MONTHYEARNL-24-0385, Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator2024-10-31031 October 2024 Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator IR 05000424/20240032024-10-30030 October 2024 – Integrated Inspection Report 05000424/2024003 and 05000425/2024003 NL-24-0386, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information2024-10-28028 October 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0366, Core Operating Limits Report, Cycle 26, Version 12024-10-25025 October 2024 Core Operating Limits Report, Cycle 26, Version 1 ML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML24269A2502024-09-26026 September 2024 Acknowledgement of the Withdrawal of the Requested Exemption and License Amendment Request to Remove Tier 1 and Tier 2* Requirements NL-24-0369, Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements2024-09-25025 September 2024 Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements NL-24-0350, Core Operating Limits Report, Cycle 24, Version 22024-09-25025 September 2024 Core Operating Limits Report, Cycle 24, Version 2 ML24243A0072024-09-10010 September 2024 – Correction of Amendment Nos. 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24249A2942024-09-0606 September 2024 Correction of Amendment Nos. 218 and 201 Regarding Revision to Technical Specifications to Use Online Monitoring Methodology 05200025/LER-2024-002, Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve2024-09-0505 September 2024 Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information 05000425/LER-2024-001, Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod2024-08-0909 August 2024 Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter 05200026/LER-2024-001, Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal2024-08-0606 August 2024 Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements ML24204A0722024-07-23023 July 2024 Issuance of Amendment No. 225, Regarding LAR to Revise TS 3.7.9 for a one-time Change to Support Nuclear Service Cooling Water Transfer Pump Repairs - Emergency Circumstances NL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24191A4562024-07-19019 July 2024 Request for Relief and Alternative Requirements for Squib (Explosively Actuated) Valves First Test Interval ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0243, Registration of Spent Fuel Cask Use2024-06-18018 June 2024 Registration of Spent Fuel Cask Use ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24155A1772024-06-0505 June 2024 Regulatory Audit in Support of Review of the LAR to Revise Emergency Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, Surveillance Requirements NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24094A1402024-05-16016 May 2024 Staff Response to Request for Revision to NRC Staff Assessment of Updated Seismic Hazard Information and Latest Understanding of Seismic Hazards at the Vogtle Plant Site Following the NRC Process for the Ongoing Assessment of Natural Hazard ML24120A1812024-05-13013 May 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage IR24 Steam Generator Tube Inspection Report – Enclosure 2 ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24101A2112024-05-11011 May 2024 Expedited Issuance of Amendment No. 198 Change to Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) ML24120A2832024-04-30030 April 2024 Project Manager Reassignment 2024-09-09
[Table view] Category:License-Operator Examination Report (Non-Power Reactors Only)
MONTHYEARIR 05000424/20053022006-01-0606 January 2006 Er 05000424-05-302 & 05000425-05-302, 11/23/05, Vogtle Electric Generating Plant, Units1 and 2 Licensed Operator Examinations IR 05000424/20053012005-07-0505 July 2005 Er 05000424-05-301, Er 05000425-05-301; 5/17-25/05; Vogtle Electric Generating Plant, Units 1 and 2; Licensed Operator Examinations ML0601301502005-07-0505 July 2005 Er 05000424-05-301, Er 05000425-05-301; 5/17-25/05; Vogtle Electric Generating Plant, Units 1 and 2; Licensed Operator Examinations 2006-01-06
[Table view] |
Text
January 6, 2006Southern Nuclear Operating Company, Inc.ATTN:Mr. D. E. Grissette, Vice President - Vogtle Project P. O. Box 1295 Birmingham, AL 35201-1295SUBJECT:VOGTLE ELECTRIC GENERATING PLANT - NRC EXAMINATION REPORT 05000424/2005302 AND 05000425/2005302
Dear Mr. Grissette:
On November 23, 2005, members of your training staff administered an NRC Senior Reactorwritten retake examination to one employee of your company who had reapplied for a license to operate the Vogtle Electric Generating Plant. The NRC waived the Reactor Operator portion ofthe written examination, and the operating examinations.The SRO applicant passed the written retake examination. There were no post examcomments.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and itsenclosures will be available electronically for public inspection in the NRC Public Document Roomor from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (thePublic Electronic Reading Room).
Sincerely,
/RA/James H. Moorman, III, ChiefOperation Branch Division of Reactor SafetyDocket Nos.: 50-424, 50-425License Nos.: NPF-68, NPF-81
Enclosure:
Report Details
REGION IIDocket Nos.:050000424, 05000425License Nos.:NPF-68, NPF-81 Report Nos.:05000424/2005302, 05000425/2005302 Licensee:Southern Nuclear Operating Company, Inc. (SNC)
Facility:Vogtle Electric Generating Plant Units 1 and 2Location:7821 River RoadWaynesboro, GA 30830Date:Written Exam - November 23, 2005 Examiner:G. Laska, Chief Examiner Approved by:James H. Moorman, III, ChiefOperations Branch Division of Reactor Safety SUMMARY OF FINDINGSER 05000424/2005302, ER 05000425/2005302; 11/23/2005; Vogtle Electric Generating Plant,Units 1 and 2, Licensed Operator Examinations.An NRC examiner conducted an operator licensing initial retake examination in accordance withthe guidance of NUREG-1021, Revision 9, Operator Licensing Examiner Standards for PowerReactors. This examination implemented the operator licensing requirements of 10 CFR
§55.43. The facility licensee administered the written retake examination on November 23, 2005. Theoperator licensing initial written retake examination was developed by the licensee. One seniorreactor operator (SRO) applicant passed this retake written examination and was issued a license.No significant issues were identified.
Report Details4.OTHER ACTIVITIES (OA)4OA5Operator Licensing Initial Examinations a.Inspection ScopeThe examiners reviewed the written examination developed by the licensee forcompliance with the guidelines specified in NUREG-1021, Revision 9.The examiner reviewed the licensee's examination security measures while preparingand administering the examinations to ensure that examination security and integrity complied with 10 CFR 55.49, "Integrity of examinations and tests." The examiner evaluated one SRO applicant who was being assessed under theguidelines specified in NUREG-1021. The licensee administered the retake of thewritten examination on November 23, 2005. The evaluation of the applicant and areview of documentation was performed to determine if the applicant met the requirements specified in 10 CFR Part 55. b.FindingsNo findings of significance were identified. The applicant passed his retake examination.
The NRC determined that the licensee's examination submittal was within the range ofacceptability expected for a proposed examination. One SRO passed the written retakeexamination. No post exam comments were submitted. The SRO written examination and answer keys, and examination references may be accessed in the ADAM S system(ADAMS Accession Number, ML060060281).4OA6MeetingsExit Meeting SummaryOn December 1, 2005, the examiner discussed the examination and preliminary findingswith Mr. Lee Mansfield, Operations Training Manager, and other members of his staff.
The examiner confirmed that proprietary information was not provided or examined during the inspection.
PARTIAL LIST OF PERSONS CONTACTEDLicenseeL. Mansfield, Operations Training ManagerD. Scukanec, Senior Operations Instructor T. Thompson, Operations Instructor NRCG. McCoy, Senior Resident Inspector