IR 05000280/2015201 and 05000281/2015201, on 06/26/2015, Surry Power Station, Unit Nos. 1 and 2, NRC Security Inspection
ML15240A048
Person / Time
Site: Surry  Dominion icon.png
Issue date: 11/05/2015
From: Johnson R C
Division of Security Operations
To: Heacock D A
Virginia Electric & Power Co (VEPCO)
Byre E
References
IR 2015201
Download: ML15240A048 (3)


Text

November 5, 2015

Mr. David President & Chief Nuclear Officer Virginia Electric & Power Company Surry Power Station, Units 1 and 2 Innsbrook Technical Center 5000 Dominion Boulevard

Glen Allen, VA 23060 SUBJECT: SURRY POWER STATION, UNIT 1 AND 2 - NRC SECURITY INSPECTION REPORT 05000280/2015201 AND 05000281/2015201

Dear Mr. Heacock:

On June 26, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Surry Power Station, Unit 1 and 2. On August 6, 2015, the NRC inspectors discussed results of this inspection with Mr. Roy Simmons, Plant Manager and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection

report. The NRC inspectors documented two findings of very low security significance (Green) in this report. These findings were a violation of NRC requirements. The NRC is treating these violations as non-cited violations (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest these violations or the significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator Region II; Director, Office of Nuclear Security and Incident Response, and the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident inspector at the Surry Power Station, Unit 1 and 2.

If you disagree with a cross-cutting assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region II; the Director, Office of Nuclear Security, and Incident Response, and the NRC resident inspector at the Surry Power Station, Unit 1 and 2. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 "Public Inspections, Exemptions, Requests for Withholding,"

of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, the material enclosed herewith contains Safeguards Information as defined by 10 CFR 73.21 "Protection of Safeguards Information; Performance Requirements," and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Safeguards Information

is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, if Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from Public Disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1)

and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,

/RA D. Cardenas for/

Robert C. Johnson, Chief

Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response

Docket Nos. 50-280, 50-281 License Nos. DPR-32, DPR-37

Nonpublic Enclosure: Inspection Report 05000280/2015201 and 05000281/2015201 w/Attachment: Supplemental Information

cc w/enclosure: Terry Rawls, Manager Site Security

ML15240A048 OFFICE NSIR/DSO/SPEB NSIR/DSO NSIR/DSO/SPEB RII NSIR/DSO/SPEB NAME D. Hostetter J. Clark J. Berry B. Desai D. Cardenas for/C. JohnsonDATE 08/24/2015 9/10/2015 8/26/2015 9/9/2015 11/05/2015