Letter Sequence Acceptance Review |
---|
TAC:MF6061, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B (Open) |
|
|
|
---|
Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24234A2772024-08-21021 August 2024 NRR E-mail Capture - Final RAI - Constellation Energy, LLC - Fleet Request - Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031) ML24240A1902024-08-12012 August 2024 E-mail (8/12/2024) from R. Reynolds (CEG) to R. Guzman (NRC) - Corrected TS Pages for LAR TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24213A2202024-07-31031 July 2024 Updated Change in Estimated Review Schedule Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24197A0092024-07-15015 July 2024 Acceptance Review Determination for LAR to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24156A0082024-05-31031 May 2024 NRR E-mail Capture - Constellation Energy, LLC - Fleet Request - Acceptance of Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24008A0592024-01-0808 January 2024 E-mail Dated 1-8-2024 from R. Guzman to R. Reynolds Correct TS Page 204 for License Amendment No. 250 Adoption of TSTF-505 ML24008A2622024-01-0808 January 2024 Acceptance Review Determination for Relief Request I5R-12, Concerning Installation of a FSWOL on RPV Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23255A2872023-09-12012 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative to Use the Successive Inspection Requirements of BWRVIP-75-A ML23237B3972023-08-24024 August 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative Request to Use Updated BWRVIP Guidelines ML23205A2432023-07-19019 July 2023 NRC Staff Follow-up Question on Audit Question 18 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/19/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23205A2412023-07-11011 July 2023 NRC Staff Follow-up Comments on Audit Questions 6a, 6b, and 6c TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/11/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23205A2422023-07-11011 July 2023 NRC Staff Follow-up Comments on Audit Questions 17 and 19 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/11/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23209A7692023-06-14014 June 2023 Draft Audit Results File TSTF-505 and 50.69 (E-mail Dated 6/14/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23209A7672023-06-13013 June 2023 Share File Observations on Response to Question 06 and 22 TSTF-505 and 50.69 (E-mail Dated 6/13/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23149A0012023-05-29029 May 2023 Audit Agenda TSTF-505 and 50.69 (E-mail Dated 5/29/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23142A0222023-05-22022 May 2023 Regulatory Audit Questions (PRA) TSTF-505 and 50.69 (E-mail Dated 5/22/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23118A3882023-04-28028 April 2023 Regulatory Audit Questions TSTF-505 and 50.69 (E-mail Dated 4/28/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23104A3472023-04-14014 April 2023 Verbal Authorization for Relief Request I5R-14, Proposed Alternative Associated with N2E Dissimilar Metal Weld Overlay Repair with Laminar Indication ML23093A1782023-04-0303 April 2023 E-mail from T. Loomis to R. Guzman Proposed Alternative to Utilize Specific Provisions of Code Case N-716-3 ML23090A1302023-03-31031 March 2023 Verbal Authorization for Relief Request I5R-11, Proposed Alternative Repair of Recirculation Inlet Nozzle N2E Dissimilar Metal Weld ML23087A2912023-03-28028 March 2023 Request for Additional Information (3/28/2023 E-mail) - Proposed Emergent I5R-11 Alternative Associated with a Weld Overlay on RPV Recirculation Nozzle N2E DM Weld ML23061A0522023-03-0202 March 2023 Request for Additional Information (3/2/2023 E-mail) - Proposed Alternative Associated with a Weld Overlay Repair to the Torus ML23047A3832023-02-15015 February 2023 (2-15-2023 Email from J. Nelson to R. Guzman) Long Island Power Authority and Long Island Lighting Company Request for Threshold Determination ML23033A0142023-02-0202 February 2023 E-mail Dated 2-2-2023 from R.Guzman to R.Reynolds Correction to Error in NMP1 TSTF-505 and 50.69 Audit Plan ML23019A3092023-01-19019 January 2023 Acceptance Review Determination License Amendment Request to Adopt 10 CFR 50.69 Categorization Process ML23019A3032023-01-19019 January 2023 Acceptance Review Determination License Amendment Requets to Adopt TSTF-505 ML23013A3332023-01-13013 January 2023 Acceptance Review Determination Proposed Alternative for Weld Overlay Repair to the Torus ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22342B1462022-11-21021 November 2022 NRR E-mail Capture - Acceptance Review for TSTF 295A ML22314A2262022-11-10010 November 2022 E-mail Dated 11/10/2022 Relief Request Associated with Pump Periodic Verification Tests of Core Spray System Pumps ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22252A1522022-09-0909 September 2022 Acceptance Review Determination Partial Adoption of TSTF-568 to Revise TS 3.3.1 for Primary Containment Oxygen Concentration ML22207A0192022-07-26026 July 2022 (E-mail Dated 7/26/2022) Setup of Online Reference Portal for Revision to Alternative Source Term Calculation for MSIV and Non-MSIV Leakage ML22207A0122022-07-26026 July 2022 Acceptance Review Determination Revision to Alternative Source Term Analysis for Containment Leakage ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22194A9412022-07-13013 July 2022 Request for Additional Information Relief Request CS-PR-02 (7/13/2022 e-mail) ML22173A0802022-06-22022 June 2022 E-mail Dated 6/22/2022, Acceptance of Requested License Amendment Request to Revise Surveillance Requirements to Reduce Number of Fast Starts of EDGs ML22075A0362022-03-16016 March 2022 Acceptance Review Determination - Relief Request CS-PR-02 Associated with Pump Periodic Verification Test of Core Spray System Pumps, E-mail Dated 3/16/2022 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles 2024-09-06
[Table view] |
Text
NRR-PMDAPEm Resource From: Vaidya, Bhalchandra Sent: Monday, July 27, 2015 2:03 PM To: Mozafari, Brenda
Subject:
FW: Nine Mile Point Nuclear Station Unit No. 1; , TAC Nos. MF6061 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: License Amendment Request- Adoption of TSTF-425, Rev 3 ADAMSAccessionNumber:ML15128A299 ADAMSVersionSeriesId: {1662187A-0F93-412A-B759-B4CA0533B72C}
fyi From: Vaidya, Bhalchandra Sent: Friday, May 08, 2015 11:16 AM To: Villar, Enrique:(GenCo-Nuc) (Enrique.Villar@exeloncorp.com); David.Gudger@exeloncorp.com; Reynolds, Ronnie J.:(GenCo-Nuc) (Ronnie.Reynolds@exeloncorp.com)
Cc: Snyder, Pete; Rosenberg, Stacey; Elliott, Robert; ONeal, Daniel; Dudek, Michael
Subject:
Nine Mile Point Nuclear Station Unit No. 1; , TAC Nos. MF6061 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: License Amendment Request- Adoption of TSTF-425, Rev 3
SUBJECT:
Nine Mile Point Nuclear Station Unit No. 1; Docket No. 50-220 Renewed Facility Operating License No. DPR-63 License Amendment Request for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) (TAC No. MF6061)
By letter dated March 26, 2015 (ADAMS Accession No. ML15089A231, Exelon Generation Company, LLC (EGC) submitted a license amendment request (LAR) for Nine Mile Point Nuclear Station Unit No. 1. The proposed amendment would modify NMP, Unit 1 TS by relocating specific surveillance frequencies to a licensee-controlled program with the implementation of Nuclear Energy Institute (NEI) 04-10, "Risk-Informed Technical Specifications Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies." The changes are consistent with NRC-approved Industry Technical Specifications Task Force (TSTF) Standard Technical Specifications (STS) change TSTF-425, Revision 3, (ADAMS Accession No. ML090850642). The Federal Register Notice published on July 6, 2009 (74 FR 31996),
announced the availability of this TS improvement.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
1
If you have any questions, please contact me at (301) 415-3308.
Bhalchandra K. Vaidya Licensing Project Manager NRC/NRR/DORL/LPL1-1 (301)-415-3308 (O) bhalchandra.vaidya@nrc.gov 2
Hearing Identifier: NRR_PMDA Email Number: 2251 Mail Envelope Properties (51d10e1d411f4a378552af64932e0dbc)
Subject:
FW: Nine Mile Point Nuclear Station Unit No. 1; , TAC Nos. MF6061 -
ACCEPTANCE OF REQUESTED LICENSING ACTION RE: License Amendment Request- Adoption of TSTF-425, Rev 3 Sent Date: 7/27/2015 2:03:06 PM Received Date: 7/27/2015 2:03:07 PM From: Vaidya, Bhalchandra Created By: Bhalchandra.Vaidya@nrc.gov Recipients:
"Mozafari, Brenda" <Brenda.Mozafari@nrc.gov>
Tracking Status: None Post Office: HQPWMSMRS06.nrc.gov Files Size Date & Time MESSAGE 4002 7/27/2015 2:03:07 PM Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:
Recipients Received: