Examination Outline Submittal for the Fermi Retake Examination - August 2006
ML063460556
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/08/2006
From: Walton R
NRC/RGN-III/DRS/OLB
To:
Detroit Edison
Shared Package
ML062420262 List:
References
50-341/06-302 50-341/06-302
Download: ML063460556 (11)


Text

EXAMINATION OUTLINE SUBMITTAL FOR THE FERMI RETAKE EXAMINATION - AUGUST 2006 June 29,2006 NRC-06-0050 Mr. Hironori Peterson, Chief Operations Branch Division of Reactor Safety U. S. NRC Region I11 Suite 210 2443 Warrenville koad Lisle, Illinois 60532-4352

Dear Mr. Peterson:

Enclosed please find the following examination materials submitted to the NRC in preparation for the upcoming Fermi 2 Initial License Retake Examination scheduled to occur during the week of August 7,2006: . Seventy-five (75) question Reactor Operator Examination (Hardcopy wmeferences)

Plant Procedures (Compact Disc)

Appropriate quality verification checklists from Revision 9, NUREG 102 1 . The examination materials were developed using the appropriate guidance contained in Revision 9, NUREG 1021. These materials shall be withheld from public disclosure until after the examinations are complete.

We look forward to working with you during this process. If you have any questions or comments regarding the contents of the items listed above, please contact Mr. Timothy Horan at (734) 586-4961.

Enclosure ES-201 Examination Outline Qualitv Checklist Form ES-201-2 Facility:

Fermi-2 Date of Examination: '8/11/2006 Initials Item Task Description

1. I a. Verify that the outline(s) fit(s) the appropriate model, in accordance with ES401. IR R I b. Assess whether the outline was systematically and randomly prepared in accordance with I Section D.l of ES-401 and whether all KIA cateaories are amroDriatelv sampled. T T I c. Assess whether the outline over-emphasizes any systems, evolutions, or generic topics.

r N I d. Assess whether the justifications for deselected or rejected WA statements are appropriate.

I ~ 2. C a. Using Form ES-301-5. verify that the proposed scenario sets cover the required number of normal evolutions, instrument and component failures, technical specifications, and major transients.

b. Assess whether there are enough scenario sets (and spares) to test the projected number and mix of applicants in accordance with the expected crew composition and rotation schedule without compromising exam integrity, and ensure that each applicant can be tested using at least one new or significantly modified scenario, that no scenarios are duplicated from the applicants' audit test(s), and scenarios will not be repeated on subsequent days.

Pb c. To the extent possible, assess whether the outline(s) conform(s) with the qualitative and quantitative criteria specified on Form ES-301-4 and described in Appendix D. - 3. w J T a. Verify that the systems walk-through outline meets the criteria specified on Form ES-301-2:

(1) the outline(s) contain(s) the required number of control room and in-plant tasks disbibuted among the safety functions as specified on the form (2) task repetition from the last two NRC examinations is within the limits specified on the form (3) no tasks are duplicated from the applicants' audit test(s)

(4) the number of new or modified tasks meets or exceeds the minimums specified on the form (5) the number of alternate path, low-power, emergency, and RCA tasks meet the criteria W on the form Verify that the administrative outline meets the criteria specified on Form ES-301-1:

(1) the tasks are distributed among the topics as specified on the form (2) at least one task is new or significantly modified (3) no more than one task is repeated from the last two NRC licensing examinations Determine if there are enough different outlines to test the projected number and mix of applicants and ensure that no items are duplicated on subsequent days. Assess whether plant-specific priorities (induding PRA and IPE insights) are covered in the appropriate exam section. Assess whether the 10 CFR 55.41143 and 55.45 sampling is appropriate.

Ensure that K/A importance ratings (except for plant-specific priorities) are at least 2.5. b. PIP Np. 4 E &f c. a. b. c. 4. N R d. Check for duplication and overlap among exam sections.

Q A e. Check the entire exam for balance of coverage.

L f. Assess whether the exam fits the appropriate job level (RO or SRO). Date a. Author 6/16/2006 b. Facility Reviewer (*) 6/76/2006 c. NRC Chief Examiner (#) d NRC Supervisor

&130/2006 I. NOTE: # Independent NRC Reviewer inibal items in Column "c', chief examiner concurrence required ES-401 BWR Examination Outline FORM ES-401-1 Note: 1. Ensure that at least two topics from every applicable WA category are sampled within each tier of the RO and SRO-only outlines (Le., except for one category in Tier 3 of the SRO-only outline, the "Tier Totals" in each WA category shall not be less than two). The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by i1 from that specified in the table based on NRC revisions.

The final RO exam must total 75 points and the SRO-only exam must total 25 points. Systemdevolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems that are not included on the outline should be added. Refer to ES-401, Attachment 2, for guidance regarding the elimination of inappropriate WA statements. Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution. Absent a plant-specific priority, only those WAS having an importance rating (IR) of 2.5 or higher shall be selected Use the RO and SRO ratings for the RO and SRO-only portions, respectively.

Select SRO topics for Tiers 1 and 2 from the shaded systems and WA categories.

The generic (G) WAS in Tiers 1 and 2 shall be selected from Section 2 of the WA Catalog, but the topics must be relevant to the applicable evolution or system.

On the following pages, enter the WA numbers, a brief descnption of each topic, the topics' importance ratings (IRs) for the applicable license level, and the point totals

(#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G' on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note $1 does not apply). Use duplicate pages for RO and SRO-only exams.

For Tier 3, select topics from Section 2 of the WA catalog, and enter the WA numbers, descriptions, IRs, and point totals

(#)on Form ES-401-3.

Limit SRO selections to WAS that are linked to 10 CFR 55.43. 2. 3. 4 5 6. 7.' a. 9. ES-401, Page 16 of 33 ES-401 2 Form ES-401-1 KKK , EIAPE # I Name I Safety Function p-40 1 BWR Examination Outline Form ES-401-1 -4 95024 High Drywell Pressure

/ 5 I lyl Partial or Complete Loss of Forced ore Flow Circulation

/ 1 8 4 02.* 2 0 5 295003 Partial or Complete Loss of AC I6 295004 Partial or Total Loss of DC Pwr I 6 95005 Main Turbine Generator Trip I 3 295006 SCRAM I 1 Knowledge of limihng conditions for operations and safety Ilmits 3 4 1 0 1 Control Room Abandonment

/ 7 0 1 295018 Partial or Total Loss of CCW I 8 0 1 295019 Partial or Total Loss of lnst Air i 8 95021 Loss of Shutdown Cooling I4 Pressure effects on reactor water level Suppression chamber pressure MaiY-IBIi SBLC lnlectlon DELETED SEE ES-lO:-I Emergency depressurization Ill 20 1195023 Refueling Acc / 8 35 1 3 2 3 7 2 0 36 1 0 0 6 295025 High Reactor Pressure I3 46 1 Aaequate core cooling 31 1 04.0 Knowledge symptom based EOP mitigabon svategies 6 42 1 Protecbon of the general publii 95026 Suppression Pool High Water emp I5 3 Ill 1p95027 High Containment Temperature

/ 5 25 1 Breakers relays, and disconnects 3 3 Group Point To;al 20 I I I: 24 1195028 High Drywell Temperature

/ 5 95030 Low Suppression Pool Wtr Lvl I5 95031 Reactor Low Water Level

/ 2 295037 SCRAM Condition Present and Power 4bove APRM Downscale or Unknown / 1 0 2 295038 High Off-site Release Rate I9 0 4 00000 Plant Fire On Site I 8 A Category Totals 344 )mal Plant Evolutions - Tier IIGroup 1 (RO) K/A Topias) Reurculation system Ill Ahility to recognize aonormal indicabons for sy6:sm operating Dararneters which are entry-level conditions for emergency and amormai operating procedures Reactor recirculation 5 OI I I I3l1 I I IArea radiabon levels ECCS systems (NPSH consioerations) Plant-Specific Ol 1 I I ES-401, Page 17 of 33 ES-401 3 Form ES-401-1 BWR Examination Outline Form ES-401- ES-401, Page 18 of 33 ES-401 4 Form ES-401-1 ES-40 1, Page 19 of 33 ES-401-1 5 Form ES-401-1 s-40 1 BWR Examination Outline Form ES-401-' Plant Systems - Tier 2IGrouo 2 (RO) ES-401, Page 20 Of 33 ES-401 Generic Knowledge and Abilities Outline (Tier

3) FO~I ES-401-3 Category :onduct of )perations I Equipment lontrol 3. iadiation Zontrol 1. :mergency

'rocedures Plan her 3 Point le: Fermi 2 Date of Exam: 8/11/2006 ESllOl , Page 26 of 33 Summary of Systematic Random Selection Process 1. Random Number Generator was used using Excel Spreadsheet "RANDBETWEEN" fimction to generate all random selections.

2. For All Tiers, Random Selection was used to generate KA Topics and Statements.
3. Commencing with Tier 1 Group 1, the random number 2 was generated for the first APE, 295001. An "Am" statement was randomly chosen using the Random Number Generator.
4. Systematic and uniform sampling was assured by progressing through KA Categories on the ES-401-1 form with the exception of APE 295016. No "AK1" category topic exists. Randomly selected an "AK2" statement and reverted to the previously described sequence on the next APE. This was noted on ES-40 1-4. 5. For Tier 1 Group 2, random number 2 was generated to select the first KA Category (K2). Random selection produced topics and statements with sequentially selected KA Categories (Kl, K2, K3, AI, A2, and G). 6. For Tier 2 Group 1, random number 7 was generated to select the first KA Category (A1 ). Random selection produced statements with sequentially selected KA Categories (KI, K2, K3, K4, K5, K6 Al, A2, A3, A4 and G). 7. For Tier 2 Group 2, random number 6 was generated to select the first KA Category (K6). Random selection produced systems and statements with sequentiaIIy seIected KA Categories (KI, K2, K3, Al, A2, and G).

~~ ~ ES-401 Record of Reiected WAS Form ES-401-4 Tier / Group 1 /1 Reason for Rejection High Containment Temperature (Mk 3) is N/A at Fermi-2. Plant is equipped Randomly Selected K/A 295027 1 /2 2/1 2/ 1 2/2 2/2 2/2 1 /1 2/1 2/1 I interraction.

Randomly reselected KA 21 5005 K1.16, same KA category.

1/2 I 295010 2.2.22 1 Double Jeopardy (High Drywell Pressure) with Question 21, KA EPE with a Mk 1 Containment High Containment Temperature (Mk 3) is N/A at Fermi-2. Plant is equipped with a Mk 1 Containment Isolation Condenser is N/A at Fermi-2. Plant is equipped with RCIC.

HPCS is N/A at Fermi-2. Plant is equipped with HPCI. RSCS is abandoned in place at Fermi-2. RClS is N/A at Fermi-2. Plant is equipped with RMCS/ RBM/RWM. MSIV-LCS is abandoned in place at Fermi-2 Initial random selection led to K1 category. There are no K1 statements, used K2 for this topic and returned to category progression on next KA. Low Importance (2.4) randomly reselected statement K6.03 Double Jeopardy with 21 5002 K2.03, both topics involved RBM / APRM 29501 1 207000 209002 201 004 201 005 239003 295016 K1 21 1000 K6.01 21 5005 K1.03 I 295024 (High D$ei Pressure) 2.2.22. Selected 2.4.31 as replacement.

1 I ES-401, Page 27 of 33