MONTHYEARML24276A1002024-10-0202 October 2024 Email: Perry LRA - Requests for Confirmatory Information (RCI) ML24276A1282024-10-0202 October 2024 LRA - Requests for Additional Information - Round 1 (Set 3) - Email to Applicant ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24241A1012024-08-28028 August 2024 LRA - Requests for Additional Information - Round 1 (Set 2)_Email to Applicant ML24204A0012024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information Vistraops Fleet Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Reports ML24192A2222024-07-0909 July 2024 LRA Changes - Selective Leaching Program (AMP XI.33) ML24192A2232024-07-0808 July 2024 License Renewal Clarification (AMP XI.33) ML24103A1262024-05-0808 May 2024 Email to Phil Lashley Decision on the Exemption Request for Perry ML24127A1992024-05-0606 May 2024 NRR E-mail Capture - (External_Sender) Perry License Renewal Scoping and Screening Breakout Question B.2.24 (Partial TRP-55) ML24103A1272024-05-0303 May 2024 Email to Phil Lashley Availability of Environmental Assessment for the Perry Exemption ML24120A3222024-04-26026 April 2024 Response from State of Oh Regarding Review of Environmental Assessment for Perry HI-STORM Exemption Request ML24120A3212024-04-25025 April 2024 Email to State of Oh Requesting Review of EA for Perry HI-STORM Exemption Request ML24061A1002024-03-29029 March 2024 Energy Harbor Fleet- Closing of Transaction Between Vistra Operations Company LLC and Energy Harbor Nuclear Corporation (Email) ML24080A3922024-03-20020 March 2024 NRR E-mail Capture - Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Power Station Unit No. 1, and Perry Nuclear Power Plant, Unit No. - Acceptance of Requested Licensing Action Exemption for Final Safety Analysis Report Update ML24074A4272024-03-14014 March 2024 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Inservice Inspection Alternative VR-9 ML24052A0092024-02-16016 February 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-264 ML24017A2392024-01-17017 January 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Valve Testing Frequency Alternative VR-9 ML23226A0742023-08-14014 August 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Remove the Table of Contents from the Technical Specifications ML23180A2322023-06-29029 June 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-276-A, Revision 2 ML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23095A3442023-04-0505 April 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan ML23010A2892023-01-10010 January 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment Regarding Revising the Methodology Used for Flood Hazard Analysis ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML22241A0362022-08-29029 August 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-541, Revision 2 ML22167A1002022-06-16016 June 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (EPIDs No.L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML22020A0722022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Alternative Requests Regarding VR-10 and VR-11 Inservice Valve Testing ML22020A0702022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Inservice Inspection Alternative IR-063 ML22020A0712022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Alternative VR-12 ML21140A2802021-05-20020 May 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (Epids: L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML21110A6852021-04-19019 April 2021 NRR E-mail Capture - Final RAI - Perry - Request to Review the Emergency Plan ML21084A2562021-03-25025 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-002, Revision 1 ML21077A0012021-03-17017 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Correction to Acceptance of Relief Requests Regarding VR-3 VR-4, VR-5, VR-6, VR-7, and VR-8 Valve Testing Extensions (Epids: L-2021-LLR-0007 Through L-2021-LLR-0012) ML21070A4042021-03-11011 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant -Acceptance of License Amendment Request to Adopt TSTF-230, Revision 1 ML21063A1922021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-4, Revision 0 ML21063A1912021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-3, Revision 0 ML21063A1932021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-5, Revision 0 ML21063A1952021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-6, Revision 0 ML21063A1982021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-8, Revision 0 ML21063A1962021-03-0404 March 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Verbal Authorization of Request VR-7, Revision 0 ML21063A1342021-03-0404 March 2021 E-Mail Concurrence - SR-2 SE ML21050A1032021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-3, Rev. 0 and VR-5, Rev. 0 ML21050A1072021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-7, Rev. 0 ML21050A1112021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-4, Rev. 0 and VR-6, Rev. 0 ML21054A1802021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests Regarding VR-4, VR-6, and VR-8 Valve Testing Extensions ML21054A1782021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Request Regarding VR-7 Check Valve Testing Extension ML21049A2702021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request SR-2, Rev. 0 (EPID: L-2021-LLR-0005) (2nd Round RAI) ML21054A1742021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests Regarding VR-3 and VR-5 Valve Testing Extensions ML21032A3422021-02-0101 February 2021 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Alternative Request SR-2, Rev. 0 2024-09-06
[Table view] |
Text
From: Bensi, Mark J To: Siva Lingam
Subject:
[External_Sender] Perry LRA Changes - Selective Leaching Program Date: Tuesday, July 9, 2024 5:09:52 PM
- Siva,
Thank you again for coordinating todays selective leaching discussion. We found it beneficial and productive. As discussed with you and your staff, we plan to develop and submit an additional supplement to our application to address the questions raised by your technical staff. This supplement will be separate from our Supplement 3 scheduled for submittal later this month. This additional supplement will segregate the selective leaching program into a one-time program consistent with the GALL and a new ongoing plant-specific program that will address the material/environment combinations for which Perry has identified selective leaching. This new supplement will present the specific material/environment combinations within the scope of the new ongoing plant-specific program. We intend to provide the sample population requirements for the material/environment combination within the plant-specific program. The plant-specific program will address (1) gray cast iron material exposed to raw water, (2) Gray cast iron material exposed to soil and (3) ductile iron material exposed to soil.
As part of this supplement, we will supersede the changes made to the selective leaching program presented in the July 2024 annual update to our application. Please note that the one-time selective leaching program will exclude the above material/environment combinations as they will be managed by the new plant specific selective leaching program.
We will develop a schedule for development and submittal of this additional supplement and communicate this to you for planning purposes.
If you have any questions, please let me know.
Thank you again,
Mark J. Bensi Project Manager, Perry License Renewal Perry Nuclear Engineering Department Perry Nuclear Power Plant
Electronic Confidentiality and Privacy Notice: This e-mail, and any attachments, contains information that may be confidential, constitutes non-public information, may be protected by electronic communication privacy laws, or is a privileged communication (attorney-client or otherwise). The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, use, disclosure, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify the sender immediately by reply e-mail or by phone, and destroy all copies of the original message.