ML18137A429

From kanterella
Revision as of 00:36, 3 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Tp 2017-301 Exam Administrative Items (ADAMS-2D)
ML18137A429
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 05/17/2018
From:
NRC/RGN-II
To:
Florida Power & Light Co
References
Download: ML18137A429 (30)


Text

L-17-1 NRC EXAM SECURE INFORMATION ES-301 Transient and Event Checklist Form ES-301-5 Facility: Turkey Point Units 3 & 4 Date of Exam: 10/23/2017 Operating Test No.: 2017-301 A E Scenarios P V P E N2 N3 N4 N5 N7 T M L N O I CREW POSITION CREW CREW CREW CREW I T T N POSITION POSITION POSITION POSITION C A I A T S A B S A B S A B S A B S A B M R T O R T O R T O R T O R T O L N Y U T P O C P O C P O C P O C P O C P M(*)

E R I RX 4 5 5 3 1 NOR 1* 1 1 I/C 2,3,5 2,4 1,2, 9 4 SROI-1 3,4 MAJ 6 6 6 3 2 TS 1,4 1,2, 4 2 3

RX 4 1 4 3 1 NOR 1* 1 1 SROI-2 I/C 2,3,5 3,5 1,2, 9 4 3,5 MAJ 6 7 6 3 2 TS 1,4 2,3 4 2 RX 4 5 1 3 1 NOR 1* 1 1 SROI-3 I/C 2,3,5 1,2, 3,5 9 4 3,4 MAJ 6 6 7 3 2 TS 1,4 1,2, 4 2 3

RX 5 1 4 3 1 NOR 3* 1 1 I/C 2,4 4,5, 1,2, 9 4 SROI-4 6 3,5 MAJ 6 7 6 3 2 TS 2,4 2,3 4 2 RX 5 5 4 3 1 NOR 1* 1 1 I/C 2,3, 2,4 1,2, 9 4 SROI-5 4 3,5 MAJ 6 6 6 3 2 TS 1,2 2,3 4 2 ES-301-5 pg 1 of 3

L-17-1 NRC EXAM SECURE INFORMATION ES-301 Transient and Event Checklist Form ES-301-5 RX 5 5 2 1 NOR 4 1 1 SROI-6 I/C 2,3 1,2, 2,4 8 4 3,4 MAJ 6 6 6 3 2 TS 1,2 2 2 RX 1 4 2 1 NOR 4 1 1 SROI-7 I/C 2,3 3,4, 3,5 8 4 5,6 MAJ 6 7 6 3 2 TS 2,4 2 2 RX 5 1 2 1 NOR 4 1 1 SROI-8 I/C 2,3 2,4 3,4, 8 4 5,6 MAJ 6 6 7 3 2 TS 2,4 2 2 RX 5 4 2 1 NOR 1 1 1 I/C 1,2, 4,6 3,5 8 4 SROI-9 3,4 MAJ 6 7 6 3 2 TS 1,2 2 2 RX 5 4 2 1 NOR 5 1 1 I/C 1,3 1,2, 3,5 8 4 SROI-10 3,4 MAJ 6 6 6 3 2 TS 1,2, 2 2 3

ES-301-5 pg 2 of 3

L-17-1 NRC EXAM SECURE INFORMATION ES-301 Transient and Event Checklist Form ES-301-5 RX 4 1 1 NOR 5 5 2 1 RO-1 I/C 1,5 1,3 1,3 6 4 MAJ 6 6 6 3 2 RX 4 1 1 NOR 1 4 2 1 RO-2 I/C 1,5 4,6 1,2 6 4 MAJ 6 7 6 3 2 RX 4 1 1 NOR 5 1 2 1 RO-3 I/C 1,5 1,3 4,6 6 4 MAJ 6 6 7 3 2 RX 1 1 1 NOR 5 4 2 1 RO-4 I/C 1,3 3,5 1,2 6 4 MAJ 6 7 6 3 2 RX 5 1 1 NOR 5 4 2 1 RO-5 I/C 2,4 1,3 1,2 6 4 MAJ 6 6 6 3 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional I/C malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For new reactor facility licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301-5 pg 3 of 3

L-17-1 NRC EXAM SECURE INFORMATION ES-301 Competencies Checklist Form ES-301-6 Facility: Turkey Point Units 3 & 4 Date of Examination: 10/23/2017 Operating Test No.: 2017-301 APPLICANTS SRO-I SRO-I SRO-I RO RO RO BOP BOP BOP Competencies SCENARIO SCENARIO SCENARIO N2 N3 N4 N5 N7 N2 N3 N4 N5 N7 N2 N3 N4 N5 N7 Interpret/Diagnose Events and 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 Conditions Comply with and 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 Use Procedures (1)

Operate Control 2,4 2,4 2,4 1,3 3,4 1,3 1,3 1,3 1,4 1,2 N/A N/A N/A N/A N/A Boards (2) 5,6 5,6 5,6 5,7 5,6 4,6 5,6 5,6 6,7 4,6 Communicate 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 1-6 1-6 1-6 1-7 1-6 and Interact Demonstrate 1-6 1-6 1-6 1-7 1-6 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Supervisory Ability (3)

Comply with and 1,2, 1,4 1,2 2,4 2,3 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Use TS (3) 3 Notes:

(1) Includes TS compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Forms ES-303-1 and ES-303-3 describe the competency rating factors.)

ES-301-6 pg 1 of 1

AUG 07201?

L-2017-143 10 CfR2.390 PPL Joseph Viera Chief Examiner, Region II U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Initial Operator Licensing Examination 75 Day Submittal In accordance with the requirements ofNUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 11 Florida Power and Light (FPL) is submitting herein the following initial licensing examination checklists, outlines, scenarios, and JPMs for the Turkey Point Nuclear Plant for the October 2017 Operator Licensing Examination:

ES-201-2 Examination Outline Quality Checklist ES-201-3 Examination Security Agreement (copy)

ES-301-l Administrative Topics Outlines (RO) and (SRO-I)

ES-301-2 Control Room/In-Plant Systems Outlines (RO) and (SRO-1)

ES-301-3 Operating Test Quality Checklist ES-301-4 Simulator Scenario Quality Checklist ES-301-5 Transient and Event Checklist ES-301-6 Competencies Checklist ES-401-4 Record of Rejected K/As ES-401-5 Written Examination Key with Reference For Each Question (100 Questions)

ES-40 1-6 Written Examination Quality Checklist ES-C-I Job Performance Measure Worksheet (twenty equivalent facility JPMs forms)

ES-D-ls Scenario Outlines (seven)

ES-D-2s Required Operator Actions (seven equivalent facility Simulator Exercise Guides)

ES-20 1 Attachment 3 Reference Material Guidelines for Initial Licensing Examinations Pursuant to the provisions of N1JREG 1021, Revision 11, the enclosed material shall be withheld from public disclosure until after the examinations are complete.

Should there be any questions, please contact Mark Wilson at (305) 246-6691.

Sincerely, Brian Stamp Plant General Manager Turkey Point Nuclear Plant Enclosure cc: Chief, Operations Branch, Division of Reactor Safety, Region II, w/o enclosure Regional Administrator, Region II, USNRC, w/o enclosure Document Control Desk, USNRC, Washington, D.C., w/o enclosure Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant, w/o enclosure Florida Power & Light Company 9760 SW. 344t] Street Homestead, FL 33035

OCT 0 5201?

L20i7-i78 ERL Joseph Viera, Chief Examiner, Region 11 U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Initial Operator Licensing Examination Final Submittal In accordance with the requirements ofNUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 11 florida Power and Light (fPL) is submitting herein the following initial license examination checklists, outlines, scenarios, and JPMs for the Turkey Point Nuclear Plant for the October 2017 Operator Licensing Examination:

ES-201-2 Examination Outline Quality Checklist ES-201-3 Examination Security Agreement (copy)

ES-30l-1 Administrative Topics Outlines (RO) and (SRO-1)

ES-301-2 Control Room/In-Plant Systems Outlines (RO) and (SRO-I)

ES-301-3 Operating Test Quality Checklist ES-301-4 Simulator Scenario Quality Checklist ES-301-5 Transient and Event Checklist ES-301-6 Competencies Checklist ES-40l-4 Record of Rejected K/As ES-401-5 Written Examination Key with Reference for Each Question (100 Questions)

ES-401-6 Written Examination Quality Checklist SRO Master Written Examination with Answer Key SRO Master Written Exam Reference Package RO Master Written Examination with Answer Key RO Master Written Exam Reference Package ES-C-i Job Performance Measure Worksheet (twenty equivalent facility JPMs forms)

ES-D-ls Scenario Outlines (six)

ES-D-2s Required Operator Actions (six equivalent facility Simulator Exercise Guides)

Pursuant to the provisions of NUREG 1021, Revision 11, the enclosed material shall be withheld from public disclosure until after the examinations are complete.

Should there be any questions, please contact Mark Wilson at (305) 246-6691.

Sincerely, Thomas Summers Regional Vice President, Southern Region Turkey Point Nuclear Plant Enclosure cc: Chief, Operations Branch, Division of Reactor Safety, Region II, w/o enclosure Regional Administrator, Region II, USNRC, w/o enclosure Document Control Desk, USNRC, Washington, D.C., w/o enclosure Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant, w/o enclosure Florida Power & Light Company 9760 SW. 344th Street I lornestead, FL 33035