the Spent Fuel Pool ( SFP) that had an initial enrichment of 4.70 weight percent and contained no Integral Fuel Burnable Absorber (IFBA) rods. These assemblies were first loaded in Unit 2 Cycle 21 in 1994.
Technical Specification 3.7.12 requires fuel assemblies with an initial enrichment greater than 4.60 weight percent to have an acceptable number of IFBA rods based on Figure 3.7.12-1. The 12 assemblies in question had a nominal initial enrichment of 4.70 weight percent and no IFBA rods.
Storage of the 12 assemblies had previously been evaluated as being acceptable using an approved methodology.�A new criticality analysis confirms the earlier analysis by demonstrating that these assemblies may be used in any configuration in the SFP, even if the SFP were filled with unborated water and no Boraflex is present. Therefore, the safety significance of this condition is minimal.
This condition is reportable in accordance with 10 CFR 50.73(a)(2)(i)(B), "Any operation or condition which was prohibited by the plant's Technical Specifications." No corresponding 10 CFR 50.72 report applies. |
FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 PAGE (3)
Event Description:
On June 26, 2006, Point Beach Nuclear Plant (PBNP) discovered that 12 fuel assemblies stored in the spent fuel pool [DA] do not meet the requirements of Technical Specification 3.7.12.
Technical Specification 3.7.12 requires fuel assemblies with an initial enrichment greater than 4.60 weight percent to have an acceptable number of Integral Fuel Burnable Absorber (IFBA) rods based on Figure 3.7.12-1. The 12 assemblies in question had a nominal initial enrichment of 4.70 weight percent and no IFBA rods. Per Figure 3.7.12-1, fuel with an initial enrichment of 4.70 weight percent requires at least four 1.0X IFBA rods.
Different criticality analysis and Technical Specification requirements were in place when the fuel assemblies were purchased and put into use. When the assemblies were purchased, the approved criticality analysis upper limit on initial enrichment was 4.75 weight percent and IFBA was not required.
A license amendment to use a new criticality analysis was approved by the Commission on September 4, 1997, which is the present analysis of record. The new criticality analysis allows fuel with enrichment up to 5.00 weight percent, but requires that fuel with an initial enrichment greater than 4.60 weight percent have a certain number of IFBA rods (based on initial enrichment) to ensure the requirements for SFP keffective (keff) are met. At the time, these 12 assemblies were recognized as not meeting the new requirements. To accommodate these assemblies, an alternate analysis methodology was included in the Technical Specifications. It stated that if assemblies with initial enrichment greater than 4.60 weight percent can be demonstrated to have a kinfinite (kinf) less than a specified value, they would also be acceptable for storage.
When PBNP received the new criticality analysis, a separate report was also received that demonstrated that the kinf for the 12 assemblies was below the Westinghouse specified value and the assemblies were acceptable for storage. At that time, PBNP was in full compliance with the Technical Specification requirements for fuel storage.
On February 26, 1999, Westinghouse issued NSAL-99-003. The advisory letter stated Westinghouse was abandoning the kinf methodology because it could lead to IFBA requirements which are lower than those required by the IFBA enrichment curve. Westinghouse requested that plants with both the kinf and IFBA enrichment curve methodologies to use only the IFBA enrichment curve.
PBNP submitted License Amendment Request (LAR) 214 to remove the kinf methodology from the Technical Specifications without recognizing that it would affect these 12 assemblies. This condition has existed since March 20, 2000, when the amendment to remove the kinf methodology was approved by the Commission.
On June 26, 2006, at 1440, the plant entered Technical Specification Action Condition (TSAC) 3.7.12.A.1, which requires the spent fuel pool to be restored within fuel storage limits immediately. This condition remains in effect pending LAR approval.
FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 PAGE (3) POINT BEACH NUCLEAR PLANT UNIT 2 05000301 YEAR Component and system Description:
The spent fuel pool will accommodate 1502 fuel assemblies. The new and spent fuel storage racks are designed so it is not possible to insert assemblies in other than the prescribed locations. In addition, the spent fuel pool has an area set aside for accepting spent fuel shipping casks or dry storage casks.
Borated water is used to fill the spent fuel storage pool at a concentration to match or exceed that used in the reactor cavity and refueling canal during refueling operations. The fuel in the spent fuel pool is stored vertically in an array with sufficient center-to-center distance and intervening solid neutron absorber between assemblies to assure keff assemblies.
Event Analysis and Safety Significance:
Each of the 12 fuel assemblies has a burnup greater than 45,000 MWD/MTU. Therefore, the current enrichment of the fuel is far below the initial enrichment. Storage of the 12 assemblies had previously been evaluated as being acceptable for storage in the SFP in accordance with an approved methodology.
Although the PBNP license was amended to no longer rely on that methodology, the physical factors for assuring safety of the assemblies' storage in the SFP did not change. A new criticality analysis confirms the adequacy of the previous assessment by demonstrating that these assemblies may be used in any configuration in the SFP, even if it is filled with unborated water and no Boraflex is present. Therefore, this condition is of low safety significance.
Cause:
The apparent cause of this event was failure to validate and verify that there were assemblies that could be affected when the Technical Specification change was made to remove the kinf methodology.
Corrective Action:
A license amendment to correct this condition is under development. The amendment is based on a new analysis that takes credit for the burnup of the fuel assemblies. Under the new proposed criticality analysis, the 12 assemblies are acceptable for storage.
A new administrative procedure was issued on June 28, 2006. This procedure includes a "Reload Safety Licensing Checklist" as part of the design process and ensures that new fuel will meet Technical Specification requirements.
FACILITY NAME (1) DOCKET NUMBER i2) LER NUMBER (6) PAGE (3) POINT BEACH NUCLEAR PLANT UNIT 2 05000301
Previous Similar Events:
LER Number� Title 266/1975-018-00� Three Fuel Assemblies Determined to be in Wrong Position in the Spent Fuel Pool.
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|