MONTHYEARML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 IR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23348A3712023-12-14014 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report (05000416/2024011) and Request for Information ML23340A2222023-12-13013 December 2023 Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1422023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000416/20234032023-11-13013 November 2023 Security Baseline Inspection Report 05000416/2023403 Cover Letter ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000416/20230032023-11-0808 November 2023 Integrated Inspection Report 05000416/2023003 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23270B1892023-09-27027 September 2023 Evacuation Time Estimate Study ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23240A3952023-08-28028 August 2023 Reply to a Notice of Violation; EA-23-019 IR 05000416/20230052023-08-21021 August 2023 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2023005) ML23226A1002023-08-18018 August 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 IR 05000416/20234042023-08-0707 August 2023 Material Control and Accounting Program Inspection Report 05000416/2023404 IR 05000416/20230912023-07-28028 July 2023 Final Significance Determination of a Green Finding and Notice of Violation; NRC Inspection Report 05000416/2023091 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23166B0712023-06-15015 June 2023 Reply to Notice of Violation EA-22-104 and EA-22-115 ML23166B0662023-06-15015 June 2023 Response to NRC Integrated Inspection Report 05000416/2023001 ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) GNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML23122A1632023-05-18018 May 2023 NRC Inspection Report 05000416/2023090 and Preliminary White Finding IR 05000416/20234022023-05-17017 May 2023 Security Baseline Inspection Report 05000416/2023402 ML23110A8002023-05-10010 May 2023 Notice of Violation; Integrated Inspection Report 05000416/2023001 and NRC Investigation Report 4-2022-004 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000416/20230012023-05-10010 May 2023 Notice of Violation; Integrated Inspection Report 05000416/2023001 and NRC Investigation Report 4-2022-004 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23117A0422023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) ML23111A2132023-04-21021 April 2023 Responses to RAI Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML23110A0552023-04-20020 April 2023 Annual Radiological Environmental Operating Report (AREOR) ML23103A1022023-04-13013 April 2023 Annual Report of Individual Monitoring - NRC Form 5 for 2022 Per 10 CFR 20.2206 ML23102A1482023-04-12012 April 2023 Notification of NRC Initial Operator Licensing Examination 05000416/2024301 ML23089A0602023-03-30030 March 2023 Entergy Operations, Inc. - Fleet Project Manager Assignment ML23088A3922023-03-29029 March 2023 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML23079A2772023-03-21021 March 2023 U.S. Nuclear Regulatory Commission Presentation at the May 1, 2023, Port Gibson City Council Meeting ML23080A2882023-03-21021 March 2023 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) Entergy Operations, Inc IR 05000416/20230112023-03-0808 March 2023 Design Basis Assurance Inspection Report 05000416/2023011 2024-01-31
[Table view] |
Text
November 3, 2020 Mr. Robert Franssen, Site Vice President Entergy Operations, Inc.
Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
ASSESSMENT FOLLOW-UP LETTER FOR GRAND GULF NUCLEAR STATION
Dear Mr. Franssen:
As a result of our quarterly review of plant performance, which was completed on November 2, 2020, the NRC updated its assessment of Grand Gulf Nuclear Station. The NRCs evaluation consisted of a review of performance indicators and inspection results.
This letter informs you of the NRCs assessment and our plans for a future inspection at your facility. This letter supplements, but does not supersede, the annual assessment letter issued on March 3, 2020.
The NRCs review of Grand Gulf Nuclear Station identified that the Unplanned Scrams Per 7,000 Critical Hours performance indicator has crossed the Green-to-White threshold.
The performance issues associated with this performance indicator led to three reactor scram events that occurred from May through August 2020. These events included an automatic reactor scram due to a turbine trip, a manual reactor scram due to turbine control valve oscillations, and an automatic reactor scram due to low reactor water level following a reactor feedwater pump trip.
The NRC determined the performance at Grand Gulf Nuclear Station to be in the Regulatory Response Column (Column 2) of the Reactor Oversight Process Action Matrix beginning the third quarter of 2020. Therefore, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs. The objectives of the supplemental inspection are (1) to assure that the root causes and contributing causes of individual and collective White performance issues are understood, (2) to independently assess and ensure that the extent of condition and extent of cause of individual and collective White performance issues are identified, (3) to ensure that completed corrective actions to address and preclude repetition of White performance issues are prompt and effective, and (4) to ensure that pending corrective action plans direct prompt and effective actions to address and preclude repetition of White performance issues. This inspection will be scheduled after you notify the NRC of your readiness.
R. Franssen 2 Although plant performance was determined to be within the Regulatory Response Column, the NRC has not yet finalized the significance of Apparent Violation (AV)05000416/2020015-01, Failure to Meet DOT Regulations During a Radioactive Shipment Due to an Incorrect Shipping Name, Marking, and Emergency Response Guide. The final safety significance determination may affect the NRCs assessment of plant performance and the associated supplemental inspection plan.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Jason Kozal at 817-200-1144 with any questions you have regarding this letter.
Sincerely,
/RA/
Anton Vegel Digitally signed by Anton Vegel Date: 2020.11.03 11:45:05 -06'00' Anton Vegel, Director Division of Reactor Projects Docket No. 05000416 License No. NPF-29 cc: Distribution via LISTSERV
ML20308A396 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: CHY Yes No Publicly Available Sensitive NRC-002 OFFICE DRP:C/SPE DRP:PBC DRP: D NAME CYoung JKozal AVegel SIGNATURE /RA/ /RA/ /RA/
DATE 11/02/2020 11/02/2020 11/03/2020