Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML23095A3442023-04-0505 April 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan Project stage: Acceptance Review ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate Project stage: Approval 2023-04-05
[Table View] |
Similar Documents at Perry |
---|
Category:E-Mail
MONTHYEARML24017A2392024-01-17017 January 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Valve Testing Frequency Alternative VR-9 ML23226A0742023-08-14014 August 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Remove the Table of Contents from the Technical Specifications ML23180A2322023-06-29029 June 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-276-A, Revision 2 ML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23095A3442023-04-0505 April 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan ML23010A2892023-01-10010 January 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment Regarding Revising the Methodology Used for Flood Hazard Analysis ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML22241A0362022-08-29029 August 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-541, Revision 2 ML22167A1002022-06-16016 June 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (EPIDs No.L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML22020A0722022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Alternative Requests Regarding VR-10 and VR-11 Inservice Valve Testing ML22020A0702022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Inservice Inspection Alternative IR-063 ML22020A0712022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Alternative VR-12 ML21140A2802021-05-20020 May 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (Epids: L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML21110A6852021-04-19019 April 2021 NRR E-mail Capture - Final RAI - Perry - Request to Review the Emergency Plan ML21084A2562021-03-25025 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-002, Revision 1 ML21077A0012021-03-17017 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Correction to Acceptance of Relief Requests Regarding VR-3 VR-4, VR-5, VR-6, VR-7, and VR-8 Valve Testing Extensions (Epids: L-2021-LLR-0007 Through L-2021-LLR-0012) ML21070A4042021-03-11011 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant -Acceptance of License Amendment Request to Adopt TSTF-230, Revision 1 ML21063A1922021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-4, Revision 0 ML21063A1912021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-3, Revision 0 ML21063A1932021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-5, Revision 0 ML21063A1952021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-6, Revision 0 ML21063A1982021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-8, Revision 0 ML21063A1962021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-7, Revision 0 ML21063A1342021-03-0404 March 2021 E-Mail Concurrence - SR-2 SE ML21050A1032021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-3, Rev. 0 and VR-5, Rev. 0 ML21050A1072021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-7, Rev. 0 ML21050A1112021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-4, Rev. 0 and VR-6, Rev. 0 ML21054A1802021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests Regarding VR-4, VR-6, and VR-8 Valve Testing Extensions ML21054A1782021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Request Regarding VR-7 Check Valve Testing Extension ML21049A2702021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request SR-2, Rev. 0 (EPID: L-2021-LLR-0005) (2nd Round RAI) ML21054A1742021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests Regarding VR-3 and VR-5 Valve Testing Extensions ML21032A3422021-02-0101 February 2021 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Alternative Request SR-2, Rev. 0 ML21027A2032021-01-27027 January 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Request Regarding Snubber Testing Extension ML21021A2602021-01-21021 January 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request Regarding Residual Heat Removal Shutdown Cooling Subsystems ML21011A2732021-01-11011 January 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Review the Emergency Plan ML20325A2782020-11-20020 November 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Part 73 Force-on-Force Exemption ML20289A3562020-10-14014 October 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Regarding DC Electrical Systems Consistent with TSTF-582 ML20281A3692020-10-0505 October 2020 Energy Harbor Fleet, Results of Acceptance Review Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, EPID-l-2020-LLR-0132 ML20289A0992020-10-0505 October 2020 NRR E-mail Capture - Energy Harbor Fleet, Results of Acceptance Review Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, EPID-l-2020-LLR-0132 ML20289A1012020-10-0505 October 2020 NRR E-mail Capture - Final 2nd Round RAI - Perry Request for Relief - Proposed Alternative Request IR-056, Rev. 3 ML20241A0092020-08-27027 August 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Requested Licensing Action, One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic ML20241A0102020-08-27027 August 2020 NRR E-mail Capture - (External_Sender) State Notification of Amendments to Shearon Harris, Unit 1 - Revise TS for the Adoption of 10 CFR 50, Appendix J, Option B for Type B and C Testing and for Permanent Extension of Type a, B and C ML20191A0192020-07-0101 July 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Extension to License Expiration Date by Recapturing Low-Power Testing Time ML20134J0842020-05-13013 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant -Acceptance of License Amendment Request to Revise Technical Specifications Regarding DC Electrical Systems Consistent with TSTF-500, Revision 2 ML20132A0222020-05-0808 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Request Regarding Impracticality for Inservice Inspection for Certain Welds ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML20127H8692020-05-0606 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request IR-054, Rev. 2 ML20111A2802020-04-20020 April 2020 NRR E-mail Capture - Perry Nuclear Power Plant -Acceptance of License Amendment Request to Extend License Expiration Date by Recapturing Low-Power Testing Time 2024-01-17
[Table view] |
Text
From: Scott Wall Sent: Wednesday, April 5, 2023 3:44 PM To: Lashley, Phil H (EH)
Cc: Morgan, Jeffrey D.
Subject:
Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan (EPID No. L-2023-LLL-0007)
Dear Mr. Lashley:
By letter dated November 1, 2021 (Agencywide Documents Access and Management System Accession No. ML21305A781), in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.54(bb), Energy Harbor Nuclear Corp (EHNC, the licensee) provided the irradiated fuel management plan (IFMP) for Perry Nuclear Power Plant (PNPP). By letter dated March 29, 2021 (ML21088A295), EHNC submitted the decommissioning trust fund (DTF) financial status report in accordance with 10 CFR 50.75(f)(1). In accordance with 10 CFR 50.75(f)(3), the licensee provided the PNPP site-specific decommissioning cost estimate (DCE) as Enclosure C of the March 29, 2021, letter. These submittals address how EHNC will meet the requirements for PNPP set forth in 10 CFR 50.54(bb) and 10 CFR 50.75(f)(3).
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this application. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. .
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed exemption in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> to complete. The NRC staff expects to complete this review by October 2023. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.
If you have any questions, please contact me at (301) 415-2855 or e-mail at Scott.Wall@nrc.gov.
Scott P. Wall, LSS BB, BSP Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301.415.2855 Scott.Wall@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 2030 Mail Envelope Properties (SA0PR09MB60582ADF9C5B218D5818BCA892909)
Subject:
Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan (EPID No. L-2023-LLL-0007)
Sent Date: 4/5/2023 3:44:02 PM Received Date: 4/5/2023 3:44:03 PM From: Scott Wall Created By: Scott.Wall@nrc.gov Recipients:
"Morgan, Jeffrey D." <jdmorgan@energyharbor.com>
Tracking Status: None "Lashley, Phil H (EH)" <phlashley@energyharbor.com>
Tracking Status: None Post Office: SA0PR09MB6058.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3347 4/5/2023 3:44:03 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: