Letter Sequence Withholding Request Acceptance |
---|
|
|
MONTHYEARML15022A1652015-01-0909 January 2015 License Amendment Request for Areva Extended Flow Window Supplement to Respond to NRC Staff Questions Project stage: Supplement ML15030A0092015-01-28028 January 2015 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance Review for License Amendment Request Transition to Areva Extended Flow Window Methodology Project stage: Acceptance Review ML15195A4472015-08-0505 August 2015 Summary of Public Meeting with Xcel Energy and Areva to Discuss Changes to the Proposed Technical Specifications and COLR in Support of the Areva Extended Flow Window License Amendment Request Project stage: Meeting L-MT-15-057, License Amendment Request for Areva Extended Flow Window Supplement to Respond to NRC Staff Questions2015-08-26026 August 2015 License Amendment Request for Areva Extended Flow Window Supplement to Respond to NRC Staff Questions Project stage: Supplement ML15140A1242015-09-28028 September 2015 Request for Withholding Information from Public Disclosure from Areva Inc. Associated with the Areva Extended Flow Window License Amendment Request Project stage: Withholding Request Acceptance ML15140A1472015-09-28028 September 2015 Request for Withholding Information from Public Disclosure (GE-Hitachi LLC) Associated with the Areva Extended Flow Window License Amendment Request Project stage: Withholding Request Acceptance ML15274A4732015-09-29029 September 2015 License Amendment Request for Areva Extended Flow Window Supplement to Respond to NRC Staff Questions Project stage: Supplement L-MT-15-065, Enclosure 8, Areva Report ANP-3424NP, Revision 1 to Areva Responses to RAI from Scvb on MNGP EFW LAR (Non-Proprietary) and Enclosure 9, Areva Affidavits2015-09-29029 September 2015 Enclosure 8, Areva Report ANP-3424NP, Revision 1 to Areva Responses to RAI from Scvb on MNGP EFW LAR (Non-Proprietary) and Enclosure 9, Areva Affidavits Project stage: Response to RAI ML15274A4752015-09-29029 September 2015 Enclosure 6, Areva Report ANP-3435NP, Revision 0 to Are VA Responses to RAI-8 and RAI-32 from Srxb and Snpb on MNGP EFW LAR (Non-Proprietary) Project stage: Response to RAI ML15274A4742015-09-29029 September 2015 Enclosure 4, Engineering Evaluation, EC 25987, Calculation Framework for the Extended Flow Window Stability (Efws) Setpoints Project stage: Other L-MT-15-081, ANP-3435NP, Revision 1, Areva Responses to RAI-8 and RAI-32 from Srxb and Snpb on MNGP EFW Lar.2015-12-0808 December 2015 ANP-3435NP, Revision 1, Areva Responses to RAI-8 and RAI-32 from Srxb and Snpb on MNGP EFW Lar. Project stage: Response to RAI ML15345A4072015-12-0808 December 2015 License Amendment Request for Areva Extended Flow Window, Supplement to Provide Revised Analysis of Anticipated Transient Without Scram Instability Project stage: Supplement ML16063A0332016-02-29029 February 2016 License Amendment Request for Areva Extended Flow Window Supplement to Disposition Changes to Non-Limiting Transient Analyses Project stage: Supplement L-MT-16-017, Revised Commitment to Reconcile Analysis of Bypass Voiding for Transition to Areva Analysis Methodology2016-04-29029 April 2016 Revised Commitment to Reconcile Analysis of Bypass Voiding for Transition to Areva Analysis Methodology Project stage: Other ML16221A2742016-07-31031 July 2016 ANP-3435NP, Revision 2, Areva Responses to RAI-8 and RAI-32 from Srxb and Snpb on MNGP EFW Lar. Project stage: Response to RAI L-MT-16-037, ANP-3284NP, Revision 1, Results of Analysis and Benchmarking of Methods for Monticello ATWS-I.2016-07-31031 July 2016 ANP-3284NP, Revision 1, Results of Analysis and Benchmarking of Methods for Monticello ATWS-I. Project stage: Other ML16221A2752016-07-31031 July 2016 ANP-3274NP, Revision 2, Analytical Methods for Monticello ATWS-I. Project stage: Other ML16221A2732016-08-0404 August 2016 License Amendment Request for Areva Extended Flow Window Supplement to Provide Revised Analysis of Anticipated Transient Without Scram Instability Project stage: Supplement L-MT-16-041, License Amendment Request for Areva Extended Flow Window Supplement to Address Power Distribution Uncertainties2016-09-14014 September 2016 License Amendment Request for Areva Extended Flow Window Supplement to Address Power Distribution Uncertainties Project stage: Supplement L-MT-16-049, License Amendment Request for Areva Extended Flow Window Supplement to Revise the Applicability of a Topical Report Limitation2016-09-28028 September 2016 License Amendment Request for Areva Extended Flow Window Supplement to Revise the Applicability of a Topical Report Limitation Project stage: Supplement 2015-09-29
[Table View] |
|
---|
Category:Letter
MONTHYEARL-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance ML24115A2972024-04-25025 April 2024 Sec106 Tribal, Miller, Cole-Shakopee Mdewakanton Sioux Community L-MT-24-012, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A2902024-04-25025 April 2024 Sec106 Tribal, Jackson-Street, Lonna-Spirit Lake Nation ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe ML24115A2882024-04-25025 April 2024 Sec106 Tribal, Fairbanks, Michael-White Earth Nation.Docx ML24115A3012024-04-25025 April 2024 Sec106 Tribal, Seki, Darrell-Red Lake Nation ML24115A2922024-04-25025 April 2024 Sec106 Tribal, Jensvold, Kevin-Upper Sioux Community ML24115A2942024-04-25025 April 2024 Sec106 Tribal, Johnson, John-Lac Du Flambeau Band of Lake Superior Chippewa Indians ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3002024-04-25025 April 2024 Sec106 Tribal, Rhodd, Timothy-Iowa Tribe of Kansas and Nebraska ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa 2024-09-26
[Table view] Category:Proprietary Information Review
MONTHYEARML23115A4172023-04-28028 April 2023 Requesting for Withholding Information from Public Disclosure for Monticello Nuclear Generating Plant Core Operating Limits Report (COLR) for Cycle31, Revision 2 ML22187A2912022-08-0303 August 2022 Request for Withholding Information from Public Disclosure Monticello Nuclear Generating Plant ML21277A2952021-11-0808 November 2021 Request for Withholding Information from Public Disclosure ML21013A4542021-01-21021 January 2021 Request for Withholding Information from Public Disclosure ML16243A4602016-09-15015 September 2016 Request for Withholding Information from Public Disclosure ML16160A0862016-06-13013 June 2016 Request for Withholding Information from Public Disclosure ML15301A0942015-12-0707 December 2015 Request for Withholding Information from Public Disclosure from Areva Inc. Associated with the Areva Extended Flow Window License Amendment Request ML15301A5502015-11-30030 November 2015 Request for Withholding Information from Public Disclosure from Westinghouse Associated with Submittal of Power Ascension Testing Results for Replacement Steam Dryer ML15140A1472015-09-28028 September 2015 Request for Withholding Information from Public Disclosure (GE-Hitachi LLC) Associated with the Areva Extended Flow Window License Amendment Request ML15140A1242015-09-28028 September 2015 Request for Withholding Information from Public Disclosure from Areva Inc. Associated with the Areva Extended Flow Window License Amendment Request ML14155A1692014-07-0808 July 2014 Request for Withholding Information from Public Disclosure Associated with Affidavit Executed on April 22, 2014, by Mr. Alan B. Meginnis of Areva Inc. ML14155A1772014-07-0808 July 2014 Request for Withholding Information from Public Disclosure Associated with Affidavit Executed on April 28, 2014, by Mr. Philip A. Opsal of Areva Inc. ML14155A1672014-07-0808 July 2014 Request for Withholding Information from Public Disclosure Associated with Affidavit Executed on January 23, 2014, by Mr. Alan B. Meginnis of Areva Np, Inc. ML13239A0842013-10-0808 October 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavits Executed on March 14, 2013, by Linda Dolan and June 12, 2013, by Kurt Edsinger of ML13239A0762013-10-0808 October 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on March 14, 2013, by Linda C. Dolan of GE-Hitachi ML13239A0022013-10-0808 October 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on January 14, 2013, by James F. Harrison of GE-Hitachi ML13239A0822013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavits Executed on March 19, 20, 21, 25 & 27, 2013, by Bradley F. Maurer of Westinghouse ML13239A1092013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on July 16, by James A. Gresham of Westinghouse ML13239A0892013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavits Executed on July 31 and August 1, 2013, by Hank A. Sepp and James A. Gresham of Westinghouse ML13239A0612013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on March 14, 2013, by Bradley F. Maurer of Westinghouse ML13239A0482013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on March 7, 2013, by James A. Gresham of Westinghouse ML13239A0152013-09-30030 September 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on February 20, 2013, by Bradley F. Maurer of Westinghouse ML13009A0122013-01-25025 January 2013 Request for Withholding of Proprietary Information from Public Disclosure Enclosure 1 of Letter Dated November 30, 2012 ML12240A1232012-09-13013 September 2012 Letter Approving Withholding from Public Disclosure of Submitted Proprietary Information ML12214A5862012-08-0707 August 2012 Letter Approving Withholding from Public Disclosure of Certain Submitted Information Regarding the Nordic Replacement Steam Dryer ML11325A4262011-11-30030 November 2011 Letter Approving Withholding from Public Disclosure Two Documents Containing Proprietary Information Submitted in the Licensee'S 11/11/2011 Letter ML11125A0222011-05-26026 May 2011 Withholding of Submitted Proprietary Information from Public Disclosure ML1104809152011-03-0909 March 2011 Letter Regarding Request for Withholding Proprietary Information from Public ML1101902042011-02-0808 February 2011 Request for Withholding for Proprietary Information from Public Disclosure ML1027706892010-11-0101 November 2010 Withholding Information from Public Disclosure ML1020400512010-07-30030 July 2010 Withholding of Submitted Proprietary Information from Public Disclosure ML1018909152010-07-30030 July 2010 Determination That Appendix 4 of Enclosure 1 of 6/30/10 Submittal Contains Proprietary Information ML1003202292010-02-16016 February 2010 Determination That Attachment 3 Contains Proprietary Information and Is Withheld from Public Disclosure ML0928105542009-10-20020 October 2009 Determination That Submitted Information Is Proprietary and Is Withheld from Public Disclosure ML0926502282009-09-28028 September 2009 Request for Withholding Information from Public Disclosure ML0926109182009-09-28028 September 2009 Request for Withholding Information from Public Disclosure ML0926101052009-09-28028 September 2009 Request for Withholding Information from Public Disclosure ML0922902502009-08-26026 August 2009 Approves Withholding of Proprietary Information in 08/12/2009 Letter from Public Disclosure ML0921608892009-08-14014 August 2009 Request for Withholding Information from Public Disclosure ML0911404702009-05-0707 May 2009 Determination That Submitted Information Can Be Withheld from Public Disclosure ML0905002592009-03-0303 March 2009 Letter to Approve Request to Withhold Document Containing Proprietary Information from Public Disclosure ML0835706102009-01-26026 January 2009 Letter Conveying Determination That Enclosure 11 of 11/5/08 Application for EPU Amendment Contains Proprietary Information and Is Withheld from Public Disclosure ML0835901272009-01-14014 January 2009 Letter Conveying Determination That Enclosure 5 of 11/5/08 Application for EPU Amendment Contains Proprietary Information and Withheld from Public Disclosure ML0830106242008-11-12012 November 2008 Letter to Determine Withholding Proprietary Information from Public Disclosure ML0814802652008-07-11011 July 2008 Request for Withholding Information from Public Disclosure ML0815600232008-06-16016 June 2008 Withholding from Public Disclosure, 03/31/2008 Application for Extended Power Uprate Amendment Enclosure 1 Mechanical and Civil Engineering Branch Questions and Responses (Proprietary). ML0809805822008-04-30030 April 2008 Request for Withholding Information from Public Disclosure ML0809804572008-04-14014 April 2008 Determining of Proprietary Information in Enclosure 5 of 3/31/08 Application for Extended Power Uprate Amendment ML0805706482008-03-21021 March 2008 Request for Withholding Information from Public Disclosure ML0727506332007-10-31031 October 2007 (MNGP) - Request for Withholding Information from Public Disclosure 2023-04-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 28, 2015 Mr. Peter A. Gardner Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT- REQUEST FOR WITHHOLDING PROPRIETARY INFORMATION FROM PUBLIC DISCLOSURE (TAC NO. MF5002)
Dear Mr. Gardner:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated October 3, 2014 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML14283A125), Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy, submitted a license amendment request application to revise the technical specifications and approve certain analytical methods to support operation in the expanded power-flow operating domain described as the Extended Flow Window (EFW) at the Monticello Nuclear Generating Plant (Monticello). (located at ADAMS Accession No. ML14283A119) of the October 3, 2014, application, included four AREVA affidavits executed by Alan B. Meginnis, Manager of Product Licensing, for AREVA Inc., requesting that information designated proprietary in the following documents be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (1 O CFR), Part 2, Section 2.390.
- Enclosure 7 provides a proprietary version of AREVA report ANP-3274P, Revision 1, "Analytical Methods for Monticello A TWS-1 [Anticipated Transient Without Scram with Instability]," dated July 2014. The associated affidavit was executed on July 7, 2014.
- Enclosure 9 provides a proprietary version of AREVA report ANP-3284P, Revision 0, "Results of Analysis and Benchmarking of Methods for Monticello ATWS-1," dated April 2014. The associated affidavit was executed on April 15, 2014.
- Enclosure 11 provides a proprietary version of AREVA report ANP-3295P, Revision 2, "Monticello Licensing Analysis for EFW (EPU/MELLLA+) [(Extended Power Uprate I Maximum Extended Load Line Limit Analysis Plus))," dated September 2014. The associated affidavit was executed on September 25, 2014.
- Enclosure 13 provides a proprietary version of AREVA report ANP-3135P, Revision 0, "Applicability of AREVA BWR [boiling-water reactor] Methods to Extended Flow Window for Monticello," dated April 2014. The associated affidavit was executed on April 22, 2014.
P. Gardner The affidavits state that the information submitted in Enclosures 7, 9, 11, and 13, should be considered exempt from mandatory public disclosure for the following reasons:
- a. Use of the information by a competitor would permit the competitor to significantly reduce its expenditures, in time or resources, to design, produce, or market a similar product or service.
- b. The information reveals certain distinguishing aspects of a process, methodology, or component, the exclusive use of which provides a competitive advantage for AREVA in product optimization or marketability.
- c. The information is vital to a competitive advantage held by AREVA, would be helpful to competitors to AREVA, and would likely cause substantial harm to the competitive position of AREVA.
We have reviewed the AREVA affidavits in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the information sought to be withheld in the submittal contains proprietary commercial information and should be withheld from public disclosure. Therefore, Enclosures 7, 9, 11, and 13, which are marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b )(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Enclosures 8, 10, 12, and 14, contain non-proprietary versions of Enclosure 7, 9, 11, and 13, respectively, and have been placed in the NRC's Public Document Room and added to the NRC Library at ADAMS Accession Nos. ML14283A120, ML14283A121, ML14283A122, and ML14283A123.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
P. Gardner If you have any questions regarding this matter, I may be reached at (301) 415-3049.
Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263 cc: Mr. Alan B. Meginnis, Manager Product Licensing AREVA Inc.
2101 Horn Rapids Road Richland, WA 99354 Additional Distribution via Listserv
ML15140A124 OFFICE LPL3-1/PM LPL 1-1/LA DSS/SRXB/BC DSS/SNPB/BC LPL3-1/BC LPL3-1/PM NAME TBeltz KGoldstein CJackson JDean DPelton TBeltz DATE 05/20/15 05/27/15 09/23/15 05/30/15 09/24/15 09/28/15