MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtecs Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. O'Brien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] |
Text
Haverkamp, Trisha From: McKinley, Raymond Sent: Monday, November 17, 2014 2:50 PM To: mary.lampert@comcast.net
Subject:
Response - FW: Questions regarding Seismic Restraints and the Vertical Cask Transporter Attachments: Lampert Pilgrim QA 10-15-2014email.pdf
- Mary, Please see the attached PDF which addresses your questions below.
Sincerely, Ray McKinley Chief, Division of Reactor Projects Branch 5 U.S. NRC Region I From: Mary Lampert [1]
Sent: Wednesday, October 15, 2014 11:46 AM To: McKinley, Raymond Cc: Kevin Nord; michal freedhoff; Dave Lochbaum; weavenel@gmail.com; Becky Chin; James lampert; marischka dopp; Nancy Nowak; Pat Gagnon
Subject:
Questions regarding Seismic Restraints and the Vertical Cask Transporter October 15, 2014 Hello Ray:
Hope you had an enjoyable Columbus Day week-end; here are a couple of questions regarding seismic restraints and the Vertical Cask Transporter.
Reactor Building Crane If seismic restraints were not already in place, does Pilgrims upgrade include adding seismic restraints to maintain the crane on the girder and runway rails? If not, please explain the justification for not including the seismic restraints. Specifically, absent the restraints in a maximal seismic event that can be anticipated today and into the future, how will the crane stay on the girder and runway rails? Include in the answer, the maximum earthquake assumed and the basis for choosing that level of severity.
Vertical Cask Transporter (VCT)
Please provide MLs for analysis of Pilgrims VCT and associated documents Does Pilgrims VCT use foam filled rubber tires instead of the old track-style systems?
If Pilgrim does not use rubber tires please explain the justification by Entergy and NRC to allow the use of a VCT with track tires. We understand that rubber tires have advantages in seismic situations (rubber tires 1
have elasticity and a lower center of gravity). Again, please include in the answer, the maximum earthquake assumed and the basis for choosing that level of severity.
If Pilgrim does not use foam filled rubber tires please explain the justification by Entergy and NRC to allow the use of a VCT without foam fill. We understand that foam fill prevents flat-spotting, loss of pressure, blow-outs and prevents damage to travel surface.
We really appreciate your help in providing information so that we can better understand what is going on and if it is in the best interest of our communities. We also hope that our questions may stimulate that extra look by NRC so that all Ts are crossed and Is dotted by your inspectors.
- Cheers, Mary Mary Lampert, on behalf of Pilgrim Watch/ Town of Duxbury Nuclear Advisory Committee 148 Washington Street Duxbury MA 02332 Tel 781.934.0389/Email: mary.lampert@comcast.net 2
- 1. Reactor Building Crane If seismic restraints were not already in place, does Pilgrims upgrade include adding seismic restraints to maintain the crane on the girder and runway rails? If not, please explain the justification for not including the seismic restraints. Specifically, absent the restraints in a maximal seismic event that can be anticipated today and into the future, how will the crane stay on the girder and runway rails? Include in the answer, the maximum earthquake assumed and the basis for choosing that level of severity.
The Reactor Building crane is a Class II component upgraded to meet the guidance of NUREG-0554 for single-failure-proof cranes and the guidance of NUREG-0612 Appendix C for the modification of existing cranes. The upgraded crane includes a new trolley with a single-failure-proof 100 ton main hoist, designed and qualified in accordance with the appropriated requirements of ASME NOG-1-2004. The trolley also includes a 10 ton non single-failure- proof auxiliary hoist which conforms to the requirements of the Crane Manufactures Association of America Specification # 70. The Reactor Building crane has been evaluated for earthquake loading to meet NUREG-0554 seismic design requirements, and the Reactor Building structure has been evaluated to ensure its integrity for the associated crane reactions.
The reactor building crane meets the NUREG-0554 and ASME NOG-1 requirements and is qualified to the Operating Basis Earthquake (OBE) and Safe Shutdown Earthquake (SSE). This equates to a horizontal ground acceleration of 0.08g (OBE) and 0.15g (SSE). The crane is designed to meet the sites current licensed design basis seismic event.
- 2. Vertical Cask Transporter (VCT)
Please provide MLs for analysis of Pilgrims VCT and associated documents Does Pilgrims VCT use foam filled rubber tires instead of old track-style systems?
If Pilgrim does not use rubber tires please explain the justification by Entergy and NRC to allow the use of a VCT with track tires. We understand that rubber tires have advantages in seismic situations (rubber tires have elasticity and a lower center of gravity). Again, please include in the answer, the maximum earthquake assumed and the basis for choosing that level of severity.
If Pilgrim does not use foam filled rubber tires please explain the justification by Entergy and NRC to allow the use of a VCT without foam fill. We understand that foam fill prevents flat-spotting, loss of pressure, blow-outs and prevents damage to travel surface.
Entergy is constructing and operating an Independent Spent Fuel Storage Installation (ISFSI) under a general license. They will be using the HOLTEC HI-STORM 100 system as licensed and described in Amendment 7 of the Certificate of Compliance (ADAMS Accession Number: ML093620049) and HOLTECs Final Safety Analysis Report (revision
- 9) (ADAMS Accession Number: ML101400161). Information concerning the vertical cask transporter (VCT) are discussed in the documents referenced above and can be found in ADAMS, the NRCs electronic filing system. The VCT being used by Entergy at Pilgrim has foam filled rubber tires.