PDSNP Ef n DSca'letti:cw CMiller 06/q/89 06/(/89 06//6 /89
V k
+ o UNITED STATES
=
g {
E n NUCLEAR REGULATORY COMMISSION l W ASHINGTON, D. C. 20555
, h 1 June 163 1989
%, . . . . . .o#
l Docket No. STh 50-605 l
i, Mr. Patrick W. Marriott, Manager i Licensing & Consulting Services !
GE Nuclear Energy l General Electric Company i 175 Curtner Avenue San Jose, California 95125 q i
l
Dear Mr. Marriott:
4 Enclosed for your information are copies of a Director's Decision, letter of l transmittal and Federal Register notice issued by the Director, Office of i NucleerReactorRegulation(Director)inresponsetoaPetitionfiledunder 10 CFR 2.206 of the Commission's regulations. The Petition was filed b Ms. Susan Hiatt on behalf of the Ohio Citizens for Responsible Energy (yOCRE).
The Petitioner expressed concerns regarding the March 9,1989 power oscillation event at LaSalle, Unit 2 and requested that the Director and Comission take specified action with respect to all boiling water reactors. As discussed in the enclosed Director's Decision, the Petitioner's request under 10 CFR 2.206 3 has been denied. However, the Petitioner's request to reopen rulemaking i proceedingsregardingAnticipatedTransientsWithoutScram(ATWS)isbeing- l treated as a petition for rulemaking under 10 CFR 2.802 of the Commission's
! regulations.
Please contact me at (301) 492-1118 if ycu have any questions on this issue. ;
i Sincerely, Chd,/n1b.
Charles L. Miller, Director-Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects - III, IV, i V and Special Projects '.
Office of Nuclear Reactor Regulation
Enclosures:
- 1. Letter dated April 27, 1989 ,
to Ms. Susan L. Hiatt j
- 2. Director's Decision dated April 27, 1989 :
- 3. Federal J Re ister Notice
~ doted AprTTP7,1989 cc w/ enclosures:
See next page l
Mr. P. W. Marriott- Docket No. STN 50-605 General Electric Company l
cc: Mr. Robert Mitchell General Electric Company 175 Curtner Avenue San Jose, California 95114-Mr. L. Gifford, Program Manager J Regulatory Programs GE Nuclear Energy 12300 Twinbrook Parkway Suite 315 Rockville, Maryland 20852 1 ll Director, Criteria & Standards Division f Office of Radiation Programs U. S. Environmental Protection Agency j]
401 M Street, S.W.
Washington, D.C. 20460 Mr. Daniel F. Giessing Division of Nuclear Regulation and Safety Office of Converter Reactor Deployment, NE-12 !
1 Office of Nuclear Energy Washington, D.C. 20545 s
1 I
.-___m____.- ___
( l
,', - ENCLOSURE 1
/,,a ncy% UNITED STATES
, ? ,. ~j NUCLE AR REGULATORY COMMISSION WASHtNGTON, D. C. 20666 j p k..../ a April 27, 1989 y Ms. Susan L. Hiatt Representative of Ohio Citizens for Responsible Energy. Inc.
8275 Munson Road Mentor, Ohio 44060 1
Dear Ms. Hiatt:
1 This letter is in further response to your Petition of July 22, 1988 requesting that the Director, Office of Nuclear Reactor Regulation (NRR), take Imediate action with respect to boiling water reactors (BWRs) to relieve what you allege to be undue risks to the public health and safety posed by the themal-hydraulic
' instability of BWRs as revealed by an event at LaSalle County Station, Unit 2, ,
on March 9, 1988. I 1
On August 26, 1988, I infcrmed you that your request for imediate relief was I denied because the alhgations that form the basis for your Petition did not I reveal any new operational safety issue that posed an imediate safety concern ;
for continued BWR operation.. I also informed you that your Petition was being i treated under 10 CFR 2.206 of the Jomission's regulations and that appropriate action, that is, a formal decision, would be taken within a reasonable time.
For the reasons set forth in the enclosed Director's Decision under 10 CFR 2.206, your Petition has been denied. However, cs discussed below, your request to reopen rulemaking proceedings regarding anticipated transients without scram (ATWS) is being treated as a Petition for rulemaking under 10 CFR 2.80" f the j Comission's regulations. A copy of the Decision will be filed with t..e Secretary ,
of the Comission for the Comission's review in accordance with 10 CFR 2.206. 4 The Decision will constitute final action of the Commission 25 days after the cate of issuance unless the Comission, on its own motion, institutes a review of the Decision within that time. ,
In the August 26, 1988 letter, I acknowledged your request to reopen rulemaking proceedings regarding ATWS as part of the relief requested. However, since that time, I have determined that this' request is more properly treated as.a petition for rulemaking under 10 CFR 2.802 of the Comission s regulations. As such, it has been referred to the NRC Office of Research for appropriate action. However. ,
it is important to note that both the NRC and BWR Owners Group (BWROG) currently l
~
have programs in which analyses of ATWS conditions are being conducted. These analyses treat large amplitude power oscillations with state-of-the-art analytical methods. The results of these analyses to date confirm the technical bases for the current ATWS rule. Consequently, at this time, the NRC staff sees no basis for recommending that the Comission reopen rulemaking proceedings regarding ATWS.
If, however, the staff finds evidence which contradicts the assumptions and results of previous ATWS analyses from either the information you provided in support of thenyour bePetition or new appropriate forinformation from ongoing the Comission NRC and to reconsider BWROGATWS the current programs,le.it ru may y /W0&Y ~
~
l
. i 4
I Susan L. Hiatt For your information, I am enclosing a copy of Supplerent I to NRC Bulletin No. SS-07, " Power Oscillations in Boiling Water Reactors", which is referenced i in the Director's Decision. I am also enclosing a copy of the notice regarding !
this Decision that was filed with the Office of the Federal Register for i publication. I 1
Sincerely, I i
1[
Thomar E. Murley Office of Nuclear, Director Reactor Regulation
Enclosures:
- 1. Director's Decision
- 2. Federal Recister Notice
- 3. NRC Eulletin No. 88-07, Supplement 1 .
l l
4 i
j i
..'. ENCLOSURE 2 l 1
DD-89-03 I UNITED STATES OF AMERICA i
NUCLEAR REGULATORY COMMISSION 0FFICE OF NUCLEAR REACTOR REGULATION Thomas E. Murley, Director In the Matter of BOSTON EDISON CD. (Pilgrim Nuclear Power Station, Docket No. 50-293) 1 CAROLINA POWER & LIGHT CO. (Brunswick Station, Units 1 and 2, Docket Nos. 50-324 )
and 50-325) 1 CLEVELAND ELECTRIC ILLUMINATING CO., ET AL. (Perry Nuclear Power Plant, Unit 1, Docket No. 50-440)
COMMONWEALTH EDISON CO. (Dresden Nuclear Power Plant, Units 2 and 3, Docket Nos. '
50-237 and 50-249), (Quad Cities Nuclear Power Plant, Units 1 and 2. Docket Nos. l
. 50-254 and 50-265), (LaSalle County Station, Units 1 and 2, Docket Nos. 50-373 and 50-374)
CONSUMERS POWER CO. (Big Rock Point, Docket No. 50-155)
DETROIT EDISON CO. (Fermi Unit 2., Docket No. 50-341) i l
GENERAL PUBLIC UTILITIES (Oyster Creek Station, Docket No. 50-219)
GEORGIA POW'ER CO. (Hatch Nuclear Power Plant, Units 1 and 2, Docket Nos. 50-321 and 50-366)
GULF STATES UTILITIES CO. (River Bend Station, Docket No. 50-458)
ILLINDIS POWER CO. (Clinton Nuclear Power Plant, Docket No.' 50-461)
IOWA ELECTRIC LIGHT & POWER CO. (Duane Arnold Nuclear Power Plant, Docket No. 50-331)
LONGISLANDLIGHTINGCO.(ShorehamNuclearPowerPlant,DocketNo.50-322)
MISSISSIPPIPOWER&LIGHTCO.(GrandGulfNuclearStation,DocketNo.50-416)
NEBRASKA PUBLIC POWER DISTRICT (Cooper Station, Docket No. 50-298)
NIAGARA MOHAWK F0WER CORP. (Nine Mile Point Units 1 and 2, Docket Nos. 50-220 and50-410)
NORTHEASTUTILITIES(MillstoneUnit1,DocketNo.50-245) l l
g5v { g i W 5 ('/
f.CF.THERfi STATES POWER CO. (Monticello fluclear Power Plant, Docket No. 50-263)
PEtifiSYLVAfilA POWER & LIGHT CO. (Susquehanna Steam Electric Station, Units 1 and 2,.
Docket fics. 50-387 and 50-388)
PHILADELPHIA ELECTRIC CO. (Peach Bottom Nuclear Station, Units 2 and 3, Docket Nos.
50-277 and 50-278), (Limerick Nuclear Power Plant, Unit 1, Docket No. 50-352)
POWER AUTHORITY OF THE STATE Of tiEW YORK (James A. Fitzpatrick Station, Docket No. 50-333)
PUBLIC SERVICE ELECTRIC & GAS CO. (Hope Creek Generating Station, 1 Docket No. 50-354)
TENfiESSEE VALLEY AUTHORITY (Browns Ferry Nuclear Station, Units 1, 2, and 3, i
- Docket tios. 5C-259, 50-260, and 50-296)
VERM0f;T YAfiKEE NUCLEAR POWER CORP. (Vermont Yankee Nuclear Power Plant, )
Docket No. 50-271)
WASP!!!GT0fi FLELIC POWER SUPPLY SYSTEf4 (WNP Unit 2, Docket No. 50-397)
DIRECTOR'S DECISION UNDER 10 CFR 2.206
- 1. INTRODUCTION Cn July 22, 1988, Ms. Susan Hiatt, on behalf of Ohio Citizens for Responsible Energy, Inc., (Petitioner) filed a Petition in accordance with 10 CFR 2.2C6 with the !!uclear Regulatory Commission (NRC). The petition was referred to the Director, Office of Nuclear Reactor Regulation (NRR) for consideration.
. The Petition asked the Director, NRR, to take imediate action to relieve alleged undue risks to the publi. health and safety posed by the thermal-hydraulic instability of boiling-water reactors (BWRs), as revealed by the power oscil-lation event at LaSalle Unit 2 on March, 9 1988 (LaSalle Event). The Petitioner specifically requested the NRC to order all dWR licensees to (1) place their reactors in cold shutdown, (2) develop and implement specified operating procedures relating to the thermal-hydraulic instability issues, (3) demonstrate
'l 4 .
)
1 i
l j
i that certain specified training has been provided relating te these procedures, j (t) demerstrate the capability of instrumentation related to power esci11ations, (5) cevelop simulators capable of modeling power oscillations similar to those
' occurring at LaSalle as well as out-of-phase power esc 111ations, (5) report to the NRC all past and future incidents in which recirculation pumps have tripped I off, (7) submit to the NRC justification for continued operation of BWRs, and a l
(8) submit a report to the NRC within 1 year demonstrating compliance with.
Criterion 12 given in 10 CFR Part 50, Appendix A (GDC-12)I . .In addit' ion, the i'
Petitier.er requested the Comission to reopen Generic Issues B-19 and B-59, to reopen the Anticipated Transients Without Scram (ATWS) rulemaking proceeding, and to reconsider the use of the end-of-cycle recirculation pump trip on SWRs.
Ms. Hiatt alleged as grounds for the Pet'ition that the LaSa11it Event has serious safety implications fcr all BWRs and that the Nuclear Regulatory Ccr.rission (NRC) has failed to take appropriate regulatory action in response to the LaSalle Event. In the Petition, Ms. Hiatt cites the following postulated i safety implications, some of which had been previously identified in several ,
referenced documents attached to the Petition: (1) decay ratios determined by licensing calculations are not reliable indicators of core stability (Attachment 2 to Petition) and design analyses of the reactor cannot be relied upon to ensure that esci11ations are not possible in BWRs; (2) The General Electric (GE) Company's guidance for operations provided in Service Information Letter (SIL) 380, Revision 1, is inadequate to ensure compliance with 00C-12 ( Attachment 4 to Petition); and (3) BWR plant instrumentation may 10 CFR Part 50, Appendix A," Criterion 12. " Suppression of Reactor Power Oscillations," states that: The reactor core and essociated coolant, control, and protection systets shall be designed to assure that power oscillations which can result in conditions exceeding specified acceptable fuel design iimits are not possible or can te reliably and readily detected and suppressed."
n .
4 not detect power esci11ations if they occur out of phase or too rapidly (Attachments 1 and 4 to Petition). Ms. Hiatt then asserts that (1) given the implications of the LaSalle Event, the actions requested of BWR licensees in NRC Bulletin No. 88-07 are insufficient, (2) most, if not all BWRs, are in a stile of noncompliance with GDC-12, and (3) the NRC must take aggressive enforcement action to protect the health and safety of the public.
On August 26, 1988, I acknowledged receipt of the Petition. I informed Ms. Hiatt that (1) her request for imediate relief was denied because the allegations that formed the basis for the Petition did not reveal any new operational safety issues that posed an imediate safety concern for continued BWR operation, k ) the Petition would be treated under 10 CFR 2.206 of the Commission's regulations, and (3) appropriate action would be taken within a reasonable amount of time. For reasons discussed below, the Petition is denied.
Ms. Hiatt's request to reopen rulemaking proceedings regarding ATWS is being l treated separately as a petition for rulemaking under 10 CFR 2.802 of the Comission's regulations.
II. BACKGROUND The LaSalle nuclear power station, operated by the Commonwealth Edison Company (CECO), is a two-unit site located 11 miles southeast of Ottawa, ,
Illinois. Both units utilize General Electric-designed BWR/5 reactors with containments of the Mark 11 design.
On March 9, 1988, LaSalle Unit 2 underwent a dual recirculation pump trip event that resulted in a loss of forced circulation cooling, a reduction in
4
)
reacter power, and a decrease in reactor inlet feedwater temperature. I Approximately 6 minutes af ter the recirculation pump trip, with the reactor j being cooled via natural circulation, operators observed that the average power rarge monitor (ApRM) indications were oscillating between 25 and 50 percent power (25 percent peak to peak) every 2 to 3 seconds. At the same time, the local power range monitor (LpRM) downscale alarms began to annunciate 1 and clear, indicating that peer was oscillating about the downscale alarm l
setpcint. During this period, the operators recognized that they were operating in a regicn of core instabi,11ty. They attempted to restart a recirculation pump in order to increase flow to prevent instability, but this action was unsuccessful as All of the pump start permissive conditions had not been s a tisfied. (Permissives are protective features designed to inhibit start-up of equipent when certain specified conditions critical to proper functioning of
]
the equipr.ent are not within specified limits). Approximately 7 minutes after the recirculation pump trip, as operators were preparing to perform a manual scrac, the reactor scrammed automatically because of high neutron flux in the ,
i reactor. (A reactor scram involves rapid insertion of shutdown and control rods !
by either manual or automatic actuation of the reactor protection system). l l The scram shut the reactor down, and recovery from the scram proceeded normally.
l l On March 16, 1988, after receiving additional information from the '
licensee concerning the event, the NRC dispatched an augmented inspection team
( AIT) to the site. The AIT completed its inspection on March 24, 1988, and issued its inspection report on May 6,1988. TheAITconcludedthat(1) fuel design limits had not been exceeded during the transient, and fuel damage had not occurred; (2) plant equipment functioned as designed; and (3) operator actions during the event were within the bounds of their procedures and training,
. 1 f
i
]
I but the procedures and training program themselves were inadequate. The AIT also identified a number of generic technical concerns and recommended that they be considered further by the staff.
On June 8,1988, the NRC Office for Analysis and Evaluation of Operational Data (AEOD) issued a special report documenting its concerns regarding the power oscillation event at LaSalle 2 and its recommendations for follow-up action.
A response to the recommendations was provided to AEOD by NRR on June 24, 1988.
On June 15, 1988, following completion of its evaluation of the March 9, 1988, event at LaSt.11e, the NRC issued Bulletin No. 88-07 to holders of operating licenses and construction permits for BWRs. The bulletin requested that recipients take action to ensure that adequate operating procedures and instrumentation are avail-able and adequate operator training is provided to prevent the occurrence of power oscillations during all modes of BMR operation.
The bulletin required that recipients confirm oy letter to the NRC that the requested actions were completed and implemented. All confirmation letters have )
been received and reviewed. They indicate that:
- 1. All EWR licensees have procedures in place to detect and suppress instability regardless of the value of previously calculated decay ratios;
- 2. All licensed reactor operators and shift technical advisors were briefed regarding the LaSalle Event within 15 days following receipt of the bulletin, or before resuming shift duties if they had been unavailable during the 15 day period;
- 3. All action to modify operating procedures and the operator training I
program with respect to detection and suppression of potential reactor instabilities had been completed or would be completed before 1
L___.____ _ _ _ _ ._ __
4 a l
7 startup from the current outage and, in a few cases, no later than December 15, 1988; and, 4 All licensees have confirmed that instrumentation relied upon by plant operators to execute operating procedures is adequate based on.an assessment by the equipment vendor (GE) and a review of any modifi-cations made to equipment since installation.- I The staff has begun to audit licensee responses to the bulletin in-more detail. .
The audits will continue over the next year.
In November 1968, General Electric Company'(GE),- working with the BWR- i
~
Owners' Group (BWROG), issued a letter entitled " Interim Recommendations for Stability Actiers" to the BWR licensees. The interim recommendations are based on the results of a generic evaluation of power oscillations performed for the BWROG at the request of the NRC staff. This evaluation has indicated 2
that when' regional power oscillations become detectable on the average power range monitors, the safety margin with respect to the plant minimum critical power ratio (MCPR) may be insufficient under some operating' conditions to ensure that operator action in response to APRM signals would prevent violation of the MCPR safety limit. The interim recommendations include explicit restrictions and modified operator actions to ensure that operation in the vulnerable power / flow operating regime is avoided. The recommendations were reviewed by the NRC staff and have beer, found acceptable for those plants which have effective automatic scram protection for regional oscillations. ' For plants 2
Regional oscillations are ones in which power oscillates only in distinct-regions of the reactor core, as opposed to a core-wide oscillation, in which power oscillates throughout-the core as was the case in the LaSalle Event.
i r
-)
\
i 1
which-do not have effective automatic scram protection for regional oscillations, the staff believes that the interim recommendations may not provide sufficient, reliable protection. Consequently, the staff has requested that licensees I s
implement the interim recommendations, and if appropriate, implement additional J actions which compensate for the lack of automatic scram protection for regional i oscillations. The staff's request is contained in Supplement I to NRC Bulletin j 88-07 which is discussed in the.next paragraph.
On December 30, ISEB. the NRC issued Supplement I to NRC Bulletin 88-07.
i The supplement provides addressees with new information concerning power i l
oscillations in BWRs and requests that they take specified actions to ensure that the safety limit for the plant minimum critical power ratio (MCPR) is not .
I violated as a result of regional power oscillations. The supplement is an.
outgrowth of generic evaluations of power oscillations performed by the BWROG at the NRC staff's request and the staff's independent study of. regional power 1
oscillations. The preliminary results of these evaluations indicate that when )
~ !
regional power oscillations become detectable on the average power range monitors, i the MCPR safety margin may be insufficient under some operating conditions to ensure that manual actions taken in response to APRM signals would prevent 3
violation of the MCPR safety limit. Licensees were requested to take the following actions: i l
l 3'ThesupplementisnotapplicabletoBigRockPoint(DocketNo.50-155) ,
because of unique design features and because existing operating limitations enforced by technical specifications address the stability concerns which are the subject of the supplement.
~
1
=. ,
1 i
J
.g.
J (1) Within 30 days of receipt of the supplement, all BWR licensees should implement the GE interim stability recommendations described in the GE ,
letter entitled " Interim Recommendations for Stability Actions". However, )
fur those plants that do not have effective automatic scram protection in j the event of regional oscillations, a manual scram should be initiated ;
under all operating conditions when two recirculation pumps trip !
(or "no pumps operating") with the reactor in the RUN mode. 1 (2) The boundaries of Regions A, B, and C shown in Figure 1 of the GE recom-mendations were derived for those.BWRs using NRC approved GE fuel. For BWRs using fuel supplied by other vendors, these regions should be adopted in principle, but the power / flow boundaries should be based on existing.
boundaries that have.been previously> approved by the NRC. For proposed !
new fuel designs, the stability boundaries should be reevaluated and i justified. based on any applicable operating experience,. calculated changes in core decay ratio usirg NRC approved methodology, and/or core decay ratio measurements. There should be a high. degree of assurance that instabil- 3 ities'will not occur under any circumstances of operation in Region C.
(3) The GE interim recommendations are ambiguous with respect to permissible conc'itiens fcir entry of Regions B and C. Although the recommendations state that intentional operation in Region B is not permitted and operation in Region C is permitted only for purpose of fuel conditioning during rod withdrawal startup operations, intentional entry into Region B ,
or C is also allowable in situations where rod insertion or a flow l increase is required by procedures to exit Regions A and B after unin- i tentional entry. Licensees should ensure that the procedures and training employed for implementation of these recommendations-avoid.any similar ambiguity which could lead to operator confusion.
Fursuant to 10 CFR 50.54(f), licensees are required to advise the NRC by letter within EC days of receipt of the supplement whether the requested. actions have been completed and implemented. The staff will evaluate the responses and the results of studies which are continuing over the next several months to determine whether any additional action by the staff is necessary.
^ .
III. DISCUSSION i i
My staff and I have considered the safety implications identified in the l
Petition and the specific relief requested and have dorse so in light of the most
]
recent data available to the staff from the BWROG and staff consultants. Our evaluation follows.
A. Eases for Recuest
- 1. Reliability of Decay Ratio for predicting Stability I i
Decay ratio in a reactor is a measure of the response of tha neutron flux to a change nr perturbation. As such, it is a convenient measura of the relative stability of a re6ctor core. A decay ratio of less than 1.0 indicates inherent stateility in that the response to a perturbation will decay to the steady state l value. A decay ratio equal to 1.0 represents the special condition when the response to a perturbation will be continuing oscillations of constant magnitude l termed limit cycles. A decay ratio greater than 1.0 indicates an unstable condition in that the response to the perturbation diverges in a linear system. In a
. BWR, which is a non-linear system, decay ratios greater than 1.0 are indicative of larger amplitude limit cycle oscillations. Predictive methods developed by General Electric for determining BWR decay ratios were approved by the NRC with the provision that a 20 percent uncertainty be applied conservatively to the result.
Calculated core decay ratios of less than 0.80 (i.e.,1.0 minus an uncertainty ,
of .2) by GE methods were approved as acceptable evidence of core stability '
and ccepliance with GDC-12. I
____-___-__m
j The predicted decay ratio for the LaSalle Unit 2 reactor was 0.6C.
However, large oscillations were observed during the LaSalle Event that indicate that actual decay ratio was greater than 1.0. Consequently, the uncertainty in i I
the predictive method was significantly larger than expected, that is at least ]
40 percent versus 20 percent.
The larger-than-expected calculational uncertainty has since been attributed i to an inadecuate representation of actual reactor operating conditions in the i
LaSalle calculational model. In light of this potential for error, the staff has concluded that it will no longer accept predictive calculations of core decay ratio es bases fer demonstrating compliance with GDC-12.-
In order for a licensee to satisfy GDC-IT with respect to core-wide power oscillations, the staff's position i: that each BWR unit must have the necessary operating limitations, response procedures, and t,perator training program to readily and reliably detect and suppress core-wide power oscillations regardless of calculated decay ratio. The staff has communicated this position to licensees in NRC Bulletin No. 88-07. As discussed above, all licensees have now responded to Bulletin No. 86-07 and have indicated that they have the necessary procedures and oper6 tor training program to readily and reliably detect and suppress core-wide power oscillations regardless of calculated decay ratios.
l
- 2. Adequacy of Procedural Guidance from GE (Service Information Letter 380, Revision 1) l The General Electric company issued Service Information Letter (SIL) 380, Revision I to its customers on February 10, 1984 The letter reflected new technical information regarding BWR stability and provided new guidance to BWR L____-___________.
creretors fer detectine and suppressing neutron flux oscillations. The letter superseded the treviously issued SIL 380.
The fiRC staff reviewed SIL 380, Revision 1, as part of its action to resolve Generic Issue B-29, "BWR Thermal-Hydraulic Stability." On the basis of the staff's review and that of its contractor, Oak Ridge National Laboratory, the staff concluded that
- operating limitations which provide for the detection and suppression of flux escilletions in operating regions of potential instability, consistentwiththerecommendationsofGeneralElectricSIL380(Rev.1),are acceptable to demonstrate complier.ce with GDC-10 and GDC-12 for cores loaded with approved CE fuel designs." The basis for this conclusion was the result cf a technical evaluation that indicated that if properly irnplemented, the recommendations contained in the SIL were sufficient to readily and reliably cctect and suppress limit cycle oscillations.4 It is important to note that operating procedures consistent with GE SIL 380, Revision I were not in place at LaSalle Unit 2 at the time of the March 9, 1988 it.cie nt. Consequently, the respotisc and performance of rea'ctor operators during the LaSalle Event does not reflect on tF.e adequacy of the SIL re com.endations.
The flRC staff continues to enoorse the general operational guidance given in GE SIL 380, Revision 1 and believes that if properly implemented, it is sufficient to identify and terminate core-wide limit cycle oscillations. However, i
i i;RC Memorandum and attachments from Harold R. Denton to Victor Stello, l dated May 21, 1985. l 1
q i
l
~
l 1
I l
l es discussec previously in section II of this document, supplementary procedural I ections are necessary to ensure that the safety limit for the plant minimum ,
i critical power ratio is not violated as a result of cegional power esci11ations, j i
- 3. Adecuacy of Plant Instrumentation
. l Ir. BhRs designed by GE, the neutron monitoring system (NMS) is used to monitor j the core for neutron flux oscillations. The NMS uses incere detectors to monitor {
neutron flux from startup through full-power operation ar.d is a safety-related system. The tJC staff reviews the design of the NMS as part of its normal licensing review. !
I In gereral, the staff considers the NMS to be adequate for implementation of the guicelires provided in GE SIL 380, Revision 1. However, during follow-up review cf the LaSalle Event the NRC augmented inspection team identified some time response and filtering characteristics of the NMS instruments in LaSalle L' nit 2 that they were concerned about. The AIT also expressed concern about the ability hf the AFRMs to properly detect regional oscillations which cause LFRM signals to oscillate out-of-phase. Because of these concerns, the staff requested, in NRC Bulletin No. 88-07 and in meetings with the BWROG, that licensees verify the adequacy of the instrumentation that is relied upon by operators within their procedures.
In response to Eulletin 88-07, all ficensees have evaluated their instrumentation with regard to time response and filtering characteristics and
--.-----------------,----_-.2-_---__ _m_A
1 I
24 l 1
have irdicated that instrumentation relied upon by plant operators to execute j operating procedures is adequate. The BWROG and the NRC staff have j independently evaluated the ability of NMS instrumentation to properly detect regional oscillations which occur as asymmetric out-of-phase oscillations.
The results of these evaluations are discussed below.
Power oscillations with an amplitude and phase that vary spatially in i l
the reactor are termed regional oscillations, and usually occur as asymmetric )
' out-of-phase oscillations.. These oscillations are difficult to monitor accurately with average power range instruments in the NMS but can be detected with local 4 power rar.ge instruments. The results of generic evaluations of power oscillations performed by GE for the BWR owners group (BWROG) at the request of the NRC steff and the staff's independent evaluation have indicated that when re$ional power oscillations become detectable on the APkMs, the safety margin with respect to the plant minimum critical power ratio (MCPR) may be insufficient under some operating conditions to ensure that operator action in response to APRit signals would prevent violation of the MCPR safety limit. In l light of this GE issued interim recommendations to BWR licensees which include i i
explicit restrictions on reactor power level and coolant flowrate, and actions j i
for plant operators to take if unacceptable power / flow operating regimes are
~ I entered unintentionally. The interim recommendations were reviewed by the NRC l staff and found acceptable for those plants which have effective automatic scram i protection for regional oscillations. For plants which do not have effective automatic scram protection for regional oscillations, the staff believes that l the interim recommendations may not provide sufficient, reliable protection.
Consequently, the staff has requested that licensees implement the interim recommendatiers, and if appropriate, implement additional actions which
l 4
15-1 corrensete for the lack of automatic scram protsetion for regional oscillations.
The staff's request is contained in Supplement 1 to NRC Bulletin 88-07 which was discussed previously in the section II, of this document. .The staff believes that implementation of the requests in NRC Bulletin 88-07 and Supplement I to the l bulletin will ensure continued safe plant operation in the interim until long-l term corrective actions are developed and put in place. The NRC staff will contirue to work with the BWROG to develop long-term corrective actions.
The steff expects to issue another generic communication within 12 to 24 months that will provide guidance for long-term resolution of this stability issue.
- 4. Safety Significance of Power Oscillations Power oscillations in BWRs are not considered to be a serious generic safety concern because oscillations can be detected and suppressed. Tests and l operating experience (LaSalle Event) indicate that core-wide power oscillations can be terminated manually in a timely fashion by control room operators or ultimately by automatic action of the high-power level trip function in the reactor protection system. I Asymme'ric out-of-phase oscillations are unlikely because of restrictions on reactor operating conditions. Moreover, procedures specified in Supplement 1 to NRC Bulletin 88-07 ensure that such oscillations would be suppressed quickly with an anticipatory reactor scram initiated manually by a reactor operator.
l
4
,. E. Petitioner's Reauest
- 1. ' Order All BWR Licensees To Place Their Reactors in Cold Shutdown As' described above, the NRC' issued Bulletin No. 88-07 in response to the LaSalle event. As indicated by their responses to Bulletin' No. 88-07, all BWR licensees have developed and implemented procedures to detect and sup-press core-wide power oscillations. Consequently, no BWR licensee now relies er a calculated decay ratio .to demonstrate compliance with GDC-12.
As already explained, supplement I to Bulletin No. 88-07 speci.fied additional procedures to deal with regional power oscillations. The recommendations.of.
Supplement I are currently being-implemented. In light of the relatively short period for implementation (60 days), and existing restrictions on' reactor cperating conditions that minimize the probability of. regional oscillations, the staff has concluded that continued operation of all BWRs while licensees'are implementing the recommendations of Supplement 1 is acceptable.
In summary, based on our review of the generic implications of the LaSalle Event to date, we have not identified any operational safety concerns nor instances of regulatory non-compliance which warrant a shutdown of boiling water reactors. Consequently, your request is denied.
- 2. Order All EWR Licensees to Develop and Implement Specified Procedures.5 I
This request is denied for the following reasons:
)
I (a) The NRC staff currently believes that procedural guidance provided to licensees in SIL 380, Revision 1 for detecting and suppressing I 1
power estillations is adequate for mitigating core-wide oscillations. )
I 1
(b) The NFC staff has determined that explicit procedures different from those specified by the Petitioner are necessary to control regional power esti11ations and ensure continued plant operation in accordance with GDC 12. The staff has specified the necessary procedures in Supplement I to NRC Bulletin 88-07 and requested that licensees implement the specified procedures within 30 days of receipt j of the supplement.
s i
i 5
Petitioner requests implementation of the following specific procedures: !
(a) Innediately insert control rods to below the 80% rod line following reduction or loss of recirculation flow or other transients which result in entry into potentially unstable regions of the power / flow map; (b) Increase recirculation flow during routine reactor startups and insert some control rods prior to reducing recirculation flow below 50% during shutdowns to avoid operation in potentially unstable areas of the power / flow map; (c) immediately scram the reactor if (a) or (b) above are not successful in preventing and suppressing oscillations. The licensees sht il submit these procedures to the NRC for review and approval.
i
., 1
. t
, )
l The contents of Supplement 1 to NRC Bulletin 88-07, including the
specified procedures, are discussed in section 11 of this document. '
The staff has judged that continued plant operation during the'30 day implementation period is acceptable based on the low likelihood of a regional oscillation in the relatively short period of 30 days. !
l
- 3. Order all BWR Licensees To Demonstrate That Certain Training Related to j 1
the Specified Procedures Has Been. Provided d
This request is denied for the following reasons:-
1 l
(a) The responses to NRC Bulletin No. 88-07 indicate that all licented reactor operators and shift technical advisors performing shift duties at BWRs were briefed thoroughly regarding the LaSalle Event within 15 days of receipt of NRC Bulletin No. 68-07 or soon thereafter.
(b) The responses to NRC Bulletin No. 88-07 indicate that all BWR I lic'ensees have confirmed the adequacy of their existing operator training program regarding detection and suppression of power
~
oscillations or have made the program modifications necessary to properly address this subject and accommodate changes in i procedures in response to Supplement I to the bulletin.
1 i
J
~.x_------------.-__--_--.-_-_.--_-___..-_._--__ _ . _ - . - _ - _ . - - - - _
,C .
. l I
~
l i
i l
L. Orcer All BWR Licensees To Demonstrate the Capability of Instrumentation Related to Power Oscillations-1 i
This request is denied for the following reasons:
(a) The NRC staff. considers the neutron monitoring system cesignt'd for BWRs by GE to be adequate for detecting core-wide power oscillations l in BWRs.
l (b) On the basis of responses to NRC Bulletin No. 88-07, the.NRC staff l
believes that all licensees have confirmed that the response j and filtering characteristics of instrumentation relied upon
. i by operators to execute operating procedures are acceptable. l l
(c) Implementation of operating procedures specified in Supplement l 1 to NRC Bulletin 88-07 will compensate for inability of APRMs to properly detect regional oscillations.
- 5. Order All BWR Licensees To Develop Simulators Capable of Modeling Power Oscillations Similar to Those Occurring at tasalle and Out-of-Phase l Oscillations l
Ttis request is denied for the following reason:
(a) Current NRC regulations, that is, 10 CFR 555.45(b), in conjunction with NRC Regulatory Guide 1.149 and NUREG-1258, already require utilities to have a simulation facility capable of modeling the effects of loss of forced reactor coolant flow and to certify the simulation facility for use in operator licensing examination after May 26, 1991. However, although simulator training for control of power oscillations l will improve an operator's ability to detect and suppress oscillations in a timely fashion, non-simulation based training i can be fashioned which is sufficient to address stability 1
concerns. Consequently, the staff concludes that training )!
programs now in place, including improvements made in response l
' .I to NRC Bulletin 88-07, are adequate in the interim until the enhancements of 10 CFR 555.45(b) take full effect in 1991, l
i .
- 6. Order All BWR Licensees To Report to the NRC Regarding all Future and Past Incidents in which Recirculation Pumps have Tripped Off or that Involved Power Oscillations.
1 l
i
)
4 21 This requ'est is denied for the following reasons:
(a) Existing NRC regulations, that is, 10 CFR 650.72 and-10 CFR 550.73, already require that significant events involving recirculation pump 4 trips or power oscillations be reported to the Commission. Such ever.ts are those in which the pump trips or oscillations lead to (a) l I
completion of any nuclear plant shutdown required by the plant's tuhnical specifications; or, (b) any operation or condition prohibited .)
ty the plar.t's technical specifications; or, (c) the plant being in a. I condition not covered by the plant's operating and emergency procedures, or (d) any event or condition that resulted in an unplanned manual or 1
automatic. actuation of any engineered safety feature, including the l reactor protection system. Petitioner demonstrates no basis for requiring repetition of reports already required by 150.72 and i 150.73.
(b) Since the accident at Three Mile Island, Unit 2 in 1979, programs have been developed and implemented in several NRC offices to systematically review and evaluate operating reactor event reports. Such programs include Analysis and Evaluation of Operational Data (AEOD), Operating Reactors Assessment and Events Analysis (NRR) and the Resident Inspector program (NRC Regional l Offices). These reviews have been performed to ensure prompt response to accidents. 9 identify significant precursor events and
4 b y l
s to identify adverse trends and patterns in operating experience, including any associated with BWR instability. The staff considers these past reviews of licensee event reports to have been adequate.
The Petition gives no basis to re-examine these reports and the staff
-concludes that action to collect and review past event reports is unnecessa ry.
I, 1
- 7. Reopen Generic Issue B-19, "BWR Thermal-Hydraulic Stability" J
. l This request is denied because a generic reassessment of BWR stability is net r.ecessary in order for the staff to specify criteria licensees must meet i to be in compliance with existing regulations.
1 tiRC staff action on Generic Issue B-19 culminated in the identification of two acceptable methods by which licensees could show compliance with GDC-10 and GDC-12. Licensees could either (1) show that thermal-hydraulic instabilities are not possible by design by calculating acceptably low decay ratios with analytical methods approved by the staff, or (2) show that proper capabilities for detection a.nd suppression of oscillations are embodied in plant operating procedures and operating limits. As discussed in section A.1. of this Decision, the staff has concluded that in light of the LaSalle Event, use of a calculated decay ratio to demonstrate compliance with general design criteria is no longer acceptable and that all BWR licensees must show that proper detection and suppression capabilities exist at their plants, that is, method 2 listed l previously. Because the staff concludes that the implementation of method 2 listed above continues to be a valid means for complying with GDC-12, method 2 remains a valid resolution of Generic Issue B-19. ' Consequently, repetition of the ger.eric issue resolution process for Issue B-19 is unnecessary.
4
- 8. Reopen Generic Issue B-59, "Part Loop Operation in PWRs and BWRs" This request is denied because the LaSalle Event has not revealed any deficiency in the technical resolution of Generic Issue B-59.
In resolving Generic Issue B-59 for BWRs, the staff evaluated the accept-ability of operating the reactor fer electricity production at reduced power with only one of two recirculation loops in operation (i.e. at a reduced coolantflowrate). The results of the evaluation were that stable single loop operation is achievable and acceptable with specified operating limits and procedures for avoiding as well as detecting and suppressing power oscillations that may arise (e.g., if perhaps the operating recirculation pump tripped). In tne LaSalle Event, instability arose following inadvertent trip of both recirculation pumps when the reactor operated with no recirculation loops in operation. Power operation with both recirculation loops inoperable is prohibited by each license for operation of a BWR. The LaSalle Event reaffirms the necessity "for prohibiting operation with no recirculation loops in operation. However, the LaSalle Event does not invalidate the technical findings from the review of Generic Issue B-59.
i
- 9. Reopen Rulemaking Proceedings Regarding Anticipated Transients Without Scram l
In the acknowledgement letter sent to Petitioner on August 26, 1988, I included this request among those to be considered pursuant to 10 CFR 2.206. I have subsequently determined, however, that this request is more properly treated as a petition for rulemaking under 10 CFR 2.802. As such, it has been referred to the NRC Office of Research for appropriate action. However, it is important to
<~ .
l; i
i note that both the NRC and BWR Owners Group (BWROG) currently have programs in which analyses of ATWS conditions are being conducted. These analyses treat large '!
amplitude power oscillations with state-of-the-art analytical methods. The results of these analyses to date confirm the technical bases for the current !
ATWS rule. Consequently, at this time, the NRC staff sees no basis for recom-mending that the Commission recpen rulemaking proceedings regarding ATWS. If, I however, the staff finds evidence which contradicts the assumptions and results of previous ATW5 analyses from either the .infonnation you provided in support of the request or new information from ongoing NRC and BWROG programs, it may then >
be appropriate for the Commission to reconsider the current ATWS rule. ;
- 10. Reconsider Use of the End-of-Cycle Recirculation Pump Trip on BWRs The end-of-cycle recirculation pump trip (EOC-RPT) is part of the reactor protection system and is an essential safety supplement to the reactor trip. The EOC-RPT reduces reacter coolant flowrate to provide additional n'eghtive reactivity for mitigation of events in which the reactor coolant system is pressurized rapidly.
The additional negative reactivity from the EOC-RPT is needed primarily at the and of the cycle to compensate for (1) changes in reactor power distribution over the cycle that have reduced thermal margin.and (2) a decrease in the rate of negative reactivity insertion during reactor scram. The two events for which the EOC-RPT protective feature will function are closure of the turbine stop valves and fast closure of the turbine control valvLs. In both cases, the EOC-RPT is accompanied by an anticipatory scram of the reactor that is initiated by the same signals that initiate the EOC-RPT.
II. Recuire Licensees To Submit Justification For Continued Operation in Light of the Issues Raised in the Petition 4 In NRC Bulletin 87-07 and Supplement 1 to that bulletin, the NRC Staff specified actions licensees should take to ensure continued safe operation er,d i
cocpliance with the Commission's regulations. All licensees have confirmed, {
under oath and affirmation, that (1) all necessary actions requested in NRC Eulletin 87-07 have been completed and, (2) that full documentation of the , ):
action taken is available for inspection by the NRC. Licensees are also required tc advise the NRC by letter, within 60 days of receipt of Supplement 3 !
to the. tulletin, whether actions requested in the supplement have been completed and irrierented. The staff corsiders respcnses to both the bulletin and the supplement, which ere acceptable to the staff, to be adequate justification on
~
l the part of licensees for continued opt. ration. Consequently, yeur request is denied. j l
I
- 12. Order All EWR Licensees to Submit e Report to the NRC Within One )
i Year Demonstrating Compliance with Criterion 12 Given in 10 CFR Part 50, Appendix A (GDC 12)
L As indicated previously in paragraph A.I., the NRC staff's position l 1
regarding compliance with GDC-12 is that, regardless of the magnitude of the !
l calculated decay ratio, each BWR licensee should have in place the necessary l
-____-__-_--_w
operating linit6tions, response procedures, and operator training program that I
pemit plant operators to identify and terminate limit cycle oscillations.
The staff's position was communicated to licensees in NRC Bulletin No. 88-07, through meetings with the BWROG and in Supplement I to !!RC Bulletin 88-07. The l
staff believes that actions licensees are expected to take in response to NRC Bulletin 88-07 are sufficient to ensure compliance with GDC-12 for core-wide oscillations. However, if plant inspectio:1s reveal that actions taken by
~
]
licer. sees are inadeqeate, plant-specific actions would be pursued at that time, f i
With respect to regional oscillations, procedures specified'in Supplement 1 to !
4 f1C Bulletin EB-07 ensure that such escillatiens would be suppressed quickly with
]
an ar.ticipatory reactor scram initiated tranually by a reactor operator. As )
discusseo previously, the staff believes that implementation of these procedures will ensure continued safe plant operation in the interim until long-term corrective actions are developed and put in place.
~
IV. CONCLUSION , i The Fetitioner seeks the institution of a show-cause proceeding pursuant to 10 CFR 2.202 to modify or revoke the operating license of all BWR facilities.
The institution of proceedings pursuant to 10 CFR 2.202 is appropriate only where substantial health and safety issues have been raised. See consolidated Edisen
, Company of New York (Indian Point, Units 1, 2, and 3), CLI-75-0, 2 NRC 173 (1975) and Washincton Public Power System (WPPS Nuclear Project No. 2), DD-84-7, 1
1
. ~ ,
19 NRC 899, 923 (1984). This is the standard that I have applied to the concerns raised by the Petitioner in this decision to determine whether enforcement action is warranted.
For the reasons discussed above, I conclude that no substantial health and safety issues have been raised by the Petitioner. Accordingly, the Petitioner's request for action pursuant to 10 CFR 2.206 is denied. As provided j in 10 CFR 2.206(c), a copy of this Decision will be filed with the Secretary of the Commission for the Commission's review.
FOR THE NUCLEAR REGULATORY COMMISSION Thomas E. Murley, Director Office of Nuclear Reactor Regulation l 4
Dated at Rockville, Maryland, this 27th day of April 1989. l l
9
1
.o ENCLOSURE 3 DD-89-03 NUCLEAR REGULATORY COMMISSION !
l DOCKET NO. 50-293, et al.* l BOSTON U;?SJN COMPANY, et al.'
(PilgrimNuclearPowerStation,etal.)* j ISSUANCE OF DIRECTOR'S DECISION UNDER 10'CFR 2.206 l
)
Notice is hereby given that the Director, Office of Nuclear Reactor Regulation (NRR), has issued a Director's Decision concerning a Petition dated July 22, 1988, filed by Ms. Susan Hiatt, on behalf of Ohio Cit'.sens for Responsible Energy Inc. The Petition asked the Director, NRR, to take immediate action to relieve what the Petitioner alleged to be undue risks to the public health and safety posed by the thermal-hydraulic instability of boiling-water reactors (BWRs), as revealed by the power oscillation event at ,
1 LaSalle Unit 2 on March 9, 1988 (LaSalle Event). The specific relief requested j was to order all BWR licensees to (1) place their reactors in cold shutdown, (2) develop and implement specified procedures relating to the thermal-hydrau'ic instability issues, (3) demonstrate that certain specified training has been provided relating to these procedures, (4) demonstrate the capability of instru-mentation related to power oscillations, (5) develop simulators capable of modeling power esci11ations similar to those occurring at LaSalle and out-of-phase power oscillations, (6) report to the NRC regarding all past and future incidents in whichrecirculationpumpshavetrippedoff,(7)submittotheNRCjustification for continued operation of BWRs, and (8) submit a report to the NRC within one year demonstrating compliance with criterion 12 given in 10 CFR Part 50, AppendixA(GDC-12). In addition, the Comission was requested to reopen Generic Issues B-19 and B-59, reopen the ATWS rulemaking proceeding, and
$00W)$ A
s ~ .
reconsider the use of the end-of-cycle circulation pump trip on BWRs. l Ms. Hiatt gave as grounds for the Petition that the LaSalle Event has serious safety implications for all BWRs and that the Nuclear Regulatory Comission (NRC) had failed to take appropriate regulatory action in response to the LaSalle Event.
On August 26, 1988, the Director, Office of Nuclear Reactor Regulation (NRR),acknowledgedreceiptofthePetition. He informed Ms. Hiatt that (1) her request for imediate relief was denied because the allegations that formed the basis for the Petition did not reveal any new operational safety issues which posed an imediate safety concern for continued BWR operation, (2) the Petition would be treated under 10 CFR 2.206 of the Comission's regulations, and (3) appropriate action would be taken within a reasonable time. ;
In the August 26, 1988 letter, the Director, NRR, acknowledged Ms. Hiatt's request to reopen the ATWS rulemaking proceedings as a request which would be
' treated pursuant to 10 CFR 2.206. This request, however, will not be treated pursuant to 10 CFR 2.206 but is being treated separately as a petition for i rulemaking under 10 CFR 2.802 of the Comission's regulations.
The Director has now deter.nined that all of Ms. Hiatt's requests, except for her request to reopen the ATWS rulemaking, should be denied for the reasons set forth in the " Director's Decision Pursuant to 10 CFR 2.206" (DD-89-03).
The Decision is available for inspection and copying in the Comission's Public Document Room, 2120 L Street N.W., Washington, D.C. 20555 and at the Local Public Document Rooms near the facilities listed below. The addresses and hours of operations for the local public document rooms may be obtained by calling the following toll-free number: 1-800-638-8081.
I
\ _ _ _ _ _
+ j
.. j i
l l
A copy of the Decision will be filed with the Secretary of the Comission j for the Comission's review in accordance with 10 CFR 2.206(c). As provided in l l
10 CFR 2.206(c), the Lecision will become the final action of the Comission twenty-five (25) days after issuance unless the Comission on its own motion i 1
institutes review of the Decision within that time. I i
I I
FOR THE NUCLEAR REGULATORY COMMISSION 4:=y f Thomas E. Murley, Director' Office of Nuclear Reacter Regulatior, i
Deted at Rockville, Maryland, j this 27th of April 1989.
l i
s I
~
l 1
D .
CAROLINA POWER & LIGHT CO. (Brunswick Station, Units 1 and 2, Docket Nos. 50-324 and 50-325)
CLEVELAND ELECTRIC ILLUMINATING CO., ET AL. (Perry Nuclear Power Plant, Unit 1, Docket No. 50-440)
COMMONWEALTH EDISON CO. (Dresden Nuclear Power Plant, Units 2 and 3, Docket Nos. 50-237 and 50-249), (Quad Cities Nuclear Power Plant, Units 1 and 2, Docket Nos.50-254 and 50-265), (LaSalle County Station, Units I and 2, Docket Nos. 50-373 and 50-374)
CONSUMERS POWER CO. (Big Rock Point, Docket No. 50-155)
DETROIT EDISON CO. (Fermi Unit 2, Docket No. 50-341)
GENERAL PUBLIC UTILITIES (Oyster Creek Stetion, Docket No. 50-219)
GEORGIA POWER CO. (Hatch Nuclear Power Plant, Units 1 and 2, Docket Nos. 50-321 and 50-366) (
GULF STATES UTILITIES C0. (River Bend Station, Docket No. 50-458) 1 i ILLINDIS POWER CO. (Clinton Nuclear Power Plant, Docket No. 50-461) l IOWA ELECTRIC LIGHT & POWER CO. (Duane Arnold Nuclear Power Plant, l Docket No. 50-331) l LONGISLANDLIGHTINGCO.(ShorehamNuclearPowerPlant,DocketNo.50-322) l MISSISSIPPI POWER & LIGHT CO. (Grand Gulf Nuclear Station, Docket No. 50-416)
NEBRASKAPUBLICPOWERDISTRICT(CooperStation,DocketNo.50-298)
NIAGARA M0 HAWK POWER CORP. (Nine Mile Point, Units 1 and 2, Docket Nos. 50-220 l and 50-410)
NORTHEASTUTILITIES(MillstoneUnit1,DocketNo.50-245) I
. NORTHERN STATES POWER CO. (Monticello Nuclear Power Plant, Docket No. 50-263) i l
PENNSYLVANIA POWER & LIGHT CO. (Susquehanna Steam Electric Station, j Units 1 and 2 Dochet Nos. 50-387 and 50-388) l PHILADELPHIA ELECTRIC C0. (Peach Bottom Nuclear Station, Units 2 and 3, Docket l Nos. 50-277 and 50-278). (Limerick Nuclear Power Plant, Unit 1, Docket No. 50-352) ]
POWER AUTHORITY OF THE STATE OF NEW YORK (James A. Fitzpatrick Station, Docket No. 50-333)
PUBLIC SERVICE ELECTRIC & GAS CO. (Hope Creek Generating Station, !
Docket No. 50-354)
TENNESSEE VALLEY AUTHORITY (Browns Ferry Nuclear Statioh, Units 1, 2, and 3, Docket Nos. 50-259,50-260,and50-296)
VERMONT YANKEE. NUCLEAR POWER CORP. (Vermont Yankee Nucl+ Power Plant, DocketNo.50-271)
WASHINGTON PUBLIC POWER SUPPLY SYSTEM (WNP Unit 2, Docket No. 50-397)
-m__ _ _ _ _ _