Relief Request S2-I4R-123 Acceptance Review (ME8847)
ML121880208
Person / Time
Site: Salem PSEG icon.png
Issue date: 07/06/2012
From: John Hughey
Plant Licensing Branch 1
To: Bernard Thomas
Public Service Enterprise Group
Hughey J
References
TAC ME8847
Download: ML121880208 (1)


Text

From: Hughey, John Sent: Friday, July 06, 2012 8:18 AM To: Thomas, Brian J.

Subject:

Relief Request S2-I4R-123 - 4th 10-Year ISI Code Edition - NRC Acceptance Review Results

Brian, By letter dated June 7, 2012, PSEG submitted a relief request S2-I4R-123 for Salem Unit 2 (ADAMS Accession No. ML12159A084; TAC No. ME8847). The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Thank you and If you have any questions, please contact me, John John Hughey Salem & Hope Creek Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov