MONTHYEARML24276A1002024-10-0202 October 2024 Email: Perry LRA - Requests for Confirmatory Information (RCI) ML24276A1282024-10-0202 October 2024 LRA - Requests for Additional Information - Round 1 (Set 3) - Email to Applicant ML24274A1482024-09-30030 September 2024 NRR E-mail Capture - Davis-Besse - RAI Re Relief Request L-23-214 ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24241A1012024-08-28028 August 2024 LRA - Requests for Additional Information - Round 1 (Set 2)_Email to Applicant ML24221A0082024-08-0707 August 2024 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Remove the Table of Contents from the Technical Specifications ML24204A0012024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information Vistraops Fleet Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Reports ML24192A2222024-07-0909 July 2024 LRA Changes - Selective Leaching Program (AMP XI.33) ML24192A2232024-07-0808 July 2024 License Renewal Clarification (AMP XI.33) ML24170B0562024-06-18018 June 2024 NRR E-mail Capture - Acceptance Review Results for Davis-Besse, Unit No. 1 - RR-A1 ISI Impracticality ML24144A1082024-05-22022 May 2024 Acceptance Review Adoption of TSTF-569, Revise Response Time Testing Definition (EPID L-2024-LLA-0059) - Email ML24103A1262024-05-0808 May 2024 Email to Phil Lashley Decision on the Exemption Request for Perry ML24127A1992024-05-0606 May 2024 NRR E-mail Capture - (External_Sender) Perry License Renewal Scoping and Screening Breakout Question B.2.24 (Partial TRP-55) ML24103A1272024-05-0303 May 2024 Email to Phil Lashley Availability of Environmental Assessment for the Perry Exemption ML24120A3222024-04-26026 April 2024 Response from State of Oh Regarding Review of Environmental Assessment for Perry HI-STORM Exemption Request ML24120A3212024-04-25025 April 2024 Email to State of Oh Requesting Review of EA for Perry HI-STORM Exemption Request ML24061A1002024-03-29029 March 2024 Energy Harbor Fleet- Closing of Transaction Between Vistra Operations Company LLC and Energy Harbor Nuclear Corporation (Email) ML24080A3922024-03-20020 March 2024 NRR E-mail Capture - Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Power Station Unit No. 1, and Perry Nuclear Power Plant, Unit No. - Acceptance of Requested Licensing Action Exemption for Final Safety Analysis Report Update ML24074A4272024-03-14014 March 2024 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Inservice Inspection Alternative VR-9 ML24060A0392024-02-28028 February 2024 Email SUNSI Action: Perry Nuclear Power Plant, Unit 1, ISFSI, Request for Specific Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24052A0092024-02-16016 February 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-264 ML24017A2392024-01-17017 January 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Valve Testing Frequency Alternative VR-9 ML23226A0742023-08-14014 August 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Remove the Table of Contents from the Technical Specifications ML23180A2322023-06-29029 June 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-276-A, Revision 2 ML23129A3122023-05-0909 May 2023 NRR E-mail Capture - Beaver Valley Unit 2 - Verbal Authorization of Alternative Request, 2-TYP-4-RV-06 ML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23125A1462023-05-0505 May 2023 NRR E-mail Capture - Beaver Valley - RAI Regarding Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23125A1602023-05-0505 May 2023 NRR E-mail Capture - Correction to Beaver Valley - RAI Regarding Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23122A0342023-05-0202 May 2023 NRR E-mail Capture - Beaver Valley - Request for Additional Information Regarding Unit 1 - 180 Day Steam Generator Tube Inspection Report ML23095A3442023-04-0505 April 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan ML23089A1252023-03-30030 March 2023 NRR E-mail Capture - Beaver Valley Upcoming Steam Generator Tube Inservice Inspection ML23086B9862023-03-27027 March 2023 NRR E-mail Capture - Davis-Besse, Unit No. 1 - Acceptance Review Results for Davis-Besse, Unit No. 1 - Proposed Alternative Request RP-5 ML23079A1202023-03-20020 March 2023 NRR E-mail Capture - Acceptance Review for Beaver Valley 1 & 2 Exemption from Specific Provisions in 10 CFR 50 Appendix H ML23065A0782023-03-0303 March 2023 Final RAIs Regarding the Beaver Valley Emergency LAR (EPID L-2023-LLA-002) - Email ML23033A0322023-02-0101 February 2023 NRR E-mail Capture - Request for Additional Information for Davis-Besse's 2022 Steam Generator Inspection Report (L-2022-LRO-0115) ML23010A2892023-01-10010 January 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment Regarding Revising the Methodology Used for Flood Hazard Analysis ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML22321A2392022-11-17017 November 2022 NRR E-mail Capture - (External_Sender) Beaver Valley Power Station, Units 1&2 - Clarification on LAR to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22312A5912022-11-0808 November 2022 NRR E-mail Capture - Beaver Valley Power Station, Units 1&2 - Request for Additional Information LAR to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22273A1132022-09-30030 September 2022 NRR E-mail Capture - Acceptance of Requested Licensing Action to Add Full Spectrum LOCA Methodology to COLR ML22266A1102022-09-23023 September 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding July 21, 2022, Request for Withholding Information from Public Disclosure ML22277A5122022-09-19019 September 2022 NRR E-mail Capture - (External_Sender) Eh Response to Corrected SE Associated with Beaver Valley Amendments 315 and 205 Changes to the EPP ML22241A0362022-08-29029 August 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-541, Revision 2 ML22238A2812022-08-25025 August 2022 Request for Additional Information for Beaver Valley Unit 2 - 2R22 Steam Generator 180 Day Report ML22202A4642022-06-29029 June 2022 Emergency Plan Safety Evaluation ML22178A1322022-06-24024 June 2022 Request for Additional Information for Beaver Valley Unit 2 Steam Generator Inspection Report - Fall 2021 Refueling Outage ML22173A0402022-06-21021 June 2022 NRR E-mail Capture - Acceptance of Requested Licensing Action Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22167A1002022-06-16016 June 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (EPIDs No.L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML22164A8572022-06-13013 June 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan ML22147A0392022-05-27027 May 2022 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Pennsylvania Regarding a Beaver Valley, Units 1 & 2 Amendment - Revise TS 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Separation Instrumentation 2024-09-06
[Table view] |
Text
From: Lentz, Thomas A (EH) <talentz@firstenergycorp.com>
Sent: Thursday, February 27, 2020 11:53 AM To: Wall, Scott Cc: Salgado, Nancy; Vaidya, Bhalchandra; Hamilton, David B (EH); Joyce, Brendan; Stenger, Daniel F.; Desai, Sachin; david.repka3@gmail.com; lbeckerman@akingump.com; Benyak, Darin M (EH); Emley, James E (EH)
Subject:
[External_Sender] Completion of License Transfer for the Beaver Valley, Davis-Besse and Perry Nuclear Units Scott:
This message is to inform the NRC that the actions required to complete the transfer of the Beaver Valley, Davis-Besse and Perry nuclear units have been completed today, effective immediately.
Consistent with the NRCs approval order dated December 2, 2019 (Order), the direct transfers of the operating authority for the facilities from FirstEnergy Nuclear Operating Company (FENOC) to Energy Harbor Nuclear Corp., and the ownership of the facilities from FirstEnergy Nuclear Generation, LLC (FENGen) to Energy Harbor Nuclear Generation LLC, were completed. The indirect transfer of ownership of the facilities from FirstEnergy Corp./FirstEnergy Solutions Corp. to Energy Harbor Corp. as the ultimate parent company was also completed. It is requested that the NRC issue the conforming license amendments consistent with the Order.
Energy Harbor Nuclear Corp. adopts and endorses the outstanding commitments, licensing actions, applications and similar items on the dockets submitted by FENOC on the behalf of the licensees.
Energy Harbor Nuclear Corp. requests NRC continuation of the regulatory reviews and actions on these items.
Any questions, please call.
Tom Thomas Lentz Energy Harbor Nuclear Corporation Manager, Nuclear Licensing & Regulatory Affairs 341 White Pond Drive Akron, Ohio 44320 talentz@firstenergycorp.com Work: (330) 315-6810 Mobile: (440) 666-8499 The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message.