Revision of Schedule for Review of Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application
ML101960636
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/16/2010
From: Jay Robinson
NRC/NRR/DLR/RPOB
To: Edington R
Arizona Public Service Co
DRUCKER D, NRR/DLR, 415-6223
References
TAC ME0261, TAC ME0262, TAC ME0263
Download: ML101960636 (4)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 July 16, 2010 Mr. Randall Edington Executive Vice President, Nuclear Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072 REVISION OF SCHEDULE FOR REVIEW FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION (TAC NOS. ME0261, ME 0262, AND ME0263)

Dear Mr. Edington:

Enclosed are changes to the schedule for the review of the Palo Verde Nuclear Generating Station license renewal application.

The issuance date of the Final Supplemental Environmental Impact Statement (SEIS) has been delayed until January 24, 2011. As discussed with your staff, this delay is primarily the result of staff time necessary to develop certain sections of the draft SEIS associated with environmental impact statements within the jurisdiction of the United States Court of Appeals for the Ninth Circuit. If you have any questions on the revised schedule, please contact me at 301-415-2878.

For questions on the environmental review, please contact David Drucker at 301-415-6223 or by e-mail at david.drucker@nrc.gov. Sincerely, tf..ut,Jay Robinson, Chief (J -Program Operations Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, 50-530

Enclosure:

As stated cc wi encl: Distribution via Listserv PALO VERDE NUCLEAR GENERATING LICENSE RENEWAL REVISION OF Milestone Schedule Actual Issue Draft Supplemental Environmental Impact Statement (SEIS) 7/15/10 8/12/10 FRN Published

-Availability 1 Comment on draft SEIS 7/30/10 8/23/10 Public Meeting -draft SEIS 9/2110 9/15/10 End of draft SEIS Comment Period 9/16/10 10/22/10 Final SEIS -Issued 12/22/10 1111111 FRN Published

-Availability of Final SEIS 1/14/11 1/24/11 July 16,2010 Mr. Randall K. Edington Executive Vice President, Nuclear Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072 REVISION OF SCHEDULE FOR REVIEW FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1,2, AND 3 LICENSE RENEWAL APPLICATION (TAC NOS. ME0261, ME 0262, ME0263)

Dear Mr. Edington:

Enclosed are changes to the schedule for the review of the Palo Verde Nuclear Generating Station license renewal application.

The issuance date of the Final Supplemental Environmental Impact Statement (SEIS) has been delayed until January 24, 2011. As discussed with your staff, this delay is primarily the result of staff time necessary to develop certain sections of the draft SEIS associated with environmental impact statements within the jurisdiction of the United States Court of Appeals for the Ninth Circuit. If you have any questions on the revised schedule, please contact me at 301-415-2878.

For questions on the environmental review, please contact David Drucker at 301-415-6223 or by e-mail at david.drucker@nrc.gov.

Sincerely, IRA! D. Drucker for Jay Robinson, Chief Program Operations Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, 50-530

Enclosure:

As stated cc wI encl: Distribution via Listserv DISTRIBUTION:

See next page ADAMS Accession No 'ML101960636

.. OFFICE PM:RPOB:DLR LA:DLR BC:RPOB:DLR NAME DDrucker IKing JRob' DATE 07/16/10 07/16/10 07/16/10 OFFICIAL RECORD COpy Letter to Randall K. Edington from Jay Robinson dated July 16, 2010 REVISION OF SCHEDULE FOR REVIEW FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1,2, AND 3 LICENSE RENEWAL APPLICATION (TAC NOS. ME0261, ME 0262, AND ME0263) DISTRIBUTION:

HARDCOPY:

DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDIrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource LRegner DDrucker BMizuno RHall RTreadway, RIV GPick, RIV ATorres