Receipt of Davis-Besse Reply to non-cited Violation in IR 04-14
ML050810071
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/18/2005
From: Reynolds S
Division Reactor Projects III
To: Bezilla M
FirstEnergy Nuclear Operating Co
References
IR-04-014
Download: ML050810071 (4)


Text

March 18, 2005 Mr. Mark B. Bezilla Vice President-Nuclear, Davis-Besse FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

RECEIPT OF DAVIS-BESSE REPLY TO NON-CITED VIOLATION IN NRC INSPECTION REPORT NO. 05000346/2004014 (NCV 2004014-02)

Dear Mr. Bezilla:

This will acknowledge receipt of your letter dated December 8, 2004, in response to our letter dated November 8, 2004, regarding corrective actions being taken with respect to a Non-Cited Violation (NCV) documented in Inspection Report 05000346/2004014 at the Davis-Besse Nuclear Power Station for inadequate corrective actions associated with repetitive operational performance issues. Due to the repetitive nature of the operational performance issues, we requested that you provide, within 30 days of the date of the November 8, 2004 letter, a written response detailing the corrective actions that had been implemented to avoid further similar violations and the basis for your belief that these corrective actions would be effective at preventing future operations department performance errors. In addition we requested your assessment of the impact that the deferral of corrective actions and effectiveness reviews has had on performance improvement in operations.

In your response to NCV 05000346/2004014-02, you accepted the NCV and described the corrective actions that had been implemented to avoid further similar violations. Additionally, your response included the basis for the belief that these corrective actions would be effective at preventing future operations department performance errors and an assessment of the impact that the deferral of corrective actions and effectiveness reviews has had on performance improvement in operations. You stated that the actions taken constituted one-time actions and are considered complete.

We have reviewed your corrective action and have no further questions at this time. These corrective actions will be examined during future inspections.

Sincerely,

/RA/

Steven A. Reynolds, Chairman Davis-Besse Oversight Panel Docket No. 50-346 License No. NPF-3 See Attached Distribution

DOCUMENT NAME: E:\Filenet\ML050810071.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII NAME MPhillips:dtp CLipa*MPhillips SReynolds for DATE 03/18/05 03/18/05 03/18/05 OFFICIAL RECORD COPY

M. Bezilla cc w/encl: The Honorable Dennis Kucinich G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC L. Myers, Chief Operating Officer, FENOC Plant Manager Manager - Regulatory Compliance M. OReilly, Attorney, FirstEnergy Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Board of County Commissioners of Lucas County J. Papcun, President, Ottawa County Board of Commissioners D. Lochbaum, Union Of Concerned Scientists J. Riccio, Greenpeace P. Gunter, N.I.R.S.

M. Bezilla -3 ADAMS Distribution:

GYS SPS1 RidsNrrDipmIipb GEG KGO CST1 CAA1 C. Pederson, DRS (hard copy - IRs only)

DRPIII DRSIII PLB1 JRK1 DB0350 WDL (IRs only)

ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)