Category:Letter
MONTHYEARML15196A0292015-07-0606 July 2015 Termination of Quality Assurance Program Approval for Radioactive Material Packages No. 0348 ML15112A0832015-04-14014 April 2015 Amendment No. 12 to Indemnity Agreement No. E-24 University of Michigan Ford Nuclear Reactor ML14310A5882015-04-0202 April 2015 Ford License Termination Letter - Termination of Facility Operating License No. R-28 for the University of Michigan Ford Nuclear Reactor ML15030A3112015-01-22022 January 2015 Analytical Results for University of Michigan Soil ML15020A7252015-01-16016 January 2015 University of Michigan, Ford Nuclear Reactor, Storage Ports Soil Sample Results ML15029A5102015-01-14014 January 2015 University of Michigan, Ford Nuclear Reactor, Report on Reactor. Operations ML14099A1072014-03-28028 March 2014 Report on Reactor Operations University of Michigan Ford Nuclear Reactor ML14063A2072014-02-26026 February 2014 University of Michigan, Request for Termination of the Ford Nuclear Reactor ML13360A1802013-12-23023 December 2013 University of Michigan Ford Reactor Master Inspection Plan IR 05000002/20120022013-10-0404 October 2013 IR 05000002-12-002(DNMS), on 09/11/2013, University of Michigan Ford Reactor Inspection Report ML13235A0092013-08-19019 August 2013 University of Michigan, Ford Nuclear Reactor, Submittal of Final Status Survey - Background Count Rate Correction ML13205A1532013-07-11011 July 2013 University of Michigan - Ford Nuclear Reactor: Final Status Survey Report (Cover Letter) ML13051A0472013-02-14014 February 2013 University of Michigan - Ford Nuclear Reactor, Reportable Occurrence #24, Reactor Building Flood - Ruptured Fire Suppression Line, Technical Specification (Section 1.0 / Item 8) ML13029A5002013-01-24024 January 2013 University of Michigan, Submittal of 2012 Report on Reactor Operations ML12356A1352012-12-18018 December 2012 MIP- University of Michigan Ford Reactor Master Inspection Plan CY2013 ML13028A1012012-12-11011 December 2012 University of Michigan, Technical Specification Amendment Request Final Status Survey - Survey Design Package for Fnr Foundation Cavity ML12312A1302012-11-0202 November 2012 Ford Nuclear Reactor, Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.5.10.6 (Final Status Survey) ML12293A3022012-10-25025 October 2012 T. Alexander Ltr. Approval of Partial Final Site Survey Plan for University of Michigan Ford Nuclear Reactor IR 05000000/20120012012-10-10010 October 2012 IR 0500000-12-001, 9/11/2012, University of Michigan - Ford Nuclear Reactor ML12264A0642012-09-18018 September 2012 University of Michigan - Ford Nuclear Reactor Final Disposition of Fnr Storage Ports ML12264A5622012-09-17017 September 2012 University of Michigan - Ford Nuclear Reactor, Quality Assurance Plan for Final Status Survey Plan ML12199A0182012-07-13013 July 2012 University of Michigan, Request an Amendment to the Ford Nuclear Reactor Technical Specification Decommissioning Plan - Revised Section 4.0 (Final Status Survey ML12157A2662012-06-0101 June 2012 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey) ML12117A1182012-04-20020 April 2012 Occupational Safety & Environmental Health ML12124A3102012-04-20020 April 2012 University of Michigan, Report on Reactor Operations for January 1 to December 31, 2011 ML12095A3782012-02-14014 February 2012 University of Michigan Ltr Ford Nuclear Reactor- Decommissioning Plan- Additional Information for Section 4.0 (Final Status Survey Plan) Docket 50-2/ License R-28 ML12025A1252012-01-20020 January 2012 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey) ML1132606162011-11-21021 November 2011 IR 05000002-11-001; 08/09/2011, University of Michigan, Reply to a NRC Inspection Report Notice of Violation IR 05000002/20110012011-10-24024 October 2011 IR 05000002-11-001 and Notice of Violation, on 08/09-11/2011 - 10/12/2011, Univ of Mi Ford Nuclear Reactor ML11273A0262011-09-29029 September 2011 Fy 2012 University of Michigan Ford Nuclear Reactor Master Inspection Plan ML1124208522011-08-23023 August 2011 Orise Contract No. DE-AC05-06OR23100 Letter Report for Analytical Results for Three Soil Samples from the University of Michigan Ford Reactor, Ann Arbor, Michigan ML11199A0092011-07-12012 July 2011 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey Plan) (Response to NRC Comments Dtd June 1, 2011 on Initial Fnr - Technical Specification Amendment Submitted A IR 05000002/19500112011-04-29029 April 2011 Notification of Licensed Operator Initial Examination 05000250-11-3002,05000251-11-302 ML11119A0042011-04-0808 April 2011 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey Plan) IR 05000002/20090032011-03-24024 March 2011 IR 05000002-09-003, on 09/14-16/2010, In-office Review Through 03/14/2011, University of Michigan - Ford Nuclear Reactor ML1104101322011-02-14014 February 2011 Change in NRC Staff Project Management for the University of Michigan Ford Nuclear Reactor ML1032300972010-11-17017 November 2010 Oak Ridge Institute for Science and Education (Orise) Letter Report for Four Soil Samples from the University of Michigan Ford Reactor (IR 05000002/2009003) ML1027803212010-10-0101 October 2010 MIP- University of Michigan Ford Nuclear Reactor Fiscal Year 2011 IR 05000002/19600102010-02-0909 February 2010 Notification of Licensed Operator Initial Examination - 05000259-10-301, 05000260-10-0301, 05000296-10-301 ML0935210582009-12-17017 December 2009 Mip - University of Michigan Ford Nuclear Reactor-FY 2010 IR 05000002/20200902009-12-0404 December 2009 IR 05000220-090-10 and 05000410-09-010; Nine Mile Point Nuclear Station, LLC; on 10/5-22/2009; Nine Mile Point Nuclear Station, Units 1 and 2; Biennial Baseline Inspection of Identification and Resolution of Problems Report ML0931305262009-11-20020 November 2009 October 23, 2009 Summary of Open Meeting with the University of Michigan to Discuss Decommissioning Status of Ford Nuclear Reactor IR 05000002/19640092009-07-0909 July 2009 IR 05000264-09 on 06/22/09 - 06/26/09 for Dow Chemical Co IR 05000002/20090022009-06-19019 June 2009 IR 05000002-09-002 on 03/24/09 and 06/01/09 - 06/02/09 for Univ of Michigan - Ford Nuclear Reactor ML0915505952009-06-0101 June 2009 Orise, Letter Report for Analytical Results for Two Soil Samples and One Concrete Sample from the Ford Reactor at the University of Michigan, Ann Arbor, Mi IR 05000002/19772782009-01-0606 January 2009 EA-08-298, Peach Bottom - Notice of Violation with Proposed Imposition of Civil Penalty - $65,000 (Peach Bottom Atomic Power Station - NRC Investigation Report No. 1-2008-001 and NRC Inspection Report Nos. 05000277-278/2007404; and 05000277 IR 05000002/20090012008-12-23023 December 2008 IR 05000002-09-01 on 12/10/08 - 12/11/2008 for Ford Nuclear Reactor; (DNMS) ML0829806362008-10-22022 October 2008 University of Michigan Ford Nuclear Reactor Master Inspection Plan - Fiscal Year 2009 IR 05000002/20080012008-09-25025 September 2008 IR 05000002-08-01 (DNMS) on 08/28/08 for Ford Nuclear Reactor, Univ. of Michigan IR 05000002/20070012007-12-0606 December 2007 IR 05000002-07-001, on 06/28/2007 & 11/13-14/2007, Univ. of Michigan - Ford Nuclear Reactor Inspection 2015-07-06
[Table view] |
Text
MICHIGAN MEMORIAL -PHOENIX PROJECT
.- PHOENIX MEMORIAL LABORATORY FORD NUCLEAR REACTOR ANN ARBOR, MICHIGAN 48109-2100 27 June 2003 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Docket 50-2, License R-28
Subject:
Ford Nuclear Reactor License and Technical Specification Amendment 47, Elimination of Possession ofSpecial Nuclear Material and Physical Security Plan
Dear Mr. Hughes:
The University of Michigan, Ford Nuclear Reactor is submitting a request to eliminate the possession of Special Nuclear Material in the license Issued to the Ford Nuclear Reactor, current amendment 45 (17 Sep 1998). This license amendment is requested in advance of the removal of all special nuclear material covered by the license for the Ford Nuclear Reactor. It is understood that this license amendment, if approved, would be effective only after all special nuclear material licensed under license R-28 has be returned to the U.S. Department of Energy in a manner which complies with all Orders and Regulations promulgated by the Commission and the Department of Transportation. The University fully expects to complete this removal within the next several months.
The University is also requesting the elimination of the requirement to "implement and maintain in effect all provisions of the physical security plan approved by the Commission" upon the removal of all special nuclear material covered by the license for the Ford Nuclear Reactor. The referenced physical security plan addresses the physical security requirements for the special nuclear materials allowed under the license and is no longer necessary once all special nuclear material covered by the license for the Ford Nuclear Reactor is removed and the license has been amended for no possession as requested above.
This license amendment is the first in a long series of steps the University will be taking over the next few years as the Ford Nuclear Reactor is shutdown, defueled, dismantled, decontaminated and the license terminated. The University requests that the license issued to the Ford Nuclear Reactor remain an operating license so that the ability to make changes to the facility as allowed in 10 CFR 50.59 remains available. The University also requests timely approval of this license amendment request as delays in its approval could result in significant financial costs to the University.
If there are any questions regarding this information, please feel free to contact Christopher W. Becker at (734) 764-6224.
I declare under penalty of perjury that the foregoing is true and correct.
Signa o A_ 7 Executed on: __ _ _
A~tho.if francis, Ph.D.
or Michigan Memorial Phoenix Project
Enclosure:
Operating License R-28, Amendment 47, Proposed File: Correspondence 03-016 License Amendment - Amendment 467 C:\Documents and Settings\UofM\Letter File\03-016.wpd a 6 Phone: (734) 764-6220 Fax: (734) 936-1571 www.umich.edu/-mmpp/
OPERATING LICENSE AND TECHNICAL SPECIFICATIONS Ford Nuclear Reactor Docket 50-2, License R-28 Amendment 47: Proposed License Renewal Issue With Amendments 1-32: 110384 Amendment: 33: 080489 34: 070191 35:040792 36:050192 37:062592 38:100792 39: 051493 40: 080193 41:111594 42: 021795 43: 080985 44: 041698 45: 091798 46: Submitted 47: Proposed FORD NUCLEAR REACTOR The University of Michigan Docket 50-2 OPERATING LICENSE R-28 A. This license applies to the Ford Nuclear Reactor owned by The University of Michigan.
The facility is located in Ann Arbor, Michigan, and is described in the application dated November 30, 1984, as supplemented.
B. Subject to the conditions and requirements incorporated herein, the Commission hereby licenses The University of Michigan:
(1) Pursuant to Section 104c of the Act and 10 CFR Part 50, "Domestic Licensing of Production and Utilization Facilities," to possess, use, and operate the facility at the designated location in Ann Arbor, Michigan, in accordance with the procedures and limitations set forth in this license, (2) Deleted 47 (3) Deleted (4) Pursuant to the Act and 10 CFR Part 30, "Rules of General Applicability to Domestic Licensing of Byproduct Material," to possess, but not to separate, such byproduct as may be produced by the operation of the facility.
(5) Pursuant of the Act and 10 CFR Part 30, 'Rules of General Applicability to 45 Domestic Licensing of Byproduct Material," to receive for irradiation in the reactor in the amounts as required any byproduct material without restriction to chemical or physical form having a definite research and development purpose.
C. This license shall be deemed to contain and is subject to the conditions specified in Parts 20, 30, 50, 51, 55, 70, and 73 of 10 CFR Chapter I, to all applicable provisions of the Act, and to the rules, regulations and orders of the Commission now or hereafter in effect and to the additional conditions specified below:
OPERATING LICENSE AND TECHNICAL SPECIFICATIONS Ford Nuclear Reactor Docket 50-2, License R-28 Amendment 47: Proposed (1) Steady State and Maximum Power Levels The licensee is authorized to operate the facility at a steady state power level of 2.0 megawatts (thermal). The maximum power level shall not be in excess of 2.2 megawatts (thermal).
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through l 47 Amendment No. 47, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the technical specifications.
(3) Deleted D. This license is effective as of the date of issuance and shall expire twenty years from its date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Director Division of Licensing Date of Issuance: July 29, 1985
Enclosure:
Appendix A, Technical Specifications