MONTHYEARML18043A1192018-01-19019 January 2018 Transmittal Report - Protective Action Recommendation Reference Material ML17347A1182016-12-16016 December 2016 Revision 31 to Emergency Plan, Effective December 21, 2016 ML16243A0322016-08-23023 August 2016 Field Monitoring Teams Radiation Monitoring Teams Field Surveys ML16189A0752016-06-28028 June 2016 Revision 14 to Emergency Plan Implementing Procedure RA-EP-02110 (Emergency Notification) ML16131A6682016-04-30030 April 2016 Revision 01 to RA-EP-02865, Emergency Plan Off Normal Occurrence Procedure ML16131A6702016-04-30030 April 2016 Revision 04 to Procedureinternal Flooding, RA-EP-2880 ML16110A3172016-04-14014 April 2016 Revision 10 to Emergency Plan Off Normal Occurrence Procedure, RA-EP-02850, Hazardous Chemical and Oil Spills. ML16082A3332016-03-16016 March 2016 Emergency Plan Off Normal Occurrence Procedure - RA-EP-02830 - Flooding ML16081A1792016-03-14014 March 2016 Emergency Plan Implementing Procedure RA-EP-02010, Revision 18 ML16048A2532016-02-0505 February 2016 Revision 06 to RA-EP-02870, Emergency Plan Off Normal Occurrence Procedure ML15364A0192015-12-22022 December 2015 Revision 13 to RA-EP-02110, Emergency Notification and Revision 13 to RA-EP-02220, Emergency Operations Facility Activation and Response ML0411403412004-04-21021 April 2004 Emergency Implementing Procedure Changes ML0410604042004-04-0808 April 2004 Transmittal of Davis-Besse Emergency Plan Implementing Procedure RA-EP-01900, General Emergency, Revision 03 ML0409004322004-03-22022 March 2004 Davis- Besse - Revision 4 to RA-EP-02620, Emergency Dose Control and Potassium Iodide Distribution. ML0406506412004-02-27027 February 2004 Revision 4 to RA-EP-01500, Emergency Classification. ML0406506462004-02-25025 February 2004 Revision 5 to RA-EP-02010, Emergency Management and Revision 3 to RA-EP-02220, Emergency Operations Facility Activation and Response ML0532604642004-02-23023 February 2004 Enclosure a, Davis-Besse Nuclear Power Station (DBNPS) Emergency Plan, Dated February 23, 2004, DBNPS Emergency Plan Implementing Procedure RA-EP-02245, Effective June 8, 2005 & DBNPS Emergency Plan Offnormal Occurrence Procedure RA-EP-0287 ML0404203782004-02-0202 February 2004 Emergency Plan Implementing Procedure Revision 01 for RA-EP-02240, Offsite Dose Assessment. ML0402906512004-01-21021 January 2004 Emergency Plan Offnormal Occurrence Procedure RA-EP-02800, Rev 02, Preparation and Transport of Contaminated Injured Personnel. ML0336305932003-12-17017 December 2003 Revision 02 to Procedure RA-EP-02260, Radiological Controls in the Dbab. ML0334303522003-12-0202 December 2003 Emergency Plan Implementing Procedure RA-EP-02270, Facilities Support, Revision 02 ML0333605922003-11-25025 November 2003 Rev. 2 to RA-EP-02710, Reentry ML0332904612003-11-13013 November 2003 Transmittal of Emergency Plan Off Normal Occurrence Procedure RA-EP-02820 ML0325214712003-09-0202 September 2003 Revision 03 to Emergency Plan Implementing Procedure RA-EP-02250, Radiation Monitoring Team Surveys ML0323406152003-08-13013 August 2003 Transmittal of Emergency Plan Implementing Procedure RA-EP-02410, Revision 5 ML0322003182003-08-0101 August 2003 Revised Emergency Plan Implementing Procedures ML0321206522003-07-19019 July 2003 Emergency Plan Implementing Procedure ML0319902262003-07-10010 July 2003 Transmittal of Emergency Plan Implementing Procedure, RA-EP-01500, Revision 3 ML0319000372003-06-30030 June 2003 Transmittal of Revision 3 to RA-EP-02861, Emergency Plan Off Normal Occurence Procedure ML0317606102003-06-17017 June 2003 5 to Davis-Besse Emergency Plan Implementing Procedure RA-EP-02110, Emergency Notification. ML0316812832003-06-0606 June 2003 Transmittal of Revision 4 to Table of Contents for Davis Besse Nuclear Power Station Emergency Procedure RA-EP-02820 ML0316109702003-05-30030 May 2003 Transmittal of Emergency Plan Off Normal Occurrence Procedure ML0313405452003-05-0505 May 2003 Transmittal of Revision 2 to EPIP RA-EP-02250, Radiation Monitoring Team Surveys. ML0312606292003-04-29029 April 2003 Transmittal of Emergency Plan Implementing Procedure, RA-EP-02250, Radiation Monitoring Team Surveys, Revision 01 ML0311403822003-04-11011 April 2003 Transmittal of Emergency Plan Implementing Procedure RA-EP-01500, Revision 02 ML0309906722003-04-0202 April 2003 Transmittal of Emergency Plan Off Normal Occurrence Procedure, RA-EP-02820 ML0307004652003-03-0505 March 2003 Emergency Plan Off Normal Occurrence Procedures, Revision 2 to RA-EP-02810, Tornado, and Revision 1 to RA-EP-02840, Explosion. ML0306406512003-02-25025 February 2003 Revised Emergency Plan Implementing Procedures ML0304404522003-02-0606 February 2003 Emergency Plan Implementing Procedure, RA-EP-02720, Rev 4 ML0303803752003-01-29029 January 2003 Rev 3 to RA-EP-02610, Emergency Radiation Protection Organization Activation and Response. ML0303602192003-01-23023 January 2003 Emergency Plan Off Normal Occurrence Procedure, RA-EP-02850, Rev 4 ML0303601402003-01-23023 January 2003 Emergency Plan Implementing Procedure, RA-EP-02110, Rev 4 ML0302204582003-01-10010 January 2003 Transmittal of Revised Davis-Besse Emergency Plan Implementing Procedure RA-EP-02245, Revision 0001 ML0302201142003-01-0909 January 2003 Transmittal of Revised Davis-Besse Emergency Plan Implementing Procedures RA-EP-02220, Revision 02, RA-EP-02310, Revision 02, RA-EP-02410, Revision 04, RA-EP-02620, Revision 02, RA-EP-02805, Revision 03, & RA-EP-02807, Revision 02 ML0236004882002-12-12012 December 2002 Revisions to Emergency Plan Implementing Procedures, Including Rev 0 to RA-EP-02550, Offsite Personnel & Vehicle Monitoring & Decontamination. ML0233700182002-11-13013 November 2002 Emergency Plan Offnormal Occurrence Procedure RA-EP-02870, Revision 2 ML0232903552002-11-0505 November 2002 Procedure RA-EP-02880 Internal Flooding Revision 02 ML0231005372002-10-29029 October 2002 Emergency Plan Implementing Procedures, Rev. 3 to RA-EP-02720, Rev. 1 to RA-EP-02800, and Rev. 1 to RA-EP-02870 ML0230304622002-10-23023 October 2002 Emergency Plan Implementing Procedure RA-EP-02110, Rev. 03 ML0228201302002-09-27027 September 2002 to Emergency Plan Implementing Procedure RA-EP-2510, Emergency Security Organization Activation & Response, for Davis Besse Power Station 2018-01-19
[Table view] Category:Letter
MONTHYEARIR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 L-24-025, Submittal of the Updated Final Safety Analysis Report, Revision 352024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant ML24045A0322023-10-26026 October 2023 L-23-221 Proposed Exam Submittal Cover Letter L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) 2024-09-06
[Table view] |
Text
Davis Besse Power Station Control Copy Number: 1665 Transmittal / Receipt Acknowledgement Transmittal Number: 0311-43355 Transmittal Date: 11-25-2003 To: DOC. CONTROL DESK Mail Stop / Address- USNRC DIVISION OF EMERGENCY PREPARDNESS WASHINGTON, D.C. 20555 Document holders are responsible for control and maintenance of documents in accordance with the actions specified by this transmittal. Outdated material shall either be removed and destroyed or marked to reflect that it is superseded or voided and is no longer considered controlled.
Note: Destroy Safeguard information by shredding.
File documents in tab order as identified on the Table of Contents Contact Document Control with any questions at (419)-321-7483 631-jx
('.. C. ('
Davis Besse Power Station Control Copy Number: 1665 Transmittal / Receipt Acknowledgement Transmittal Number: 0311-43355 Transmittal Date: 11-25-2003 Document _.
'tt TOC I TOC 2 Te Number ShtlSec Changes Rev Status old EPIC PROC RA-EP-02710 0001 APPROVE1Y' new EPIC PROC RA-EP-027 10 0002 APPROVED
rE, Page I of II K>
Davis-Besse Nuclear Power Station EMERGENCY PLAN IMPLEMENTING PROCEDURE; RA-EP-02710 I
- -REENTRY REVISION 02 Prepared by: B.W. Cope Procedure Owner: . Manager - Regulator rgt
' I .. . ; i .
f;,C^,i,I:.k,
. 1 FDX& fi. Cor'; I Effective Date: NOV 2 5 m Procedure Classification:
X Safety Related LEVEL OF USE:
Quality Related IN-FIELD REFERENCE Non-Quality Related K>
2 RA7EP-02710
- Revision 02 TABLE OF CONTENTS Page 1.0 PURPOSE .. 3
2.0 REFERENCES
.. 3 3.0 DEFINITIONS .. 3 4.0 RESPONSIBILITIES .. 3 5.0 INITIATING CONDITIONS .............................................................. 4 6.0 PROCEDURE .5 6.1 Emergency Plant Manager/Plant Recovery Manager ............................ 5 6.2 Emergency RP Manager/OSC RP Coordinator .6 6.3 OSC Manager .6 6.4 Assistant OSC Manager .7 6.5 OSC Team Briefer/Debriefer .7 6.6 Reentry Team(s) ....................... 8 7.0 FINAL CONDITIONS .0..................................................... .. 10 l 8.0 RECORDS .10 COMMITMENTS ............................... ................................ 11
- 3 RA-EP-02710 Revision 02 1.0 PURPOSE This procedure provides guidance for reentry into the Davis-Besse Nuclear Power Station (DBNPS) after the emergency situation is under control.
2.0 REFERENCES
2.1 Departmental 2.1.1 DB-HP-012014 Administrative Dose Control Levels 2.1.2 RA-EP-024 10, Operations Support Center Activation and Response 2.1.3 RA-EP-02620, Emergency Dose Control and Potassium Iodide Distribution 2.1.4 RA-EP-02640, Station Radiological, Surveys and Controls During Emergencies 2.1.5 RA-EP-02720, Recovery 2.2 Manuals 2.2.1 DBNPS Emergency Plan 2.2.2 Corporate Emergency Response (CER) Plan, Davis-Besse Nuclear Power Station (DBNPS) 3.0 DEFINITIONS 3.1 REENTRY -Reentry into the DBNPS site to perform certain essential actions which could not be performed coincident with the immediate response to the emergency.
Reentry is made when the emergency situation is under control and more deliberate planning can be made for the activities to be performed. Reentry may occur before termination of the emergency or it may be conducted as part of the Recovery.
4.0 RESPONSIBILITIES 4.1 For reentry activities conducted before termination of the emergency and the initiation of Recovery, the Emergency Plant Manager shall be responsible for authorizing reentry and implementing this procedure. He shall inform the Emergency Director that reentry is being initiated.
4.2 For reentry activities conducted during Recovery, the Plant Recovery Manager shall be responsible for implementation of this procedure, and shall ensure that the Recovery Director remains informed.
I 4 RA, EP-027l0 Revision 02 4.3 The Emergency Radiation Protection (RP) Manager and the Operations Support Center Radiation Protection (OSC RP) Coordinator shall plan the personnel radiological protection aspects of reentry into the DBNPS and appoint OSC RP Briefer/lDebriefers.
4.4 The OSC Manager shall coordinate reentry activities and ensure that all reentry teams have been adequately briefed and debriefed on their return.
4.5 The Supervisor - Emergency Preparedness shall be responsible for the accumulation and submittal of Quality Assurance Records and other records deemed necessary to Nuclear Records Management.
5.0 INITIATING CONDITIONS This procedure shall be initiated when the emergency situation is under control and conditions exist which require entry into Station areas that have been evacuated due to adverse conditions or have been closed to personnel during an emergency.
"r .: /- 5 RA-EP-02710 N. Revision 02 6.() RCUUEJURE 6.1 Emergency Plant Manager/Plant Recovery Manager The Emergency Plant Manager or if recovery has been initiated, the Plant Recovery Manager should:
6.1.1 Consult with the other emergency response personnel before reentry and review the following:
- a. Available surveillance data to determine the plant areas actually or potentially affected by radiation and/or contamination.
CAUTION 6.1.1 .b The use,of personnel who have a high cumulative radiation dose shall be minimized. Every effort shall be made to maintain radiation dose within the limits specified in DB-HP-01201. The Emergency Director shall be notified, and his approval obtained, before any planned radiation dose in excess of applicable limits specified in RA-EP-02620.
- b. Radiation dose of personnel who shall participate in reentry operations to determine additional personnel requirements.
- c. The adequacy of radiation survey instrumentation, equipment and any special dosimetry requirements.
- d. Primary and backup communications methods.
- e. Known or potential hazards to personnel.
- f. Additional security requirements for emergencies that involve a security event.
6.1.2 Authorize all entries into evacuated areas of DBNPS in accordance with RA-EP-02720, if recovery has been initiated.
6.1.3 Approve and prioritize all reentry team tasks. Initial reentry team goals typically include the following:
- a. Determination of the initial objectives required for recovery operations.
- b. Observation of hazards or potential hazards associated with the recovery.
- c. Obtaining a comprehensive radiation surveillance of DBNPS facilities.
- d. Isolating and posting of radiological and safety hazards.
I 6 RA7EP-02710 1 Revision 02 NOTE 6.1.4 Non-emergency limits for radiation dose shall be considered applicable for reentry activities, except under extreme circumstances. Refer to DB-HP-01201.
6.1.4 Review and approve, as appropriate, any radiation dose in excess of applicable limits.
6.1.5 Keep the Emergency Director or Recovery Director informed of significant events. 4 6.2 Emergencv RP Manager/OSC RP Coordinator The Emergency RP Manager and/or the OSC RP Coordinator should:
6.2.1 Establish guidelines to ensure that reentry operations are conducted in a manner to minimize radiation dose to personnel.
6.2.2 Provide radiological controls coverage for all reentry teams in accordance with RA-EP-02640.
6.2.3 Ensure that the OSC Briefer/Debriefer adequately briefs reentry personnel on radiological hazards before they enter the RRA using the Emergency Team Briefing Form, DBEP-024.
6.2.4 Ensure that the OSC Team Briefer/Debriefer is informed of any significant changes in conditions so that all subsequent teams have access to the most current information.
6.3 OSC Manager 6.3.1 Oversee the activities of the OSC in accordance with RA-EP-02410.
6.3.2 Update the Emergency Plant Manager or Recovery Manager periodically on current plant conditions and the status of the reentry teams.
7 RA-EP-02710 Revision 02 6.4 Assistant OSC Manager The Assistant OSC Manager should:
6.4.1 Designate members'of the reentry teams.
6.4.2 Reentry Teams shall consist of a minimum of two people:
- a. One member trained in radiation protection;
- b. The second member will depend on the specific tasks to be accomplished.
6.4.3 A Standby'Team shall be designated and briefed with the reentry team on known or potential hazards, and kept informed of the reentry team's location so that they can provide rescue ind first aid assistance at all times. The Standby Team shall consist of at least two members:
- a. One trained in radiation protection.
- b. One trained in first aid.
6.4.4 Ensure the OSC Team Briefer/Debriefer adequately briefs reentry personnel on the maintenance and/or operation objectives of the mission, unsafe conditions and appropriate safety precautions using the Emergency Team Briefing Form, DBEP-024.
6.4.5 After obtaining approval from the Emergency Plant Manager or Plant Recovery Manager, dispatch the Reentry Team(s).
6.4.6 Maintain communications with the reentry teams.
6.4.7 Keep the OSC Manager informed of reentry team activities.
6.4.8 Ensure the OSC Team Briefer/Debriefer interviews teams on their return using the Emergency Team Debriefing Form, DBEP-024.
6.5 OSC Team Briefer/Debriefer The OSC Team Briefer/Debriefer should:
6.5.1 Ensure that reentry teams are adequately briefed using the Emergency Team Briefing Form, DBEP-024:
- a. Areas to be surveyed.
- b. Anticipated routes to the area.
- c. Anticipated radiation and contamination levels expected.
- d. Required equipment.
- e. Shielding requirements and availability.
8 RA-EP-02710 Revision 02
- f. Protective clothing and equipment required (PCs, SCBA, etc.).
- g. Access Control procedures.
- h. Exposure control limits and personnel dosimetry required.
- i. Decontamination requirements.
- j. . Primary and backup communications methods.
- k. Known or potential hazards and appropriate safety precautions.
'I 6.5.2 Interview the team(s) on their return, and document all pertinent information on the Emergency Team Debriefing Form, DBEP-024.
6.5.3 Ensure that the team(s) are informed of any significant changes in conditions.
6.5.4 Report the results of the reentry to the OSC Manager or the RP Coordinator if the Recovery Organization is in place, for further dissemination to appropriate individuals.
6.6 Reentry Team(s)
Reentry Team(s) should:
6.6.1 Assemble all the necessary equipment according to the Emergency Team Briefing Form, DBEP-024 and verify operability of equipment. V
9 RA-EP-02710 Revision 02 WARNING 6.6.2 If dose rates encountered exceed the limits established during reentry planning, reentry personnel shall:
- 1. Exit the area immediately.
- 2. Return to a safe area.
- 3. Contact the OSC Manager for further instructions.
6.6.2 Enter the area when authorized by the Emergency Plant Manager or Recovery Manager.'
6.6.3 Conduct a radiation survey of the area in accordance to RA-EP-02640.
6.6.4 Perforni first aid and rescue operations, if necessary.
6.6.5 Assess the following items as directed:
- a. Condition of plant equipment and areas
- b. Potential for additional problems
- c. Consequences of damage which occurred during the emergency
- d. Accessibility of affected areas
- e. Radiological, toxic, structural or other hazards
- f. Other potential personnel or equipment hazards 6.6.6 Perform inspections, repairs and operations as directed.
6.6.7 Maintain communications with the Assistant OSC Manager or OSC RP Coordinator, providing observed conditions and dose rates.
6.6.8 Isolate and post appropriate areas with the proper radiation warning signs and barrier ropes as Radiation, High Radiation and/or Contamination areas.
6.6.9 Return to the OSC for debriefing after completion of assigned tasks.
I 10 RA.-EP-02710
' Revision 02 7.0 FINAL CONDITIONS This procedure should be terminated when:
7.1 Reentry operations have been completed and all reentry team members have been accounted for.
7.2 Debriefing of reentry personnel has been completed and documented.
7.3 Records generated during the emergency are forwarded to the Supervisor -
Emergency Preparedness after review by the Emergency RP Manager and OSC Manager.
7.4 Emergency equipment has been inventoried and deficiencies identified and reported to the Supervisor - Emergency Preparedness.
7.5 Procedural deficiencies have been identified and reported to the Supervisor -
Emergency Preparedness.
8.0 RECORDS 8.1 The following quality assurance records are completed by this procedure and shall be listed on the Nuclear Records List, captured, and submitted to Nuclear Records Management in accordance with NG-NA-00106.
8.1.1 None 8.2 The following non-quality assurance records are completed by this procedure and may be captured and submitted to Nuclear Records Management in accordance with NG-NA-00106.
8.2.1 None
I1 RA-EP-027 10 Revision 02 COMMITMENTS Step Number Reference Comments None None None END