Letter Sequence Approval |
---|
|
|
MONTHYEARML16196A3032016-08-0101 August 2016 Issuance of Amendment Technical Specifications Surveillance Requirement 3.5.1.3 B to Correct Alternative Nitrogen System Pressure (Cac. No. MF6704) Project stage: Approval 2016-08-01
[Table View] |
|
---|
Category:Letter
MONTHYEARL-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance ML24115A2972024-04-25025 April 2024 Sec106 Tribal, Miller, Cole-Shakopee Mdewakanton Sioux Community L-MT-24-012, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A2902024-04-25025 April 2024 Sec106 Tribal, Jackson-Street, Lonna-Spirit Lake Nation ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe ML24115A2882024-04-25025 April 2024 Sec106 Tribal, Fairbanks, Michael-White Earth Nation.Docx ML24115A3012024-04-25025 April 2024 Sec106 Tribal, Seki, Darrell-Red Lake Nation ML24115A2922024-04-25025 April 2024 Sec106 Tribal, Jensvold, Kevin-Upper Sioux Community ML24115A2942024-04-25025 April 2024 Sec106 Tribal, Johnson, John-Lac Du Flambeau Band of Lake Superior Chippewa Indians ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3002024-04-25025 April 2024 Sec106 Tribal, Rhodd, Timothy-Iowa Tribe of Kansas and Nebraska ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa 2024-09-26
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23262B2272023-09-21021 September 2023 September 21, 2023, Pre-Submittal Meeting on License Amendment Request to Revise PTLR to Incorporate New Surveillance Capsule Data (EPID L-2023-LRM-0070) (Slides) ML22357A1002023-03-31031 March 2023 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations Facility ML23012A1562023-01-13013 January 2023 Issuance of Amendment No. 210 Re Revised Methodologies for Determining the Core Operating Limits (EPID L-2021-LLA-0144) - Non-proprietary ML22318A2152022-12-27027 December 2022 Issuance of Amendment No. 209 Ten-Year Inspection of the Diesel Generator Fuel Oil Storage Tank ML22308A1962022-11-10010 November 2022 Regulatory Audit Report Regarding License Amendment Request to Transition to Atrium 11 Fuel ML22264A1062022-10-31031 October 2022 Issuance of Amendment No. 208 Residual Heat Removal Drywell Spray Header and Nozzle Surveillance Frequency ML22208A2192022-08-0303 August 2022 Summary of July 25, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Amendment to Adopt Advanced Framatome Inc. Methodology for Determining Core Operating Limits for Monticello Plant ML21223A2802021-10-15015 October 2021 Issuance of Amendment No. 207 Adoption of TSTF-564 Safety Limit MCPR ML21148A2742021-07-12012 July 2021 Issuance of Amendment No. 206 TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20352A3492021-01-0808 January 2021 Issuance of Amendment No. 205, Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-582, RPV WIC Enhancements, and TSTF-583-T, TSTF-582 Diesel Generator Variation ML20210M0142020-09-0808 September 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Nos. 204, 231, and 219 TSTF-529 Clarify Use and Application Rules ML20153A8042020-07-31031 July 2020 Co. - Issuance of Amendments Revising Emergency Action RA3 ML19176A4212019-08-29029 August 2019 Issuance of Amendment No. 203 Adoption of 10 CFR 50.69 ML19162A0932019-07-30030 July 2019 Issuance of Amendment No, 202 Regarding Deletion of the Note Associated with Technical Specification 3.5.1., Erccs - Operating ML19074A2692019-04-22022 April 2019 Non-Proprietary - Issuance of Amendment Revision to Technical Specifications 2.1.2 Safety Limit Minimum Critical Power Ratio ML19065A2002019-03-11011 March 2019 Correction to License Amendment No. 200 Related to Adoption of TSTF-425, Relocated Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B ML19007A0902019-01-28028 January 2019 Issuance of Amendment Adoption of TSTF-425, Relocate Surveillance Frequencies to Licensee Control-RITSTF Initiative 5B ML18291B2142018-11-26026 November 2018 Issuance of Amendment Adoption of TSTF-551 Revise Secondary Containment Surveillance Requirements ML18250A0752018-10-29029 October 2018 Issuance of Amendment Adoption of TSTF-542, Reactor Pressure Vessel Water Inventory Control ML17345A0462018-03-0606 March 2018 Issuance of Amendment No. 197 to Adopt Changes to the Emergency Plan (CAC No. MF9560; EPID L-2017-LLA-0184) ML17310B2392017-11-28028 November 2017 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Unit Staff Qualifications (CAC Nos. MF9545, MF9546, and MF9547; EPID L-2017-LLA-0195) ML17172A4312017-06-23023 June 2017 Correction of Amendment No. 194, Issuance of Amendment to Adopt F Tstf 545, Revision 3, Ts Inservice Testing Program Removal & Clarify Sr Usage Rule Application to Section 5.5 Testing ML17123A3212017-06-16016 June 2017 Issuance of Amendment Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal and Clarify SR Usage Rule Application to Section 5.5 Testing ML17103A2352017-04-25025 April 2017 Issuance of Amendment Technical Specification 5.5.11 Primary Containment Leakage Rate Testing Program ML17013A4352017-02-27027 February 2017 Issuance of Amendment Revision to Technical Specification Surveillance Requirement 3.8.4.2 ML17054C3942017-02-23023 February 2017 Non-Proprietary Issuance of Amendment Extended Flow Window ML16196A3032016-08-0101 August 2016 Issuance of Amendment Technical Specifications Surveillance Requirement 3.5.1.3 B to Correct Alternative Nitrogen System Pressure (Cac. No. MF6704) ML16125A1652016-06-21021 June 2016 Issuance of Amendment Technical Specifications Task Force (TSTF) Standard Technical Specifications (STS) Change Traveler TSTF-523, Revision 2 Generic Letter 2008-01, Managing Gas Accumulation ML16063A0332016-02-29029 February 2016 License Amendment Request for Areva Extended Flow Window Supplement to Disposition Changes to Non-Limiting Transient Analyses ML15072A1412015-06-0505 June 2015 Issuance of Amendment No. 188 Regarding Transition to Areva Atrium 10XM Fuel and Areva Safety Analysis Methods ML14323A0332015-01-0808 January 2015 Issuance of Amendment No. 187 Regarding Revision to TS 5.5.11 for Drywell Personnel Airlock Leakage Rate Testing ML14239A2572014-11-28028 November 2014 and Prairie Island Nuclear Generation Plant, Units 1 and 2 - Issuance of License Amendments Regarding Cyber Security Plan Implementation Schedule Milestones ML14281A3182014-11-25025 November 2014 Issuance of Amendment Regarding Reduction in Steam Dome Pressure Safety Limit ML14246A4492014-11-0303 November 2014 Issuance of Amendment to Revise TS 3.5.1, ECCS - Operating ML14196A3282014-10-31031 October 2014 Issuance of Amendment to Change the Site Emergency Plan to Remove the Radwaste Operator as One of the 60-Minute Responders Specified in the Site Emergency Plan ML15160A2072014-10-24024 October 2014 Redacted, Issuance of Amendment No. 182 to Revise the Technical Specifications to Support Fuel Storage System Changes ML14058A8252014-05-0202 May 2014 Issuance of Amendment No. 181 to Adopt TSTF-522, Revision 0, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month ML14035A2482014-03-28028 March 2014 Issuance of Amendment No. 180 to Implement Maximum Extended Load Line Limit Analysis Plus (Mellla+) Operating Domain ML14027A2322014-02-28028 February 2014 Issuance of Amendment No. 179 to Adopt TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs ML13218A0612014-01-28028 January 2014 Issuance of Amendment No. 178 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML13274A1732014-01-28028 January 2014 Issuance of License Amendment No. 177 to Renewed Facility Operating License Emergency Plan Change ML13316B2982013-12-0909 December 2013 Issuance of Amendment No. 176 to Renewed Facility Operating License Regarding Extended Power Uprate ML13168A3732013-08-28028 August 2013 Issuance of Amendment No. 175 to Make Minor Corrections and Editorial Changes, Clarify Fuel Storage Capacity, and Remove Obsolete Information ML13168A2192013-08-0909 August 2013 Issuance of Amendment No. 174 to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities ML13168A0252013-07-15015 July 2013 Issuance of Amendment No. 173 to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-476, Revision 1, Improved BPWS Control Rod Insertion Process (NEDO-33091) ML13025A1552013-02-27027 February 2013 Issuance of License Amendment No. 172 to Revise and Relocate Pressure Temperature Curves to a Pressure-Temperature Limits Report ML12339A0352013-01-25025 January 2013 Issuance of License Amendment No. 171 Regarding Restoration Period Before Declaring Average Power Range Monitors Inoperable When Surveillance Requirement 3.3.1.1.2 Is Not Met ML12220A2802012-09-0707 September 2012 Issuance of Amendment No. 170 Regarding Automatic Depressurization System Bypass Timer ML12216A2692012-08-27027 August 2012 Issuance of Amendment No. 169 Regarding the Licensing Basis of the 1AR Transformer ML12185A2162012-07-27027 July 2012 Issuance of Amendment No. 168 Regarding Safety/Relieve Valves Testing 2023-09-21
[Table view] Category:Safety Evaluation
MONTHYEARML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves ML24138A1212024-07-0202 July 2024 Alternative Request RR-002 ML24077A0012024-03-18018 March 2024 Safety Evaluation to the SLRA of Monticello Nuclear Generating Plant, Unit 1 ML23248A2092023-09-18018 September 2023 Proposed Alternative VR-11 to the Requirements of the ASME OM Code Associated with Periodic Verification Testing of MO-2397, Reactor Water Cleanup Inboard Isolation Valve ML23107A2852023-04-25025 April 2023 Authorization and Safety Evaluation for Alternative Request PR-08 ML23079A0742023-04-11011 April 2023 Request RR-003 to Use Later Edition of ASME Section XI Code for ISI Code of Record ML22357A1002023-03-31031 March 2023 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations Facility ML23012A1562023-01-13013 January 2023 Issuance of Amendment No. 210 Re Revised Methodologies for Determining the Core Operating Limits (EPID L-2021-LLA-0144) - Non-proprietary ML22318A2152022-12-27027 December 2022 Issuance of Amendment No. 209 Ten-Year Inspection of the Diesel Generator Fuel Oil Storage Tank ML22264A1062022-10-31031 October 2022 Issuance of Amendment No. 208 Residual Heat Removal Drywell Spray Header and Nozzle Surveillance Frequency ML22270A2312022-09-30030 September 2022 Authorization and Safety Evaluation for Alternative Request No. VR-10 ML22154A5502022-06-0707 June 2022 Authorization and Safety Evaluation for Alternative Request No. PR-02 ML22126A1342022-05-12012 May 2022 Authorization and Safety Evaluation for Alternative Request No. PR-05 ML22098A1272022-05-0202 May 2022 Authorization and Safety Evaluation for Alternative Request No. VR-02 ML22018A1772022-01-21021 January 2022 Authorization and Safety Evaluation for Alternative Request No. VR-05 ML21223A2802021-10-15015 October 2021 Issuance of Amendment No. 207 Adoption of TSTF-564 Safety Limit MCPR ML21148A2742021-07-12012 July 2021 Issuance of Amendment No. 206 TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20352A3492021-01-0808 January 2021 Issuance of Amendment No. 205, Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-582, RPV WIC Enhancements, and TSTF-583-T, TSTF-582 Diesel Generator Variation ML20346A0972020-12-21021 December 2020 Request for Alternative for Examination of Reactor Pressure Vessel Threads in Flange ML20336A1602020-12-0909 December 2020 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20307A0172020-11-0202 November 2020 Request for Alternative for Core Support Structure Weld Examination ML20210M0142020-09-0808 September 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Nos. 204, 231, and 219 TSTF-529 Clarify Use and Application Rules ML20153A8042020-07-31031 July 2020 Co. - Issuance of Amendments Revising Emergency Action RA3 ML20174A5452020-07-15015 July 2020 Request for Alternative for Pressure Isolation Valve Testing ML20153A4012020-06-0101 June 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Relief from the Requirements of the ASME Code ML20135G9922020-05-29029 May 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Relief from the Requirements of the ASME Code ML20134H9582020-05-29029 May 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Relief from the Requirements of the ASME Code ML19255F5822019-10-0101 October 2019 Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 (CAC No. MF4376; EPID No. L-2014-JLD-0052) ML19162A0932019-07-30030 July 2019 Issuance of Amendment No, 202 Regarding Deletion of the Note Associated with Technical Specification 3.5.1., Erccs - Operating ML19074A2692019-04-22022 April 2019 Non-Proprietary - Issuance of Amendment Revision to Technical Specifications 2.1.2 Safety Limit Minimum Critical Power Ratio ML19052A1422019-03-11011 March 2019 Correction to License Amendment No. 198 Related to Adoption of TSTF-542, Reactor Pressure Vessel Water Inventory Control ML19065A2002019-03-11011 March 2019 Correction to License Amendment No. 200 Related to Adoption of TSTF-425, Relocated Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B ML19007A0902019-01-28028 January 2019 Issuance of Amendment Adoption of TSTF-425, Relocate Surveillance Frequencies to Licensee Control-RITSTF Initiative 5B ML18291B2142018-11-26026 November 2018 Issuance of Amendment Adoption of TSTF-551 Revise Secondary Containment Surveillance Requirements ML18250A0752018-10-29029 October 2018 Issuance of Amendment Adoption of TSTF-542, Reactor Pressure Vessel Water Inventory Control ML18270A0152018-10-19019 October 2018 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Relief from the Requirements of the ASME OM Code ML17345A0462018-03-0606 March 2018 Issuance of Amendment No. 197 to Adopt Changes to the Emergency Plan (CAC No. MF9560; EPID L-2017-LLA-0184) ML17319A5912017-12-10010 December 2017 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML17310B2392017-11-28028 November 2017 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Unit Staff Qualifications (CAC Nos. MF9545, MF9546, and MF9547; EPID L-2017-LLA-0195) ML17123A3212017-06-16016 June 2017 Issuance of Amendment Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal and Clarify SR Usage Rule Application to Section 5.5 Testing ML17122A1572017-05-15015 May 2017 Request for Alternative to Use Code Case OMN-20 for the Fifth 10-Year Inservice Testing Interval ML17103A2352017-04-25025 April 2017 Issuance of Amendment Technical Specification 5.5.11 Primary Containment Leakage Rate Testing Program ML17013A4352017-02-27027 February 2017 Issuance of Amendment Revision to Technical Specification Surveillance Requirement 3.8.4.2 ML17054C3942017-02-23023 February 2017 Non-Proprietary Issuance of Amendment Extended Flow Window ML16320A0212016-11-28028 November 2016 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Review of Changes to the Northern States Power Company Quality Assurance Topical Report ML16244A1202016-09-0606 September 2016 Generation Plant - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Vents) ML16208A4622016-08-0303 August 2016 Safety Evaluation for Request for Alternative Associated with Reactor Pressure Vessel Internals and Components Inspection for the Fifth 10-Year Interval ML16196A3032016-08-0101 August 2016 Issuance of Amendment Technical Specifications Surveillance Requirement 3.5.1.3 B to Correct Alternative Nitrogen System Pressure (Cac. No. MF6704) ML16125A1652016-06-21021 June 2016 Issuance of Amendment Technical Specifications Task Force (TSTF) Standard Technical Specifications (STS) Change Traveler TSTF-523, Revision 2 Generic Letter 2008-01, Managing Gas Accumulation ML15175A0162015-06-30030 June 2015 Staff Evaluation of 10 CFR 50.54(p)(2) Changes to Security Plans 2024-08-27
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Peter A. Gardner Site Vice President Monticello Nuclear Generating Plant August 1, 2016 Northern States Power Company -Minnesota (NSPM) 2807 West County Road 75 Monticello, MN 55362-9637
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT -ISSUANCE OF AMENDMENT RE: TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT 3.5.1.3.B TO CORRECT ALTERNATE NITROGEN SYSTEM PRESSURE (CAC NO. MF6704)
Dear Mr. Gardner:
The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 190 to Renewed Facility Operating License No. DPR-22 for the Monticello Nuclear Generating Plant. The amendment consists of changes to the technical specifications (TSs) in response to your application dated September 2, 2015. The amendment revises TS Surveillance Requirement 3.5.1.3.b to require verification that the alternate nitrogen system pressure be greater than or equal to 1060 pounds per square inch gauge. A copy of our related safety evaluation is also enclosed.
The Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket No. 50-263
Enclosures:
- 1. Amendment No. 190 to DPR-22 2. Safety Evaluation cc w/encls: Distribution via ListServ Sincerely, Robert F. Kunt , Se ior Project Manager Plant Licensin B nch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 NORTHERN STATES POWER COMPANY DOCKET NO. 50-263 MONTICELLO NUCLEAR GENERATING PLANT AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 190 License No. DPR-22 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that: A. The application for amendment by Northern States Power Company (NSPM, the licensee), dated September 2, 2015, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; 8. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.2 of Renewed Facility Operating License No. DPR-22 is hereby amended to read as follows: Enclosure 1 Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 190, are hereby incorporated in the license. NSPM shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 90 days. FOR THE NUCLEAR REGULATORY COMMISSION
- !--
Attachment:
Changes to the Renewed Operating License No. DPR-22 and Technical Specifications Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Date of Issuance:
August 1, 2016 ATTACHMENT TO LICENSE AMENDMENT NO. 190 RENEWED FACILITY OPERATING LICENSE NO. DPR-22 DOCKET NO. 50-263 Replace the following page of Renewed Facility Operating License DPR-22 with the attached revised page. The revised page is identified by amendment number and contains a marginal line indicating the area of change. REMOVE INSERT 3 3 Replace the following pages of Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change. REMOVE INSERT 3.5.1-5 3.5.1-5 2. Pursuant to the Act and 1 O CFR Part 70, NSPM to receive, possess, and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operations, as described in the Final Safety Analysis Report, as supplemented and amended, and the licensee's filings dated August 16, 197 4 (those portions dealing with handling of reactor fuel); 3. Pursuant to the Act and 10 CFR Parts 30, 40 and 70, NSPM to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required;
- 4. Pursuant to the Act and 1 O CFR Parts 30, 40 and 70, NSPM to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and 5. Pursuant to the Act and 10 CFR Parts 30 and 70, NSPM to possess, but not separate, such byproduct and special nuclear material as may be produced by operation of the facility.
C. This renewed operating license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission, now or hereafter in effect; and is subject to the additional conditions specified or incorporated below: 1. Maximum Power Level NSPM is authorized to operate the facility at steady state reactor core power levels not in excess of 2004 megawatts (thermal).
- 2. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 190, are hereby incorporated in the license. NSPM shall operate the facility in accordance with the Technical Specifications.
- 3. Physical Protection NSPM shall implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Renewed License No. DPR-22 Amendment No. 190 SURVEILLANCE REQUIREMENTS SURVEILLANCE SR 3.5.1.1 Verify, for each ECCS injection/spray subsystem, locations susceptible to gas accumulation are sufficiently filled with water. SR 3.5.1.2 -------------------------------NOTE------------------------------
Not required to be met for system vent flow paths opened under administrative control. ---------------------------------------------------------------------
Verify each ECCS injection/spray subsystem manual, power operated, and automatic valve in the flow path, that is not locked, sealed, or otherwise secured in position, is in the correct position.
SR 3.5.1.3 Verify ADS pneumatic pressure is as follows for each required ADS pneumatic supply: a. S/RV Accumulator Bank header pressure ;::: 88.3 psig; and b. Alternate Nitrogen System pressure is ;::: 1060 psig. SR 3.5.1.4 -------------------------------N 0 TE------------------------------
Only required to be met in MODE 1. ---------------------------------------------------------------------
Verify the RHR System intertie return line isolation valves are closed. SR 3.5.1.5 Verify correct breaker alignment to the LPCI swing bus. SR 3.5.1.6 Verify each recirculation pump discharge valve cycles through one complete cycle of full travel or is de-energized in the closed position.
ECCS -Operating 3.5.1 FREQUENCY 31 days 31 days 31 days 31 days 31 days In accordance with the lnservice Testing Program Monticello 3.5.1-5 Amendment No. 146, 155, 162, 189, 190 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 190 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-22 NORTHERN STATES POWER COMPANY MONTICELLO NUCLEAR GENERATING PLANT DOCKET NO. 50-263
1.0 INTRODUCTION
By application dated September 2, 2015, (Agencywide Documents Access and Management System (ADAMS Accession No. ML15246A530), Northern States Power Company (NSPM, the licensee), requested changes to the technical specifications (TSs) for Monticello Nuclear Generating Plant (MNGP). The proposed changes would revise TS Surveillance Requirement 3.5.1.3.b to require verification that the MNGP alternate nitrogen system (ANS) required pressure be greater than or equal to 1060 pounds per square inch gauge (psig) instead of greater than or equal to 410 psig as is currently stated.
2.0 REGULATORY EVALUATION
Title 10 of The Code of Federal Regulations (10 CFR) Section 50.36(c)(3) states that SRs are requirements relating to test, calibration, or inspection to assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the limiting conditions for operation will be met. NUREG-0737, "Clarification of TM/ Action Plan Requirements," Item ll.K.3.28, requires long term (100 day) post-accident depressurization capability to assure long term shutdown cooling operability.
3.0 TECHNICAL EVALUATION As discussed in the license amendment request, the licensee determined that the current MNGP technical specification value for ANS is non-conservative.
The non-conservatism exists based on non-conservative errors and deficiencies identified in the calculation that supports ANS operability.
Upon discovery of the errors, the licensee implemented administrative controls to maintain ANS pressure above 1060 psig, 1n accordance with the guidance of U.S. Nuclear Enclosure 2 Regulatory Commission (NRC or Commission)
Administrative Letter 98-10, "Disposition of Technical Specifications that are Insufficient to Assure Plant Safety" (ADAMS Accession No. ML031110108).
To correct the non-conservatisms in the technical specifications, the licensee submitted the September 2, 2015, license amendment request. The ANS system provides automatic, safety-related, long-term, backup pneumatic supply upon loss of the nonsafety-related instrument air/nitrogen system distribution.
It is split into an A and B train, which services various loads, including six safety relief valves (SRVs) associated with the automatic depressurization system (ADS), low-low set (LLS), and the alternate shutdown and manual depressurization functions.
The NRC staff has reviewed the licensee's request to ensure it has no effect on the ability of the ANS system to perform its required ADS function.
The NRC staff also reviewed the submitted information to ensure that the ANS system provides sufficient capacity to cycle the ADS valves five times at design pressure to satisfy Three Mile Island (TMI) action item 11.K.3.28 of NUREG-0737. Operability of the ANS is based on the capability to provide sufficient volume to its safety and required nonsafety loads. The loads of the B train of ANS bound those served by the A train. For that reason, the B train loads were used for calculation of the surveillance requirement pressure for ANS operability.
The B train ANS loads consist of one ADS SRV, one LLS SRV, one manually operated SRV, four inboard main steam isolation valves, three T-ring seals on the containment purge and vent valves, and the hard piped vent system. The licensee stated that a pressure switch in each ANS subsystem isolates the nitrogen supply from its loads when pressure decreases to 330 psig. To determine the required nitrogen bottle pressure for operability, the volume of nitrogen required to operate the loads was added to the volume of nitrogen remaining at the minimum pressure.
The licensee stated that an isentropic expansion of the nitrogen as it exits the bottles was assumed. This method is conservative to an isothermal expansion because it results in the lowest pressures in the ANS system. The Ideal Gas equation for isentropic expansion was used because the lower the pressure in the ANS system during operation of equipment, the more mass that will initially flow from the ANS tanks into the system. The required ANS load volume is added to the volume remaining in the nitrogen bottles at the time of low pressure isolation.
A conservative isolation pressure of 500 psig was used which also allows additional margin for instrument error. The NRC staff reviewed the description of the licensee's calculations in the amendment request, and verified that the ANS B train was capable of providing ten SRV actuations (five actuations for each of the two SRVs (one ADS and one LLS) supplied by ANS B train) supporting TMI action item ll.K.3.28 in addition to other system design functions.
Thus, the NRC staff concludes that the proposed change to TS surveillance requirement 3.5.1.3.b is consistent with the MNGP licensing basis, and therefore is acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Minnesota State official was notified of the proposed issuance of the amendment.
The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION The amendment changes a requirement with respect to the installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes the SRs. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure.
The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration and there has been no public comment on such finding (80 FR 61483; dated October 13, 2015). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Pursuant to 1 O CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public. Principal Contributor:
T. Sweat Date of issuance:
August 1, 2016 Mr. Peter A. Gardner Site Vice President Monticello Nuclear Generating Plant August 1, 2016 Northern States Power Company -Minnesota (NSPM) 2807 West County Road 75 Monticello, MN 55362-9637
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT -ISSUANCE OF AMENDMENT RE: TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT 3.5.1.3.B TO CORRECT ALTERNATE NITROGEN SYSTEM PRESSURE (CAC NO. MF6704)
Dear Mr. Gardner:
The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 190 to Renewed Facility Operating License No. DPR-22 for the Monticello Nuclear Generating Plant. The amendment consists of changes to the technical specifications (TSs) in response to your application dated September 2, 2015. The amendment revises TS Surveillance Requirement 3.5.1.3.b to require verification that the alternate nitrogen system pressure be greater than or equal to 1060 pounds per square inch gauge. A copy of our related safety evaluation is also enclosed.
The Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket No. 50-263
Enclosures:
- 1. Amendment No. 190 to DPR-22 2. Safety Evaluation cc w/encls: Distribution via ListServ DISTRIBUTION PUBLIC RidsNrrDssStsb Resource RidsNrrDorllpl3-1 Resource RidsNrrLASRohrer Resource RidsRgn3MailCenter Resource ADAMS Accession No.: ML16196A303 OFFICE LPL3-1/PM LPL3-1/LA NAME RKuntz SRohrer DATE 7/18/16 7/18/16 Sincerely, IRA/ Robert F. Kuntz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LPL3-1 r/f RidsNrrDorlDpr Resource RidsNrrPMMonticello Resource RidsNrrDssSbpb RidsAcrs_MailCTR Resource SB PB/BC STSB/BC OGC/NLO LPL3-1/BC RDennig AKlein Jlindell DWrona 7/18/16 7/19/16 7/26/16 8/1/16 OFFICIAL RECORD COPY LPL3-1/PM RKuntz 8/1 /16