0CAN021406, Units 1 and 2, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051)

From kanterella
Jump to navigation Jump to search

Units 1 and 2, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051)
ML14059A230
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 02/27/2014
From: Jeremy G. Browning
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
0CAN021406, EA-12-051
Download: ML14059A230 (9)


Text

Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One 0CAN021406 February 27, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852

SUBJECT:

Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051)

Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6

REFERENCES:

1. NRC Order Number EA-12-051, Order to Modify Licenses with Regard to Reliable SFP Instrumentation, dated March 12, 2012 (0CNA031207) (ML12054A679)
2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable SFP Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)
3. Nuclear Energy Institute (NEI) 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, To Modify Licenses with Regard to Reliable SFP Instrumentation, Revision 1, dated August 2012 (ML12240A307)
4. Entergy letter to NRC, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation (Order Number EA-12-051), dated October 26, 2012 (0CAN101204)

(ML12305A274)

5. Entergy letter to NRC, Overall Integrated Plan (OIP) in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable SFP Instrumentation (Order Number EA-12-051), dated February 28, 2013 (0CAN021303)

(ML13063A015)

0CAN021406 Page 2 of 3

6. Entergy letter to NRC, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable SFP Instrumentation (Order Number EA-12-051), dated August 28, 2013 (0CAN081303)

Dear Sir or Madam:

On March 12, 2012, the NRC issued an order (Reference 1) to Entergy Operations, Inc.

(Entergy). Reference 1 was immediately effective and directs Entergy to install reliable SFP level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an OIP pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3). Reference 4 provided the initial status report regarding SFP instrumentation, and Reference 5 provided the OIP.

Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports. Reference 6 provided the first six-month status report. The purpose of this letter is to provide the second six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.

This letter contains no new regulatory commitments. Should you have any questions regarding this submittal, please contact Stephenie Pyle at 479.858.4704.

I declare under penalty of perjury that the foregoing is true and correct; executed on February 27, 2014.

Sincerely, Original signed by Jeremy G. Browning JGB/nbm

Attachment:

Arkansas Nuclear One Units 1 and 2 Second Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable SFP Instrumentation

0CAN021406 Page 3 of 3 cc: Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Alan Wang MS O-88B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Mr. Michael Orenak MS O-8G9A One White Flint North 11555 Rockville Pike Rockville, MD 20852

Attachment to 0CAN021406 Arkansas Nuclear One (ANO) Units 1 and 2 (ANO-1 and ANO-2) Second Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation

Attachment to 0CAN021406 Page 1 of 5 ANO-1 and ANO-2 Second Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable SFP Instrumentation

1. Introduction Entergy Operations, Inc. developed an overall integrated plan (OIP) provided via Reference 1 for ANO-1 and ANO-2, documenting the requirements to install reliable SFP instrumentation (SFPI), in response to Reference 2. This attachment provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2. Milestone Accomplishments The following milestone(s) have been completed since August 28, 2013, and are current as of January 31, 2014:
  • Although not part of the original milestone schedule, the NRC Interim Safety Evaluation (ISE) was received October 29, 2013 (Reference 3). The ISE included 17 requests for additional information (RAIs) for the NRC to complete its review. The NRC clarified during the November 26, 2013, public meeting that the ISE questions supersede any previous requests for information issued by the Staff concerning the SFP instrumentation (Reference 4). Therefore, the RAIs received June 26, 2013 (Reference 5) are considered superseded by the RAIs contained in the ISE received October 29, 2013.
3. Milestone Schedule Status The following provides an update to the milestone schedule to support the OIP. This section provides the activity status of each item and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.

Attachment to 0CAN021406 Page 2 of 5 Revised Target Target Completion Activity Milestone Completion Date Status Date ANO-1 Reliable SFPI Design Modification Package October 2013 In Progress March 2014 Developed/Issued ANO-1 Reliable SFPI 1R25 Early 2015 Pending Installed Refueling Outage ANO-2 Reliable SFPI Design Modification Package July 2014 In Progress September 2014 Developed/Issued ANO-2 Reliable SFPI 2R24 Fall 2015 Pending Installed Refueling Outage NRC RAIs (Received N/A July 25, 2013 Submitted June 26, 2013)

(Superceded)

ISE RAIs (Received September 30, 2014 In Progress October 29, 2013)

Target Completion Date is the last submitted date from either the overall integrated plan or previous six-month update.

4. Changes to Compliance Method There are no additional changes to the compliance method.
5. Need for Relief/Relaxation and Basis for the Relief/Relaxation Entergy expects to comply with the order implementation date and no relief/relaxation is required at this time.
6. Open Items from OIP and ISE As discussed in Section 2, Entergy has received an ISE for ANO that includes 17 RAIs.

Responses to the RAIs are due September 30, 2014, and are provided in Section 9 of this six-month status report. The following table provides a status of the RAIs.

Attachment to 0CAN021406 Page 3 of 5 ANO-1 ANO-2 RAI #

Response Status Response Status 1 In Progress In Progress 2 In Progress In Progress 3 In Progress In Progress 4 See Section 9 In Progress 5 In Progress In Progress 6 In Progress In Progress 7 In Progress In Progress 8 In Progress In Progress 9 In Progress In Progress 10 In Progress In Progress 11 See Section 9 In Progress 12 In Progress In Progress 13 In Progress In Progress 14 In Progress In Progress 15 In Progress In Progress 16 In Progress In Progress 17 In Progress In Progress

7. Potential ISE Impacts There are no potential impacts to the ISE identified at this time except for those identified in Section 6.

Attachment to 0CAN021406 Page 4 of 5

8. References
1. OIP in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable SFP Instrumentation (Order Number EA-12-051), dated February 28, 2013 (0CAN021303) (ML13063A015)
2. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable SFP Instrumentation, dated March 12, 2012 (0CNA031207) (ML12054A679)
3. Arkansas Nuclear One, Units 1 and 2 - ISE and RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable SFP Instrumentation (TAC NOs. MF0944 and MF0945), dated October 29, 2013 (0CNA101407) (ML13281A502)
4. November 26, 2013, Public Meeting Summary for the Discussion Between the NRC Staff and Industry Concerning Responses to ISEs for SFP Instrumentation, dated December 26, 2013 (ML13347B030)
5. RAI for the OIP in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation (Order Number EA-12-051), dated June 26, 2013 (0CNA061308) (ML13156A313)

Attachment to 0CAN021406 Page 5 of 5

9. Responses to two of the ISE RAIs for ANO-1:

RAI #4: Please provide the results of the evaluation performed to ensure that other hardware stored in the SFP cannot adversely interact with the SFP level instrumentation.

For ANO-1, the new instruments are being mounted in the east and west corners on north side of the SFP to take advantage of missile and debris protection inherent in the corners of the SFP and from SFP curbs and SFP bridge tracks/rails. Current plant procedures and practices would not result in a need to move spent fuel into these locations either during insertion or removal of spent fuel. Normal activities associated with the SFP racks would not be impacted by mounting the instruments in these locations. An exclusion zone of two square feet around the probe is the minimum clearance required to prevent any tools or devices from disturbing the function of the probe.

RAI #11: Please provide the NRC staff with the final configuration of the power supply source for each channel so that the staff may conclude that the two channels are independent from a power supply assignment perspective.

For ANO-1, the primary channel (Instrument Channel 3) 120 volt alternating current (VAC) power is being supplied from Panel RS3, which is a Class 1E inverter-backed panel supplied from 125V direct current (VDC) Bus D01. The backup channel (Instrument Channel 4) 120 VAC power is being supplied from Panel RS4, which is a Class 1E inverter-backed panel supplied from 125 VDC Bus D02.