ML13179A293

From kanterella
Revision as of 02:14, 22 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation)
ML13179A293
Person / Time
Site: Salem  PSEG icon.png
Issue date: 06/26/2013
From: John Hughey
Plant Licensing Branch 1
To: Duke P
Public Service Enterprise Group
Hughey J
Shared Package
ML13179A286 List:
References
Download: ML13179A293 (1)


Text

From:Hughey, John To:Duke, Paul R. (Paul.Duke@pseg.com)

Subject:

RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation)

Date:Wednesday, June 26, 2013 10:51:00 AM Attachments:Draft RAI.doc Paul,By letter dated February 28, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML130640502), PSEG Nuclear, LLC, submitted an Overall Integrated Plan (OIP) in response to the March 12, 2012, U.S.

Nuclear RegulatoryCommission (NRC), Commission Order modifying licenses with regard to requirements for Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA 051; ADAMSAccession No. ML12054A679) for Salem Nuclear Generating Station Units 1 and 2.

The NRC staff has reviewed the February 28, 2013, response and determined that the attached Draft Request for Additional Information (RAI) is needed to complete its Technical

Review. If any part of this information is not available by July 26, 2013, please provide thedate this information will be submitted.

Please contact me by Monday, July 1, 2013, If youwould like to hold a teleconference to discuss these draft questions, before they are formally transmitted to you.

Thanks, John

John HugheySalem / Hope Creek Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204e-mail: John.Hughey@nrc.gov