0CAN081402, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees)
ML14241A660 | |
Person / Time | |
---|---|
Site: | Arkansas Nuclear ![]() |
Issue date: | 08/28/2014 |
From: | Browning J G Entergy Operations |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
0CAN081402, EA-12-049 | |
Download: ML14241A660 (20) | |
Text
0CAN081402
August 28, 2014
U.S. Nuclear Regulatory Commission
ATTN: Document Control Desk
11555 Rockville Pike
Rockville, MD 20852
SUBJECT:
Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for
Mitigation Strategies for Beyond-Design-Basis External Events (BDBEEs)
(Order Number EA-12-049)
Arkansas Nuclear One - Units 1 and 2
Docket Nos. 50-313 and 50-368
REFERENCES:
- 1. NRC Order Number EA-12-049, Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs , dated March 12, 2012 (0CNA031206) (ML12056A045)
- 2. Entergy letter to NRC, Overall Integrated Plan (OIP) in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (Order Number EA-12-049), dated February 28, 2013 (0CAN021302) (ML13063A151)
- 3. Entergy letter to NRC, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (Order Number EA-12-049), dated August 28, 2013 (0CAN081302)
- 4. Entergy letter to NRC, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (Order Number EA-12-049), dated February 27, 2014 (0CAN021405)
Dear Sir or Madam:
On March 12, 2012, the NRC issued an order (Reference 1) to Entergy Operations, Inc.
(Entergy) which required submission an OIP pursuant to Section IV, Condition C which
was provided by Reference 2.
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802
Tel 479-858-3110 Jeremy G. Browning Site Vice President A rkansas Nuclear One
0CAN081402 Page 2 of 2 Reference 1 also requires submission of a status report at six-month intervals following submittal of the OIP. References 3 and 4 provided the first and second six-month status
reports, respectively. The purpose of this letter is to provide the third six-month status
report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress
made in implementing the requirements of Re ference 1. The attached report provides an update of milestone accomplishments since the last status report, including any
changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no new regulatory commitments. Should you have any questions
regarding this submittal, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct; executed on
August 28, 2014.
Sincerely, ORIGINAL SIGNED BY JEREMY G. BROWNING
JGB/nbm
Attachment:
Arkansas Nuclear One Units 1 and 2 Third Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with
Regard to Requirements for Mitigation Strategies for BDBEEs
cc: Mr. Marc L. Dapas Regional Administrator
U. S. Nuclear Regulatory Commission, Region IV
1600 East Lamar Boulevard Arlington, TX 76011-4511
NRC Senior Resident Inspector
Arkansas Nuclear One
P.O. Box 310
London, AR 72847
U. S. Nuclear Regulatory Commission
Attn: Ms. Andrea E. George
MS O-8B1 One White Flint North
11555 Rockville Pike
Rockville, MD 20852
U. S. Nuclear Regulatory Commission
Attn: Mr. John Hughey
MS 13-C5 One White Flint North
11555 Rockville Pike
Rockville, MD 20852
Attachment to 0CAN081402 Arkansas Nuclear One (ANO) Units 1 and 2 (ANO-1 and ANO-2) Third Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (BDBEEs)
Attachment to 0CAN081402
Page 1 of 17 ANO-1 and ANO-2 Third Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs 1 Introduction Entergy Operations, Inc. (Entergy) developed an Overall Integrated Plan (OIP) for ANO-1 and ANO-2 (Reference 1), documenting the diverse and flexible strategies (FLEX) in response to Reference 2. The OIP was updated and submitted with the First
Six-Month Status Report (Reference 3). This enclosure provides an update of milestone
accomplishments since submittal of the last status report (Reference 8), including any
changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any. 2 Milestone Accomplishments The following milestone(s) have been completed since January 31, 2014, and are current as of July 31, 2014: Second Six-Month Status Report - February 2014 Modifications Evaluation - January 2014 Third Six-Month Status Report - Complete with submission of this document in August 2014 3 Milestone Schedule Status The following provides an update to the milestone schedule to support the OIP. It provides the activity status of each item, and whether the expected completion date has
changed. The dates are planning dates subject to change as design and
implementation details are developed.
Milestone Target Completion Date* Activity Status Revised Target Completion Date Submit OIP February 2013 Complete Update 1 August 2013 Complete Update 2 February 2014 Complete Update 3 August 2014 Complete Update 4 February 2015 Not Started Update 5 August-2015 Not Started Perform Staffing Analysis September 2014 Started Attachment to 0CAN081402
Page 2 of 17 Milestone Target Completion Date* Activity Status Revised Target Completion Date Modifications Modifications Evaluation June 2013 Complete Engineering and Implementation June 2013 -
October 2015 Started ANO-1 Implementation Outage February 2015 Not Started ANO-2 Implementation Outage October 2015 Not Started On-site FLEX Equipment Purchase June 2014 Started October 2014 Procure November 2014Not Started August 2015 Off-site FLEX Equipment Develop Strategies with Regional Response Center November 2013Started November 2014 Install Off-site Delivery Station (if necessary) October 2014 Complete Procedures Pressurized Water Reactor Owners Group issues Nuclear
System Steam Supply (NSSS)-specific guidelines June 2013 Completed Issued May 2013 Create ANO FLEX Strategy Guide November 2014Started Create Maintenance Procedures November 2014Not Started Training Develop Training Plan June 2014 Started December 2014 Implement Training November 2014Started August 2015 Validation ANO-1 walk-throughs or demonstration(s) - including all FLEX equipment points of
connect/tie-in for Phase 2
and 3 March 2015 Not Started Attachment to 0CAN081402
Page 3 of 17 Milestone Target Completion Date* Activity Status Revised Target Completion Date ANO-2 walk-throughs or demonstration(s) - including all FLEX equipment points of
connect/tie-in for Phase 2
and 3 October 2015 Not Started Submit Completion Report February 2016 Not Started Note: *Target Completion Date is the last submitted date from either the OIP or previous six month status reports. 4 Changes to Compliance Method In the continuing design development phase of the FLEX project at ANO, changes have been identified to the compliance strategies as described in the original OIP. The use of a portable FLEX reactor coolant system (RCS) makeup pump during Phase 2 for ANO-2 has been changed. The current strategy is to use an ANO-2 charging pump as the injection source to meet the FLEX RCS inventory control
requirements for ANO-2 after the ANO-1 RCS cooldown is complete (Interim Safety
Evaluation (ISE) Open Item 3.2.1.D and Audit Questions (AQ) ANO-035, ANO-046, ANO-106 and ANO-107). The NRC staff concluded "-.that the licensee provided
sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet t he requirements of Order EA 12-049 at ANO-1 and ANO-2." (Reference 7). ANO-2 cooldown and depressurization strategy would be implemented within two hours of the ELAP event in accordance with WCAP-17601-P and as assumed in the
specific ANO-2 site analysis (ISE Confirmatory Item 3.2.1.B, and AQ ANO-014, ANO-015, ANO-018, ANO-021, ANO-025, ANO-035, ANO-049, ANO-051, ANO-075, ANO-077, ANO-078, and ANO-085) (Reference 9). Entergy is submitting the following alternative to NEI 12-06 which is necessary to support the ANO-1 and ANO-2 strategies. The final analysis is expected by the end of the year 2015. The ANO-1 and ANO-2 strategy for FLEX requires use of ANO-1's
Borated Water Storage Tank (BWST) and/or ANO-2's Refueling Water Tank (RWT).
These tanks are not required for safe shutdown and so were not previously
evaluated for tornado winds and tornado missiles in the current licensing basis. An
evaluation was performed to determine if the tanks are "robust" (per the definition in Appendix A of NEI 12-06) for tornado and tornado missiles for use in the ANO FLEX
strategy. NEI 12-06 defines robust as: "
Robust (designs): the design of an SSC either meets the current plant design basis for the applicable external hazards or has been shown by analysis or test to meet or exceed the current design basis."
When evaluated against current tornado wind and missile design basis for the site, the
ANO-1's BWST and ANO-2's RWT tanks do not meet the NEI definition of "robust".
Attachment to 0CAN081402
Page 4 of 17 For the current licensing basis, ANO-1's BWST and ANO-2's RWT are the normal sources for large inventory additions to their respective RCS or spent fuel pool.
They are located between the two units and they are partially protected by the reactor and turbine buildings. Each of the tanks has sufficient capacity to support the FLEX strategy for both units.
The tornado resistant design of the ANO units was completed prior to the issuance of Regulatory Guide (RG) 1.76, Design Basis Tornado and Tornado Missiles for Nuclear Power Plants, (ANO-1 Safety Analysis Report (SAR) Section 5.1.5 and ANO-2 SAR Section 3.3.2.1). The current design assumptions used for both units
are conservative relative to the criteria of RG 1.76 Revision 1. When applying the
conservative criteria of the current design basis of the site to ANO-1's BWST and
ANO-2's RWT, the tanks do not meet the NEI definition of "robust".
As an alternative to the NEI 12-06 definition of robust, i.e., the use of current plant design basis, Entergy is requesting approval of the use of RG 1.76 Revision 1 as the
criteria for robust with respect to tornado winds and missiles for the use of ANO-1's BWST and ANO-2's RWT for support of ANO FLEX strategies.
The preliminary evaluation indicates that, relative to RG 1.76 Revision 1, both tanks may be considered robust for tornados and tornado missiles and the ANO-1 and ANO-2 FLEX strategies may consider the tanks provide a robust source of borated
water. Prior to crediting the tanks for compliance with EA-12-049, Entergy plans to
complete a detailed evaluation to confirm and document the "robust" status of
ANO-1's BWST and ANO-2's RWT relative to tornado and tornado missiles
consistent with RG 1.76 Revision 1.
This evaluation is being used only for meeting NRC Order EA-12-049 and does not alter the current design bases of ANO-1's BWST and ANO-2's RWT. Nor does the
use of RG 1.76 Revision 1 for this evaluation indicate any intent by ANO to alter the
sites current design or licensing basis. The ANO-1 and ANO-2 strategy for FLEX requires use of the "Q" condensate storage tank (QCST). Using the same approach as the one described above for the
ANO-1 BWST and ANO-2 RWT, Entergy is currently pursuing applying RG 1.76
Revision 1 to the QCST to qualify additional water supply through a finite element
analysis. In a similar way as described above, this represents an alternative to
NEI 12-06 definition of robust. 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Entergy expects to comply with the order implementation date for ANO-2; however, as part of a separate submittal (Reference 5) Entergy requested an extension for ANO-1 for
no later than startup of ANO-2 from refueling outage 2R24 currently scheduled for
October 2015. The request was submitted to support the RCS inventory control strategy
associated with the alternate power connection for the charging pump. This request for
relief/relaxation for ANO-1 was approved by the NRC via Reference 6.
Attachment to 0CAN081402
Page 5 of 17 6 Open Items from OIP and Interim Staff Evaluation (ISE)
The following tables provide a summary and status of any open items documented in the OIP and any open items or confirmatory item s documented in the ISE (Reference 10).
Also provided is a listing of Audit Questions and the status of each item. OIP Open Items Status There were no open items documented in the ANO OIP. N/A ISE Open Items Status 3.2.1.D The NRC staff has reviewed the ANO approach that uses the ANO-2 charging pump to supply makeup
to the ANO-1 RCS for inventory control but has not
concluded that this approach is acceptable. The
staff has identified a number of concerns that need
to be addressed regarding the proposed RCS
inventory control strategy. Therefore, this open item tracks completion of the development of an
acceptable integrated RCS makeup strategy that
meets the requirements of Order EA-12-049.
This item is addressed by
updated AQ
ANO-035, ANO-046, ANO-106, and
ANO-107 responses
spreadsheet on the
ePortal. 3.2.1.8.B For ANO-1 and ANO-2, verify resolution of the generic concern associated with the modeling of the
timing and uniformity of the mixing of a liquid boric
acid solution injected into the RCS under natural
circulation conditions potentially involving two-phase
flow. This item is addressed by
updated AQ
ANO-041 response
spreadsheet on the
ePortal.
ISE Confirmatory Items Status 3.1.1.2.A Confirm whether there is a need for a power source to move or deploy the FLEX equipment (e.g., to
open the door from a storage location).
This item is addressed on
updated Audit
Question (AQ)
response spreadsheet on the
ePortal. 3.1.1.4.A Confirm that the local staging area for the Regional Response Center (RRC) equipment has been
identified and a description of the methods to be
used to deliver the equipment to the site has been
provided.
In progress. This item to be
addressed on
updated AQ
response spreadsheet on the
ePortal when the
information is
available.
Attachment to 0CAN081402
Page 6 of 17 ISE Confirmatory Items Status 3.1.3.1.A Confirm that the axis of separation and distance between the portable equipment storage buildings
provides assurance that a single tornado will not
impact both buildings.
This item is addressed by
updated AQ
ANO-002 response
spreadsheet on the
ePortal. 3.2.1.A Confirm that the Atmospheric Dump Valves and associated piping at both units are sufficiently
robust and will remain functional during and
following a seismic event.
This item is addressed by
updated AQ
ANO-109 response
spreadsheet on the
ePortal. 3.2.1.B Confirm that the ANO-2 cooldown analysis supports the delay in the cooldown to eight hours following
the ELAP.
This item is addressed by
updated AQ-014, 015, 018, 021, 025,035, 049, 051, 075, 077, 078, and
085 responses
spreadsheet on the
ePortal. 3.2.1.C Confirm that the evaluation of the emergency feedwater (EFW) turbine exhaust piping for
robustness is completed with acceptable results.
This item is addressed by
updated AQ 109
response spreadsheet on the
ePortal. 3.2.1.1.A Confirm that reliance on the RELAP5/MOD2-B&W code in the ELAP analysis for ANO-1 is limited to
the flow conditions prior to boiler-condenser cooling
initiation.
In progress.
This item to be addressed by
update to AQ
ANO-015 response
spreadsheet on the
ePortal when the
information is
available. 3.2.1.1.B Confirm that the use of CENTS in the ELAP analysis is limited to the flow conditions prior to
reflux boiling initiation.
This item is addressed by
updated AQ-015
response spreadsheet on the
ePortal. 3.2.1.2.A For ANO-1 confirm that the strategy is effective in keeping the RCS temperatures within the limits of NRC Confirmatory Action Attachment to 0CAN081402
Page 7 of 17 ISE Confirmatory Items Status the seal design temperatures, and supports the leakage rate (two gallons per minute (gpm)/seal)
used in the ELAP analysis. 3.2.1.2.B For ANO-1, confirm adequate justification for (including seal leakage testing data) the use of two
gpm/seal in the ELAP analysis.
NRC Confirmatory Action 3.2.1.3.A Verify the ELAP analysis assumption that decay heat is per ANS [American Nuclear Society] 5.1-
1979 + 2 sigma, or equivalent.
This item is addressed for ANO-
2 by updated AQ
ANO-019 response
spreadsheet on the
ePortal. For ANO In progress. This item
to be addressed by
update to AQ
ANO-019 response
spreadsheet on the
ePortal when the
information is
available. 3.2.1.4.A For ANO-1, confirm the revision to WCAP-17601 used and also confirm whether there are any
deviations taken from the assumptions presented in
NEI 12-06, Section 3.2.
This item is addressed by
updated AQ
ANO-075 response
spreadsheet on the
ePortal. 3.2.1.8.A Confirm the acceptability of the ANO-2 shutdown margin results after accounting for the delay in the
cooldown to eight hours following an ELAP.
This item is addressed by
updated AQ
ANO-078 response
spreadsheet on the
ePortal. 3.2.1.9.A Confirm the adequacy of the RCS injection strategy considering the analysis in licensee calculation
CN-SEE-II-13-2 as it relates to the delay in the
ANO-2 cooldown to eight hours following an ELAP.
This item is addressed by
updated AQ
ANO-051 and
ANO-077 responses
spreadsheet on the
ePortal. 3.2.1.9.B Confirm the final specific times for connection and use of the portable RRC pumps.
In progress. This item to be
addressed by
update to AQ Attachment to 0CAN081402
Page 8 of 17 ISE Confirmatory Items Status ANO-035 response spreadsheet on the
ePortal when the
information is
available. 3.2.3.A Confirm acceptable results of the ANO-2, containment ELAP analysis after it is completed.
This item is addressed by
updated AQ
ANO-032 response
spreadsheet on the
ePortal. 3.2.4.2.A Confirm acceptable results of the ANO-2, Main Control Room heat-up calculation after it is
performed.
This item is addressed by
updated AQ
ANO-061 response
spreadsheet on the
ePortal. 3.2.4.2.B Confirm the adequacy of ANO-2 battery room ventilation for extreme temperature protection when
the design development is completed.
This item is addressed by
updated AQ
ANO-125 response
spreadsheet on the
ePortal. 3.2.4.2.C Confirm the adequacy of calculations for extreme temperature protection regarding ANO-2, turbine-
driven EFW pump room and electrical equipment
rooms when the design development is completed.
This item is addressed by
updated AQ
ANO-060 response
spreadsheet on the
ePortal. 3.2.4.4.A Confirm that upgrades to the site's communications systems have been completed as planned.
NRC Confirmatory Action 3.2.4.7.A Confirm that a final strategy for use of the mobile boration unit is developed.
This item is addressed by
updated AQ
ANO-044 response
spreadsheet on the
ePortal. 3.2.4.10.A For ANO-2, confirm that an acceptable load shedding strategy is developed.
This item is addressed by
updated AQ
ANO-128 response
spreadsheet on the
ePortal. 3.2.4.10.B For ANO-2, confirm that an acceptable dc load This item is Attachment to 0CAN081402
Page 9 of 17 ISE Confirmatory Items Status profile is developed. addressed by updated AQ
ANO-070 response
spreadsheet on the
ePortal. 3.2.4.10.C For ANO-2, confirm that an acceptable basis for the minimum dc bus voltage is determined.
This item is addressed by
updated AQ
ANO-072 response
spreadsheet on the
ePortal. 3.3.2.A Confirm that acceptable strategies and their bases are developed and maintained in an overall program
document, as described in NEI 12-06, Section 11.8, items 1 and 3.
This item is addressed on
updated AQ
response spreadsheet on the
ePortal. 3.4.A Confirm that the licensee has fully addressed considerations (2) through (10) of NEI 12-06, Section 12.2, Minimum Capability of Off-Site
Resources, which requires each site to establish a
means to ensure the necessary resources will be
available from off-site.
This item is addressed on
updated AQ
response spreadsheet on the
ePortal.
Audit Questions Status Completion or Target Date ANO-001 Closed*
ANO-002 Updated response available on the ePortal (ISE Confirmatory Item 3.1.3.1.A)
ANO-003 Closed* ANO-004 Closed* ANO-006 Closed* ANO-010 Closed* ANO-011 Updated response available on the ePortal ANO-012 Closed* ANO-013 Closed*
ANO-014 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-015 Updated response available on the ePortal (ISE
Attachment to 0CAN081402
Page 10 of 17 Audit Questions Status Completion or Target Date Confirmatory Item 3.2.1.B)
In progress - This AQ response spreadsheet on the ePortal to be updated when information is available (ISE Confirmatory Item 3.2.1.1.A)
February 2015 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.1.B)
ANO-018 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-019 ANO In progress - This AQ response spreadsheet on the ePortal to be updated when
information is available (ISE Confirmatory Item
3.2.1.3.A)
February 2015 Updated response for ANO-2 available on the ePortal (ISE Confirmatory Item 3.2.1.3.A)
ANO-020 Closed*
ANO-021 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-022 Closed* ANO-023 Closed* ANO-024 Closed*
ANO-025 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-026 Closed* ANO-027 Closed* ANO-028 Closed* ANO-029 Closed* ANO-030 Closed*
ANO-032 Updated response available on the ePortal (ISE Confirmatory Item 3.2.3.A)
ANO-034 Closed*
ANO-035 Updated response available on the ePortal (ISE Open Item 3.2.1.D)
Updated response available on the ePortal(ISE Confirmatory Item 3.2.1.B)
In progress - This AQ response spreadsheet on the ePortal to be updated when information is available February 2015 Attachment to 0CAN081402
Page 11 of 17 Audit Questions Status Completion or Target Date (ISE Confirmatory Item 3.2.1.9.B)
ANO-041 ANO In progress - This AQ response spreadsheet on the ePortal to be updated when
information is available (ISE Open Item 3.2.1.8.B)
February 2015 ANO Updated response available on the ePortal (ISE Open Item 3.2.1.8.B)
ANO-044 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.7.A)
ANO-045 Updated response available on the ePortal ANO-046 Updated response available on the ePortal (ISE Open Item 3.2.1.D)
ANO-047 Updated response available on the ePortal ANO-049 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-051 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.9.A ANO-055 Closed* ANO-056 Closed* ANO-059 Updated response available on the ePortal ANO-060 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.2.C)
ANO-061 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.2.A)
ANO-062 Updated response available on the ePortal ANO-063 Updated response available on the ePortal ANO-064 Closed* ANO-066 Closed* ANO-067 Updated response available on the ePortal ANO-068 Closed* ANO-069 Updated response available on the ePortal ANO-070 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.10.B)
ANO-071 Updated response available on the ePortal Attachment to 0CAN081402
Page 12 of 17 Audit Questions Status Completion or Target Date ANO-072 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.10.C)
ANO-075 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.4.A)
ANO-076 Closed ANO-077 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.9.A)
ANO-078 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.8.A)
ANO-080 Closed* ANO-082 Closed* ANO-084 Closed* ANO-085 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.B)
ANO-086 Closed* ANO-088 Closed* ANO-089 Updated response available on the ePortal ANO-090 Updated response available on the ePortal ANO-091 Closed* ANO-092 Closed* ANO-094 Updated response available on the ePortal ANO-098 Updated response available on the ePortal ANO-100 Updated response available on the ePortal ANO-104 Closed*
ANO-106 Updated response available on the ePortal (ISE Open Item 3.2.1.D)
ANO-107 Updated response available on the ePortal (ISE Open Item 3.2.1.D)
Attachment to 0CAN081402
Page 13 of 17 Audit Questions Status Completion or Target Date ANO-108 Closed*
ANO-109 Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.A)
Updated response available on the ePortal (ISE Confirmatory Item 3.2.1.C)
ANO-110 Updated response available on the ePortal ANO-112 Closed* ANO-113 Updated response available on the ePortal ANO-115 In progress - This AQ response on the ePortal to be updated when information is available February 2015 ANO-116 Closed* ANO-117 Updated response available on the ePortal ANO-118 Closed* ANO-120 Closed* ANO-123 Updated response available on the ePortal ANO-125 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.2.B)
ANO-126 Updated response available on the ePortal ANO-127 Updated response available on the ePortal ANO-128 Updated response available on the ePortal (ISE Confirmatory Item 3.2.4.10.A)
ANO-129 Updated response available on the ePortal The following additional questions related to ANO Cross-Unit RCS Makeup Strategy were received in January 2014 during the audit process ANO-1 Updated response available on the ePortal ANO-2 Updated response available on the ePortal ANO-3 Closed* ANO-4 Updated response available on the ePortal ANO-5 Closed* ANO-6 Updated response available on the ePortal ANO-7 Updated response available on the ePortal ANO-8 Updated response available on the ePortal ANO-9 Updated response available on the ePortal Attachment to 0CAN081402
Page 14 of 17 Audit Questions Status Completion or Target Date ANO-10 Closed* ANO-11 Updated response available on the ePortal ANO-12 Closed* ANO-13 Closed* ANO-14 Updated response available on the ePortal ANO-15 Updated response available on the ePortal ANO-16 Updated response available on the ePortal
- Closed indicates that Entergy's response is complete. 7 Potential ISE Impacts The following items have been identified which have potential impact to the Interim Staff Evaluation (ISE) except for those identified in Section 6. 1. ISE/TER (Technical Evaluation Report) Section 3.1.2.2, Page 15, the TER states "ANO-2 FLEX RCS makeup pump requires primary and secondary connections
to the HPSI/charging piping and the refueling water tank (RWT) or borated water
storage tank (BWST)." The current strategy utilizes an ANO-2 charging pump as
the RCS injection source for both units. This strategy eliminates the need for
onsite portable RCS makeup pumps, and any connections to the HPSI/charging
piping. 2. ISE/TER Section 3.2.1, Page 29, the TER states, "-the Boric Acid Makeup Tanks (BAMTs), RWT, BWST or the new borated water tank will provide this
function." Currently, besides the option to install a new borated water tank, Entergy is also pursuing applying RG 1.76 Revision 1 to the borated water
storage tanks available at the site to qualify additional borated water through a
finite element analysis. 3. ISE/TER Section 3.2.1, Page 31, the TER states, "-and ANO-2 indicate cooldown is currently scheduled to begin at approximately eight hours from event initiation. The ANO-2 cooldown requires confirmation of existing analysis or
additional analysis during the ANO-2 detailed design to support the delay in the
cooldown to eight hours following the ELAP." The current strategy is to begin
cooldown at two hours following a reactor trip resulting from a BDBEE consistent
with the Westinghouse site-specific analysis. 4. ISE/TER Section 3.2.1, Page 31, item c, the TER states, "This analysis requires confirmation or additional analysis during the ANO-2 detailed design to support
the delay in the ANO-2 cooldown to two hours following an ELAP." The current
strategy is to begin cooldown at two hours following a reactor trip resulting from a
BDBEE consistent with the Westinghouse site-specific analysis.
Attachment to 0CAN081402
Page 15 of 17
- 5. ISE/TER Section 3.2.1, Page 31, item d, the TER states, "For ANO-2 the suction source will be either the ANO-1 BWST or ANO-2 RWT." The current strategy is
to use an ANO-2 charging pump. The suction source is provided from the ANO-
2 boric acid makeup tank (BAMT) and then the ANO-2 RWT. 6. ISE/TER Section 3.2.1, Page 35, the TER states, "1 RCS makeup pump (Unless it is decided to use charging pump for ANO-2 RCS makeup)." The current
strategy is to use an ANO-2 charging pump; therefore, the RCS makeup pump is
eliminated. 7. ISE/TER Section 3.2.1.1, Page 39, the TER states, "The current ANO-2 cooldown strategy, as detailed in the 6-month update, delays the ANO-2
cooldown until eight hours following an ELAP." The current strategy is to begin
cooldown at two hours following a reactor trip resulting from a BDBEE consistent
with the Westinghouse site-specific analysis. 8. ISE/TER Section 3.2.1.1, Page 40, the TER states, "Recommendation 2 - The ANO-2 strategy incorporates cooldown starting at eight hours-" The current
strategy is to begin cooldown at two hours following a reactor trip resulting from a
BDBEE consistent with the Westinghouse site-specific analysis. 9. ISE/TER Section 3.2.1.1, Page 40, the TER states, "Recommendation 6 - -to support the delay in the ANO-2 cooldown to eight hours following an ELAP." The
current strategy is to begin cooldown at two hours following a reactor trip
resulting from a BDBEE consistent with the Westinghouse site-specific analysis. 10. ISE/TER Section 3.2.1.8, Page 48, the TER states, "The analysis requires confirmation or additional analysis during the ANO-2 detailed design to support
the delay in the cooldown to eight hours following the ELAP." The current
strategy is to begin cooldown at two hours following a reactor trip resulting from a
BDBEE consistent with the Westinghouse site-specific analysis. 11. ISE/TER Section 3.2.1.8, Page 51, the TER states, "CN-SEE-II-13-2, Revision 1, requires confirmation or additional analysis during the ANO-2 detailed design to
support the delay in the ANO-2 cooldown to eight hours following an ELAP." The
current strategy is to begin cooldown at two hours following a reactor trip
resulting from a BDBEE consistent with the Westinghouse site-specific analysis (CN-SEE-II-13-2, Revision 1). 12. ISE/TER Section 3.2.1.8, Page 52, the TER states, "-the analysis performed in CN-SEE-II-13-2, Revision 1, requires confirmation or additional analysis during
the ANO-2 detailed design to support the delay in the ANO-2 cooldown to eight
hours following an ELAP." The current strategy is to begin cooldown at two
hours following a reactor trip resulting from a BDBEE consistent with the
Westinghouse site-specific analysis (CN-SEE-II-13-2, Revision 1). 13. ISE/TER Section 3.2.1.8, Page 52, the TER states, "An alternate strategy is under consideration to use the charging pump to make up to the ANO-2 RCS
after ANO-1 cooldown is complete." The use of the charging pumps to make up
to the ANO-2 RCS has become the primary strategy.
Attachment to 0CAN081402
Page 16 of 17
- 14. ISE/TER Section 3.2.4.7, Page 65, the TER states, "For ANO-2,-RCS inventory will be added as needed by utilizing a portable FLEX RCS makeup pump." The
current strategy utilizes the ANO-2 charging pumps as the means for RCS
inventory control for both ANO-1 and ANO-2. 15. ISE/TER Section 3.2.4.7, Page 66, the TER states, "For high wind BDBEEs, a new borated water storage tank, which-" Currently, besides the option to install
a new borated water tank, Entergy is also pursuing applying RG 1.76 Revision 1, Design Basis Tornado and Tornado Missiles for Nuclear Power Plants, to the
borated water storage tanks available at the site to qualify additional borated
water through a finite element analysis. 16. ISE/TER Section 3.2.4.7, Page 67, the TER states, "This 30-minute action to manually align valves in the Intake Structure will be validated during the
procedure development phase and staffing assessment." To qualify additional
QCST inventory beyond the 30 minutes to allow enough time for aligning this
new permanently installed crosstie between the fire water and the service water, Entergy is currently pursuing applying RG 1.76 Revision 1, Design Basis
Tornado and Tornado Missiles for Nuclear Power Plants, to the QCST to qualify
additional water through a finite element analysis. 17. ISE/TER Section 3.2.4.7, Page 68, the TER states, "A new borated water tank will be installed for coping with FLEX following high wind BDBEEs." Currently, besides the option to install a new borated water tank, Entergy is also pursuing
applying RG 1.76 Revision 1, Design Basis Tornado and Tornado Missiles for
Nuclear Power Plants, to the borated water storage tanks available at the site to
qualify additional borated water through a finite element analysis. 18. ISE/TER Section 3.2.4.7, Pages 68 and 69, the TER states, ".An alternate strategy is under consideration to use the charging pumps to make up to the
ANO-2 RCS after the AN0-1 cooldown is complete." The current strategy utilizes
the ANO-2 charging pumps as the means for RCS inventory control for both
ANO-1 and ANO-2.
8 References The following references support the updates to the OIP described in this enclosure.
- 1. OIP in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (Order Number
EA-12-049), dated February 28, 2013 (0CAN021302) (ML13063A151) 2. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs , dated March 12, 2012 (0CNA031206) (ML12056A045) 3. Entergy letter to NRC, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
Attachment to 0CAN081402
Page 17 of 17 (Order Number EA-12-049), dated August 28, 2013 (0CAN081302) (ML13241A414) 4. Entergy letter to NRC, Emergency Preparedness Commitment Changes Related to the March 12, 2012, Information Request, dated October 25, 2013 (0CAN101303) 5. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (BDBEEs) (NRC Order EA-12-049) Arkansas Nuclear One - Unit 1 , dated April 8, 2014 (1CAN041401) (ML14098A114)
- 6. NRC letter, Arkansas Nuclear One, Unit 1 -Relaxation of the Schedule Requirements for Order EA-12-049 "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis
External Events
", dated May 20, 2014 (ML14114A697) 7. NRC letter, Arkansas Nuclear One, Units 1 and 2 - Update Regarding Audit Activities Associated with Order EA-12-049 (Mitigation Strategies), dated May 28, 2014 (ML14140A514) 8. Entergy letter to NRC, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 27, 2014 (0CAN021405) (ML14059A229) 9. Westinghouse calculation CN-SEE-II-13-2, Revision 1, Arkansas Nuclear One Unit 2 Reactor Coolant System Inventory, Shutdown Margin, and Modes 5 and 6 Boric Acid Precipitation Control Analyses to Support the Diverse and Flexible
Coping Strategies (FLEX), dated February 19, 2013. 10. NRC letter, Arkansas Nuclear One, Units 1 and 2 - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0942 and MF0943), dated February 25, 2014