Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements ML22287A1572022-12-0505 December 2022 Issuance of Amendment No. 171 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML22230C9242022-09-30030 September 2022 Issuance of Amendment No. 170 Revision of 120-Volt AC Vital Instrument Panel Requirements ML21008A0142021-02-25025 February 2021 Issuance of Amendment No. 168 Revise Technical Specification Table 3.3.4 to Change Time Delay Setpoints for Degraded Voltage Relays ML20293A1572020-12-28028 December 2020 Issuance of Amendment No. 167 Reactor Trip System Instrumentation Technical Specification Changes to Implement WCAP-14333 and WCAP-15376 ML20298A2532020-11-24024 November 2020 Issuance of Amendment No. 166 Revise Technical Specification 3/4.8.1, A.C. Sources Operating ML20318A0032020-11-24024 November 2020 Issuance of Revised Page for Renewed Facility Operating License Atomic Safety and Licensing Board Decisions LBP-20-09 and LBP-20-12 ML20070Q0712020-03-27027 March 2020 Issuance of Amendment No. 165 Emergency Core Cooling System Accumulator Technical Specification Changes ML19357A1952020-02-10010 February 2020 Unit No.1; & Turkey Point Nuclear Generating Unit Nos. 3 & 4 - Issuance of Amendments Nos. 265, 268, 164, 290, and 284 Revise Technical Specifications to Adopt TSTF-563 ML19326C4802019-12-0505 December 2019 Issuance of Amendment No. 163 One-Time Change to the Onsite Power Distribution Requirements ML19224A5632019-11-18018 November 2019 Issuance of Amendment No. 162 Revisions to Technical Specifications Associated with Movable Control Rods ML19148A7442019-07-31031 July 2019 Issuance of Amendment Nos. 161, 249, 200, 287, and 281 to Add Technical Specification Limiting Condition for Operation 3.0.6 ML19129A2432019-05-10010 May 2019 Correction to Amendment No. 160 Regarding Measurement and Assessment Frequency for Technical Specification 6.7.6 L, Control Room Envelope Habitability Program ML19065A2152019-03-29029 March 2019 Issuance of Amendment No. 160 Measurement and Assessment Frequency for Technical Specification 6.7.6.l, Control Room Envelope Habitability Program ML18355A4912019-03-12012 March 2019 Renewed Facility Operating License ML18204A2912019-03-11011 March 2019 Issuance of Amendment No. 159 Methodology for Analysis of Seismic Category I Structures with Concrete Affected by Alkali-Silica Reaction ML18247A5382018-11-27027 November 2018 Issuance of Amendment No. 158 Removing Requirement to Perform Certain Surveillance Requirements During Shutdown and Changes to Administrative Technical Specifications ML18199A6092018-08-0707 August 2018 Issuance of Amendment No. 157 Changes to the Technical Specifications Requirements for DC Batteries (CAC No. MG0046; EPID L-2017-LLA-0289) ML17102A8892017-04-13013 April 2017 Issuance of Amendment Licensing Basis Change for Service Water Cooling Tower ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) SBK-L-16082, Supplement to License Amendment Request 16-01 Request to Extend Containment Leakage Test Frequency2016-05-31031 May 2016 Supplement to License Amendment Request 16-01 Request to Extend Containment Leakage Test Frequency ML16068A1302016-02-27027 February 2016 License Amendment Request 15-02, Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6 Development of Emergency Action Levels for Non-Passive Reactors ML15096A2552015-11-0202 November 2015 Issuance of Amendment Regarding License Amendment Request 14-04, Revised Reactor Coolant System Pressure-Temperature Limits Applicable for 44 Effective Full Power Years ML15231A1442015-10-0606 October 2015 Issuance of Amendment No. 150 Regarding Note for Reactor Coolant System Surveillance Requirements ML15096A1312015-07-17017 July 2015 Issuance of Amendment Regarding Changes to Technical Specification 3.3.3.1, Radiation Monitoring for Plant Operations ML15118A6322015-05-18018 May 2015 Issuance of Amendment Regarding License Amendment Request Regarding New Fuel Valut ML15082A2332015-04-24024 April 2015 Issuance of Amendment Regarding Increase Voltage Limit for Diesel Generator Load Rejection Surveillance Requirement ML15058A7062015-04-22022 April 2015 Issuance of Amendment No. 146 Regarding the Cyber Security Plan Implementation Schedule ML15002A2512015-03-31031 March 2015 Unit No.1 - Issuance of Amendment Regarding License Amendment Request 14-06, Application Regarding the Removal of the Cold Leg Injection Permissive from Technical Specifications ML14345A2882015-02-0606 February 2015 Issuance of Amendment Regarding Technical Specifications Task Force Traveler-523, Generic Letter 2008-01, Managing Gas Accumulation Using the Consolidated Line Item Improvement Process ML14363A2752015-02-0404 February 2015 Non-Proprietary SE for Issuance of Amendment Regarding License Amendment Request Regarding Fixed Incore Detector System Analysis ML14184A7952014-09-0303 September 2014 Issuance of Amendment Regarding License Amendment Request Regarding Fuel Storage Changes ML13212A0692014-07-24024 July 2014 Issuance of Amendment Regarding the Risk-Informed Justifications for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program ML14029A4452014-03-0606 March 2014 Issuance of Amendment Regarding License Amendment Request 12-04, Application Regarding Cold Leg Injection Permissive ML13213A1432014-03-0505 March 2014 Issuance of Amendment Regarding the Use of Optimized Zirlo Fuel Rod Cladding Material ML13107A0162013-10-25025 October 2013 Issuance of Amendment Regarding the License Amendment Request 13-02, Application to Revise Technical Specifications to Adopt TSTSF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection.. ML13204A3792013-07-26026 July 2013 Correction to Issuance of Amendment 137 Regarding the Administrative Changes and Corrections to the Technical Specifications ML13074A7602013-06-17017 June 2013 Issuance of Amendment Regarding the Administrative Changes and Corrections to the Technical Specifications ML13114A3172013-04-25025 April 2013 Correction to Issuance of Amendment 136 Addition of Action Statement to Limiting Condition for Operation 3.6.5.1, Containment Enclosure Emergency Air Cleanup System ML1130000632013-04-23023 April 2013 Issuance of Amendment Addition of Action Statement to Limiting Condition for Operation 3.6.5.1, Containment Enclosure Emergency Air Cleanup System ML1208205102013-04-15015 April 2013 Issuance of Amendment Revision to the Applicability of the Reactor Coolant System Pressure-Temperature Limits and the Cold Overpressure Protection Setpoints ML13028A1462013-04-0404 April 2013 Issuance of Amendment Regarding the Extension of the Inspection Interval for the Reactor Coolant Pump Flywheels Using the Consolidated Line Item Improvement Process ML12332A3012013-01-31031 January 2013 Issuance of Amendment Emergency Plan ML12237A0942012-11-0202 November 2012 Issuance of Amendment Cyber Security Program ML12178A5372012-09-10010 September 2012 Issuance of Amendment Permanent Application of Steam Generator Tube Alternate Repair Criteria, H* ML1200302712012-02-23023 February 2012 Issuance of Amendment Regarding the Application to Revise the Technical Specifications for Reactor Coolant System Leakage Detection Instrumentation ML1120700482011-08-23023 August 2011 Issuance of Amendment Approval of Cyber Security Plan ML1112503882011-08-22022 August 2011 Issuance of Amendment 126 Remove Technical Specification 3.4.10, Structural Integrity ML1108401882011-04-29029 April 2011 Issuance of Amendment Relocation of Technical Specification Requirements Related to Electrical Equipment Protective Devices ML1021702782010-09-0202 September 2010 Issuance of Amendment Operations Manager Qualification Requirements 2023-12-22
[Table view] Category:Letter
MONTHYEARML24009A1152024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-180, Submittal of Changes to the Technical Specification Bases2023-12-13013 December 2023 Submittal of Changes to the Technical Specification Bases L-2023-177, Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-160, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20234032023-11-0707 November 2023 Security Baseline Inspection Report 05000443/2023403 and Independent Spent Fuel Storage Installation 07200063/2023401 IR 05000443/20230032023-11-0606 November 2023 Integrated Inspection Report 05000443/2023003 IR 05000443/20230102023-10-19019 October 2023 Triennial Fire Protection Inspection Report 05000443/2023010 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A0522023-10-0202 October 2023 Requalification Program Inspection IR 05000443/20234012023-09-0808 September 2023 Cybersecurity Inspection Report 05000443/2023401 (Cover Letter Only) IR 05000443/20234202023-09-0505 September 2023 Security Baseline Inspection Report 05000443/2023420 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000443/20233022023-08-16016 August 2023 Operator Licensing Retake Examination Report 05000443/2023302 IR 05000443/20230022023-08-0808 August 2023 Integrated Inspection Report 05000443/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-103, Inservice Inspection Examination Report2023-08-0303 August 2023 Inservice Inspection Examination Report ML23192A0782023-07-11011 July 2023 Operator Licensing Retake Examination Approval L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 ML23157A0722023-06-0606 June 2023 Notification of Conduct of a Fire Protection Team Inspection L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000443/20233012023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000443/2023301 L-2023-064, License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-05-11011 May 2023 License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves IR 05000443/20230012023-05-11011 May 2023 Integrated Inspection Report 05000443/2023001 ML23129A0312023-05-0909 May 2023 Reactor Operator Retake License Examination ML23117A3652023-05-0404 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from PTL and Low Temperature Over Pressure Protection Curves SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report L-2023-053, Core Operating Limits Report for Cycle 232023-04-0505 April 2023 Core Operating Limits Report for Cycle 23 ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code L-2023-012, License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-03-15015 March 2023 License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-023, Revised Steam Generator Tube Inspection Report2023-03-0303 March 2023 Revised Steam Generator Tube Inspection Report ML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter 2024-01-29
[Table view] Category:Safety Evaluation
MONTHYEARML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code ML22287A1572022-12-0505 December 2022 Issuance of Amendment No. 171 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML22262A3142022-10-0404 October 2022 Relief Requests 3IR-18 and 3IR-19, Relief from the Requirements of the ASME Code ML22230C9242022-09-30030 September 2022 Issuance of Amendment No. 170 Revision of 120-Volt AC Vital Instrument Panel Requirements ML21008A0142021-02-25025 February 2021 Issuance of Amendment No. 168 Revise Technical Specification Table 3.3.4 to Change Time Delay Setpoints for Degraded Voltage Relays ML20293A1572020-12-28028 December 2020 Issuance of Amendment No. 167 Reactor Trip System Instrumentation Technical Specification Changes to Implement WCAP-14333 and WCAP-15376 ML20298A2532020-11-24024 November 2020 Issuance of Amendment No. 166 Revise Technical Specification 3/4.8.1, A.C. Sources Operating ML20070Q0712020-03-27027 March 2020 Issuance of Amendment No. 165 Emergency Core Cooling System Accumulator Technical Specification Changes ML20076D2812020-03-17017 March 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML20073E4342020-03-17017 March 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML19357A1952020-02-10010 February 2020 Unit No.1; & Turkey Point Nuclear Generating Unit Nos. 3 & 4 - Issuance of Amendments Nos. 265, 268, 164, 290, and 284 Revise Technical Specifications to Adopt TSTF-563 ML20015A1232020-02-0606 February 2020 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML19340A1282019-12-13013 December 2019 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML19326C4802019-12-0505 December 2019 Issuance of Amendment No. 163 One-Time Change to the Onsite Power Distribution Requirements ML19224A5632019-11-18018 November 2019 Issuance of Amendment No. 162 Revisions to Technical Specifications Associated with Movable Control Rods ML19249B1012019-09-30030 September 2019 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code; Relief Request RA-19-001 ML19148A7442019-07-31031 July 2019 Issuance of Amendment Nos. 161, 249, 200, 287, and 281 to Add Technical Specification Limiting Condition for Operation 3.0.6 ML19065A2152019-03-29029 March 2019 Issuance of Amendment No. 160 Measurement and Assessment Frequency for Technical Specification 6.7.6.l, Control Room Envelope Habitability Program ML18204A2912019-03-11011 March 2019 Issuance of Amendment No. 159 Methodology for Analysis of Seismic Category I Structures with Concrete Affected by Alkali-Silica Reaction ML18247A5382018-11-27027 November 2018 Issuance of Amendment No. 158 Removing Requirement to Perform Certain Surveillance Requirements During Shutdown and Changes to Administrative Technical Specifications ML18199A6092018-08-0707 August 2018 Issuance of Amendment No. 157 Changes to the Technical Specifications Requirements for DC Batteries (CAC No. MG0046; EPID L-2017-LLA-0289) ML18106B1212018-04-25025 April 2018 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML17102A8892017-04-13013 April 2017 Issuance of Amendment Licensing Basis Change for Service Water Cooling Tower ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) ML17080A0382017-03-27027 March 2017 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML17046A4432017-03-15015 March 2017 Issuance of Amendment Extension of Containment Leakage Rate Test Frequency ML16330A1182016-12-15015 December 2016 NextEra Fleet - Safety Evaluation for Proposed Alternative to the American Society of Mechanical Engineers Operation and Maintenance Code by Adoption of Approved Code Case OMN-20, Inservice Test Frequency (CAC Nos. MF8195 Through MF8201) ML16321A4182016-12-0101 December 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 (CAC Nos. MF0836 and MF0837) ML15096A2552015-11-0202 November 2015 Issuance of Amendment Regarding License Amendment Request 14-04, Revised Reactor Coolant System Pressure-Temperature Limits Applicable for 44 Effective Full Power Years ML15231A1442015-10-0606 October 2015 Issuance of Amendment No. 150 Regarding Note for Reactor Coolant System Surveillance Requirements ML15096A1432015-07-28028 July 2015 Exemption from Specific Requirements of 10 CFR Part 50, Appendix G, and 10 CFR 50.60 ML15205A3332015-07-28028 July 2015 Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Request for Exemption from Table 1 of 10 CFR Part 50, Appendix G NextEra Energy Seabrook, LLC Seabrook Station, Unit 1 Docket No. 50-443 ML15096A1312015-07-17017 July 2015 Issuance of Amendment Regarding Changes to Technical Specification 3.3.3.1, Radiation Monitoring for Plant Operations ML15118A6322015-05-18018 May 2015 Issuance of Amendment Regarding License Amendment Request Regarding New Fuel Valut ML15082A2332015-04-24024 April 2015 Issuance of Amendment Regarding Increase Voltage Limit for Diesel Generator Load Rejection Surveillance Requirement ML15058A7062015-04-22022 April 2015 Issuance of Amendment No. 146 Regarding the Cyber Security Plan Implementation Schedule ML15002A2512015-03-31031 March 2015 Unit No.1 - Issuance of Amendment Regarding License Amendment Request 14-06, Application Regarding the Removal of the Cold Leg Injection Permissive from Technical Specifications ML14345A2882015-02-0606 February 2015 Issuance of Amendment Regarding Technical Specifications Task Force Traveler-523, Generic Letter 2008-01, Managing Gas Accumulation Using the Consolidated Line Item Improvement Process ML14363A2752015-02-0404 February 2015 Non-Proprietary SE for Issuance of Amendment Regarding License Amendment Request Regarding Fixed Incore Detector System Analysis ML14184A7952014-09-0303 September 2014 Issuance of Amendment Regarding License Amendment Request Regarding Fuel Storage Changes ML13212A0692014-07-24024 July 2014 Issuance of Amendment Regarding the Risk-Informed Justifications for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program ML14071A4102014-04-10010 April 2014 Request for Relief RA-14-001 from American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection Piping (TAC No. Mfxxxx) ML14029A4452014-03-0606 March 2014 Issuance of Amendment Regarding License Amendment Request 12-04, Application Regarding Cold Leg Injection Permissive ML13213A1432014-03-0505 March 2014 Issuance of Amendment Regarding the Use of Optimized Zirlo Fuel Rod Cladding Material ML13247A7772014-02-0909 February 2014 Request for Relief to Use an Alternative to the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML13107A0162013-10-25025 October 2013 Issuance of Amendment Regarding the License Amendment Request 13-02, Application to Revise Technical Specifications to Adopt TSTSF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection.. ML13074A7602013-06-17017 June 2013 Issuance of Amendment Regarding the Administrative Changes and Corrections to the Technical Specifications ML13050A1382013-06-13013 June 2013 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML1130000632013-04-23023 April 2013 Issuance of Amendment Addition of Action Statement to Limiting Condition for Operation 3.6.5.1, Containment Enclosure Emergency Air Cleanup System 2023-03-23
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C.
January 31, 2013 Mr. Kevin Walsh, Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 SEABROOK STATION, UNIT NO.1-ISSUANCE OF AMENDMENT RE: EMERGENCY PLAN (TAC NO. NlE8548)
Dear Mr. Walsh:
The Commission has issued the enclosed Amendment No. 133 to Facility Operating License No. NPF-86 for the Seabrook Station, Unit No. 1 (Seabrook).
This amendment consists of changes to the facility operating license in response to your application dated April 30, 2012. The amendment revises the emergency action level (EAL) initiating conditions involving a loss of safety system annunciation or indication in the control room. The current emergency classification scheme includes EALs that could place the plant in an emergency classification based solely on a loss of radiation monitoring indications.
The proposed changes revise the EALs to include radiation monitoring indications within the aggregate of safety system indications that are to be considered when evaluating a loss of safety system indications rather than as separate and independent EALs. A copy of our safety evaluation is also enclosed.
Notice of Issuance will be included in the Commission's biweekly Federal Register notice. G. Lamb, Senior Project Manager t Licensing Branch 1-2 D ision of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
- 1. Amendment No. 133 to NPF-86 2. Safety Evaluation cc: Listserv UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 NEXTERA ENERGY SEABROOK, LLC, ET AL.* DOCKET NO. 50-443 SEABROOK STATION, UNIT NO.1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 133 License No. NPF-86 The U.S. Nuclear Regulatory Commission (the Commission) has found that: The application for amendment filed by NextEra Energy Seabrook, LLC, et al., (the licensee) dated April 30, 2012, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in Title 10 of the Code of Federal Regulations (10 CFR) Chapter I; The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
"'NextEra Energy Seabrook, LLC is authorized to act as agent for the: Hudson Light & Power Department, Massachusetts Municipal Wholesale Electric Company, and Taunton Municipal Light Plant and has exclusive responsibility and control over the physical construction, operation and maintenance of the facility.
-Accordingly, by Amendment No. 133, Facility Operating License No. NPF-86 is hereby amended to authorize revision to the Seabrook Station Emergency Plan as set forth in NextEra Energy Seabrook, LLC's application dated April 30, 2012, and evaluated in the NRC staff's safety evaluation dated January 31, 2013. The license amendment is effective as of its date of issuance and shall be implemented within 90 days. s, Director uclear Reactor Regulation
Attachment:
Changes to the License Date of Issuance:
January 31,2013 ATTACHMENT TO LICENSE AMENDMENT NO. 133 FACILITY OPERATING LICENSE NO. NPF-86 DOCKET NO. 50-443 Replace the following page of Facility Operating License No. NPF-86 with the attached revised page. The revised page is identified by amendment number and contains a marginal line indicating the area of change. Remove 3 3
-NextEra Energy Seabrook, LLC, pursuant to the Act and 10 CFR 30, 40, and 70, to receive, possess, and use at any time any byproduct, source, and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; NextEra Energy Seabrook, LLC, pursuant to the Act and 10 CFR 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; NextEra Energy Seabrook, LLC, pursuant to the Act and 10 CFR 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility authorized herein; and DELETED This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; is subject to the additional conditions specified or incorporated below: Maximum Power Level NextEra Energy Seabrook, LLC, is authorized to operate the facility at reactor core power levels not in excess of 3648 megawatts thermal (100% of rated power). Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 133, and the Environmental Protection Plan contained in Appendix B are incorporated into the Facility License No. NPF-86. NextEra Energy Seabrook, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan. License Transfer to FPL Energy Seabrook, LLC** On the closing date(s) Of the transfer of any ownership interests in Seabrook Station covered by the Order approving the transfer, FPL Energy Seabrook, LLC**, shall obtain from each respective transferring owner all of the accumulated decommissioning trust funds for the facility, and ensure the deposit of such funds and additional funds, if necessary, into a decommissioning trust or trusts for Seabrook Station established by FPL Energy Seabrook, LLC**, such that the amount of such funds deposited meets or exceeds the amount required under 10 CFR 50.75 with respect to the interest in Seabrook Station FPL Energy Seabrook, LLC**, acquires on such dates(s).
- On April 16, 2009, the name "FPL Energy Seabrook, LLC" was changed to "NextEra Energy Seabrook, LLC". AMENDMENT NO. 133 UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 133 TO FACILITY OPERATING LICENSE NO. NPF-86 SEABROOK STATION, UNIT NO.1 DOCKET NO. 50-443
1.0 INTRODUCTION
In a letter dated April 30, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12124A341), NextEra Energy Seabrook, LLC (NextEra) proposed changes associated with the emergency action level (EAL) initiating conditions involving a loss of safety system annunciation or indication in the control room. The current emergency classification scheme includes EALs that could place the plant in an emergency classification based solely on a loss of radiation monitoring indications.
However, a loss of radiation monitoring indications by itself may not represent degradation in the level of plant safety. Therefore, the proposed changes revise the EALs to include radiation monitoring indications within the aggregate of safety system indications that are to be considered when evaluating a loss of safety system indications rather than as separate and independent EALs.
2.0 REGULATORY EVALUATION
This safety evaluation addresses the impact of the proposed changes on the Seabrook Station, Unit 1 (Seabrook)
EALs. The regulatory requirements and guidance on which the U.S. Nuclear Regulatory Commission (NRC) staff based its acceptance are as follows: 2.1 Regulations Title 10 of the Code of Federal Regulations (10 CFR), Section 50.47, "Emergency plans," sets forth emergency plan requirements for nuclear power plant facilities.
The regulations in 1 0 CFR 50.47(a)(1
)(i) state, in part, that: ... no initial operating license for a nuclear power reactor will be issued unless a finding is made by the NRC that there is reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency.
Section 50.47(b) establishes the standards that the onsite and offsite emergency response plans must meet for NRC staff to make a positive finding that there is reasonable assurance that the licensee can and will take adequate protective measures in the event of a radiological emergency.
Planning Standard (4) of this section requires that a licensee's emergency response plan contain: U[a] standard emergency classification and action level scheme, the
-bases of which include facility system and effluent parameters, is in use by the nuclear facility licensee, and State and local response plans call for reliance on information provided by facility licensees for determinations of minimum initial offsite response measures." Section 50.47(b)(4) to 10 CFR specifies a standard emergency classification and action level scheme, and as such, the NRC staff will ensure that implementation methods are relatively consistent throughout the industry for a given reactor and containment design, while simultaneously providing an opportunity for a licensee to modify their EAL scheme, as necessary, to address plant-specific design considerations or preferences.
Section 50.54(q)(4) states, in part, that: The changes to a licensee's emergency plan that reduce the effectiveness of the plan as defined in paragraph (q)(1 )(iv) of this section may not be implemented without prior approval by the NRC. The proposed change was submitted to the NRC for a technical and regulatory review prior to implementation by the licensee, as required under 10 CFR 50.54(q).
2.2 Guidance
Revision 4 to Regulatory Guide (RG) 1.101, "Emergency Planning and Preparedness for Nuclear Power Reactors," issued in July 2003 (ADAMS Accession No. ML032020276), endorses the guidance contained in the Nuclear Energy Institute (NEI) document NEI 99-01, "Methodology for Development of Emergency Action Levels," Revision 4, January 2003 (ADAMS Accession No. ML041470143).
The guidance is acceptable to the NRC staff as an alternative method to the below listed guidance for developing EALs, as required in Section IV of Appendix E to 10 CFR Part 50 and 10 CFR 50.47(b)(4): Appendix 1 to NUREG-0654/FEMA-REP-1, "Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants" (ADAMS Accession No. ML040420012), and Nuclear Utilities Management Council (NUMARC) document, entitled NESP-007, "Methodology for Development of Emergency Action Levels" (ADAMS Accession No. ML041120174).
Regulatory Issue Summary (RIS) 2003-18, with Supplements 1 &2, "Use of NEI 99-01, Methodology for Development of Emergency Action Levels," (ADAMS Accession Nos. ML032580518, ML041550395, and ML051450482), provides guidance for developing or changing a standard emergency classification and action level scheme. In addition, this RIS provides recommendations to assist licensees, consistent with Section IV.B to Appendix E of Part 50, in determining whether to seek prior NRC approval of deviations from the guidance.
NEI 99-01, "Methodology for Development of Emergency Action Levels" Revision 5 (ADAMS Accession No. ML080450149), has been determined to be acceptable to the NRC via letter dated February 22, 2008 (ADAMS Accession No. ML080430535).
-3.0 TECHNICAL EVALUATION
3.1 Background
The current NRC-approved emergency classification scheme for Seabrook is based on NEI 99-01 (Revision
- 4) and was approved by letter dated December 31, 2007 (ADAMS Accession No. ML073520318).
As part of the application, the licensee evaluated the proposed changes using the latest approved guidance in NEI 99-01 (Revision 5), which did not make any significant changes to the specific EALs affected by these proposed changes. This proposed change revises the EALs associated with Category'S'
-System Malfunction Initiating Conditions SU3, SA4, and SS6. Initiating Conditions SU3 and SA4 address an unplanned loss of safety system annunciation or indication in the control room, and SS6 involves the inability to monitor a significant event in progress.
The licensee provides a table that displays the EALs in NEI 99-01 (Revision
- 5) for these Initiating Conditions, the current Seabrook EALs and the proposed EALs. 3.2 Evaluation Initiating Conditions SU3, SA4, and SS6 in NEI 99-01 are primarily concerned with a loss of the control room staff's ability to monitor changing plant conditions.
Each of these initiating conditions contains an EAL that addresses a loss of greater than approximately 75-percent of the site-specific control room safety system indication for 15 minutes or longer. The licensee provides that their site-specific implementation for this generic EAL established two separate EALs with an "or" logic for a loss of main control board indications and for loss of radiation monitor indications.
As a consequence, when the control room staff is evaluating SU3, the loss of greater than 75-percent of the radiation monitor indications in the control room would place the plant in an unusual event. Similarly, a loss of greater than 75-percent of the radiation monitor indications in the control room would meet the threshold for satisfying one attribute in the EAL logic for placing the plant in an emergency classification under initiating conditions SA4 and SS6. The declaration of an emergency, based only on a loss of radiation monitor indications, is overly restrictive and inconsistent with the guidance in NEI 99-01. A loss of radiation monitor indications, by itself, does not meet the threshold for placing the plant in an emergency classification level, since this condition does not indicate potential degradation in plant safety that presents a threat to public health and safety or to plant workers. NEI 99-01 does not provide a separate EAL for loss of radiation monitor indications; rather, the EAL specifies a loss of control room safety system indications.
Radiation monitors are only one type of indicator included in the aggregate of the control room safety system. 3.3 Conclusion The NRC staff performed a technical and regulatory review of the proposed changes to the Initiating Conditions SU3, SA4, and SS6. The NRC staff finds that the declaration of an emergency based only on a loss of radiation monitor indications is overly restrictive and is inconsistent with the guidance provided in NEI 99-01.
Therefore, the NRC staff has determined, based on the considerations discussed in the Evaluation Section above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner; (2) such activities will be conducted in compliance with the Commission's regulations; and (3) the proposed emergency plan change will not be inimical to the common defense and security or to the health and safety of the public. The NRC staff has determined that incorporation of the proposed change continues to meet the standards of Section 50.47(b) and the requirements of Appendix E to 10 CFR Part 50, and continues to provide reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the New Hampshire and Massachusetts State officials were notified of the proposed issuance of the amendment.
The State of New Hampshire official had no comments.
The State of Massachusetts official provided two comments.
Comment 1: Presently, a UE [Unusual Event] is declared if there is an unplanned loss of 75% or more of the main control board indicators for> 15 minutes. They want to change it to only safety related indicators and radiation monitor indications on CP-180 A&B. They have decreased their safety margin by limiting the amountof indicators that could drive a classification and also reduce the calls to the State on any potential problems.
Comment 2: At the Alert, there is the same criteria as the bullet above but now they have decreased the number of radiation monitor indications to only the indicators on CP-180 A&B. Again, they are decreasing their actions for declaring an Alert and notifying the State of any issues at the plant. NRC Response to Comments 1 and 2: The EAL scheme development guidance (NEI 99-01, Revision 5) requires the development of an EAL set that results in an EAL declaration when>75% of available Control Room system annunciation and/or indication is unavailable, with escalation criteria if a significant transient is in process and compensatory indications are also unavailable.
The intent of this EAL is to recognize the impact that a loss of safety-related annunciation/indication has on the Control Room operators.
The loss of non-safety related annunciation/indication is not considered a precursor to a radiological event, and thus, does not have an EAL associated with it. If an issue arises that compromises the ability of the site to shutdown and/or cool-down, other EALs will serve to bound this condition.
-5 Please note the distinction between EALs and reportable events. EALs are intended to drive implementation of a site's radiological emergency response plan, and depending on the classification level (unusual event, alert, site area emergency, or general emergency) require specific action(s) at the site, and State/Counties, in order to mitigate the consequences of a radiological event. Reportable events (please refer to NUREG-1022) are intended to be conditions where notification to the State/Counties, and/or the NRC, is prudent given the significance of the concern. These concerns may not be considered to be precursors to a radiological emergency and may, therefore, not require an EAL. 5.0 ENVIRONMENTAL CONSIDERATION The amendment changes the requirements with respect to use of a facility component located within the restricted area, as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts and no significant change in the types of any effluents that may be released offsite and that there is no significant increase in individual or cumulative occupational radiation exposure.
The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (77 FR 31661). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner; (2) there is reasonable assurance that such activities will be conducted in compliance with the Commission's regulations; and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public. Principal Contributor:
Michael Norris Date: January 31, 2013 January 31,2013 Mr. Kevin Walsh, Site Vice President c/o Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 SEABROOK STATION, UNIT NO. 1 -ISSUANCE OF AMENDMENT RE: EMERGENCY PLAN (TAC NO. ME8548)
Dear Mr. Walsh:
The Commission has issued the enclosed Amendment No. 133 to Facility Operating License No. NPF-86 for the Seabrook Station, Unit No.1 (Seabrook).
This amendment consists of changes to the facility operating license in response to your application dated April 30, 2012. The amendment revises the emergency action level (EAL) initiating conditions involving a loss of safety system annunciation or indication in the control room. The current emergency classification scheme includes EALs that could place the plant in an emergency classification based solely on a loss of radiation monitoring indications.
The proposed changes revise the EALs to include radiation monitoring indications within the aggregate of safety system indications that are to be considered when evaluating a loss of safety system indications rather than as separate and independent EALs. A copy of our safety evaluation is also enclosed.
Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Sincerely, IRA! John G. Lamb, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
- 1. Amendment No. 133 to NPF-86 2. Safety Evaluation cc: Listserv DISTRIBUTION:
PUBLIC LPLI-2 RtF RidsAcrsAcnw
_MaiICTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl1-2 Resource RidsRgn1 MailCenter Resource RidsNsirDspCsirb Resource RidsNrrPMSeabrook Resource RidsNrrLAABaxter Resource RidsOgcRp Resource ADAMS Accession No.: ML 12332A301 "via memorandum
- via email I i OFFICE LPL 1-2/PM LPL 1-2/LA NSIR/BC OGC -NLO LPL 1-21BC DORUDD DORUD NAME JLamb ABaxterwl comments" JAnderson*
MSmith MKhanna LLund MEvans DATE 12/06/12 12/03/12 11/26/12 12/11/12 12/17/12 01/16/13 01/18/13 OFFICE NRR/D LPL1-2/PM NAME ELeeds JLamb DATE 01127/13 01/31/13 Official Record Copy