MONTHYEARML17283A0412017-08-24024 August 2017 Enclosure 3 - Licensees Presentation-Seabrook Station, License Amendment Request 16-03 ASR Structural Evaluation Methodology Project stage: Request SBK-L-17155, 8 - Response to Request for Additional Information for the Review of the License Renewal Application - Building Deformation Analyses Related to Concrete Alkali-Silica Reaction2017-10-0303 October 2017 8 - Response to Request for Additional Information for the Review of the License Renewal Application - Building Deformation Analyses Related to Concrete Alkali-Silica Reaction Project stage: Response to RAI ML17283A0402017-10-10010 October 2017 Enclosure 2 - NRCs Presentation Slides-Seabrook Station, License Amendment Request, Stage 3 Methodology Project stage: Other ML17261B2172017-10-11011 October 2017 Request for Additional Information Regarding License Amendment Request Related to Alkali-Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: RAI ML17278A7482017-10-13013 October 2017 Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Meeting ML17310A1142017-10-17017 October 2017 La - (External_Sender) Name Correction: Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Meeting SBK-L-17180, 8, Revised Alkali-Silica Reaction Aging Management Program2017-11-0303 November 2017 8, Revised Alkali-Silica Reaction Aging Management Program Project stage: Request ML17310B5402017-11-0303 November 2017 La - (External_Sender) SBK-L-17180 Supplement 58 - Revised Alkali-Silica Reaction Aging Management Program Project stage: Request ML17341A0622017-11-17017 November 2017 NextEra Energy Seabrook Presentation Slides - Seabrook Station ASR Methodology LAR: Structural Deformation - LAR 16-03, Methodology and Responses to Rais D2-D8 - for November 17, 2017, Public Meeting Project stage: Response to RAI SBK-L-17204, Response to Request for Additional Information Regarding License Amendment Request Related to Alkali-Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007)2017-12-11011 December 2017 Response to Request for Additional Information Regarding License Amendment Request Related to Alkali-Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Response to RAI ML17340A1862017-12-14014 December 2017 Summary of November 17, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction - Requests for Additional Information (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: RAI ML18058A1142018-02-27027 February 2018 NRR E-mail Capture - Site Visit Plan for the Week of March 19th Project stage: Other ML18113A5292018-04-18018 April 2018 NRR E-mail Capture - Draft - Request for Additional Information Regarding ASR Amendment Request Project stage: Draft RAI ML18121A3992018-05-0101 May 2018 NRR E-mail Capture - Request for Additional Information Regarding ASR Amendment Request Project stage: RAI SBK-L-18072, Revised Structures Monitoring Aging Management Program2018-05-18018 May 2018 Revised Structures Monitoring Aging Management Program Project stage: Request ML18135A0462018-05-21021 May 2018 Site Visit Report Regarding Regulatory Audit for License Amendment Request Alkali Silica Reaction License Amendment Request and License Renewal Alkali-Silica Reaction Aging Management Program Review (CAC No. MF8260; EPID L-2016-LLA-007) Project stage: Other SBK-L-18074, Response to Request for Additional Information Regarding License Amendment Request 16-032018-06-0707 June 2018 Response to Request for Additional Information Regarding License Amendment Request 16-03 Project stage: Response to RAI ML17088A6742018-08-17017 August 2018 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18226A2052018-09-28028 September 2018 Redacted, Submission of Alkali-Silica Reaction License Amendment Request Draft Safety Evaluation to Support Advisory Committee on Reactor Safeguards Review of Seabrook License Renewal (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Draft Approval ML18271A0692018-09-28028 September 2018 Attachment 2 NRC Staff Draft Safety Evaluation (Non-Proprietary) Project stage: Request ML19050A4602019-02-13013 February 2019 Handouts from the Public at the February 13, 2019, Seabrook ASR Public Meeting Project stage: Meeting ML19056A5862019-02-25025 February 2019 NextEras Answer Opposing C-10 Emergency Petition Project stage: Request ML19058A2162019-03-0404 March 2019 Update to Proposed Issuance of a Final No Significant Hazards Consideration Determination and License Amendment Regarding Which a Hearing Has Been Requested (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Other ML18204A2912019-03-11011 March 2019 Issuance of Amendment No. 159 Methodology for Analysis of Seismic Category I Structures with Concrete Affected by Alkali-Silica Reaction Project stage: Approval ML19015A1832019-03-11011 March 2019 Notice of Issuance of License Amendment to Facility Operating License No. NPF-86 (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Approval ML18204A2422019-03-12012 March 2019 Federal Register Notice - License Amendment; Issuance (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Other NRC-2019-0075, Federal Register Notice - License Amendment; Issuance (CAC No. MF8260; EPID L-2016-LLA-0007)2019-03-12012 March 2019 Federal Register Notice - License Amendment; Issuance (CAC No. MF8260; EPID L-2016-LLA-0007) Project stage: Other ML20318A0032020-11-24024 November 2020 Issuance of Revised Page for Renewed Facility Operating License Atomic Safety and Licensing Board Decisions LBP-20-09 and LBP-20-12 Project stage: Approval 2018-04-18
[Table View] |
Text
November 24, 2020 Mr. Don Moul Executive Vice President, Nuclear Division, and Chief Nuclear Officer Florida Power & Light Company NextEra Energy Seabrook, LLC Mail Stop: EX/JB 700 University Blvd.
Juno Beach, FL 33408
SUBJECT:
SEABROOK STATION, UNIT NO. 1 - ISSUANCE OF REVISED PAGE FOR RENEWED FACILITY OPERATING LICENSE RE: ATOMIC SAFETY AND LICENSING BOARD DECISIONS LBP-20-09 AND LBP-20-12 (EPID L-2016-LLA-0007)
Dear Mr. Moul:
The U.S. Nuclear Regulatory Commission has issued the enclosed additional page for Renewed Facility Operating License (RFOL) No. NPF-86 for the Seabrook Station, Unit No. 1.
This page memorializes the amendment to RFOL No. NPF-86 by the Initial Decision (Ruling on the Reformulated Contention) of the Atomic Safety and Licensing Board, dated August 21, 2020 (LBP-20-09), as modified by the Memorandum and Order (Denying Motion to Reopen, Motion for Leave, and Motion for Partial Reconsideration; Granting in Part and Denying in Part Motion for Leave to Reply), dated November 6, 2020 (LBP-20-12), which was immediately effective pursuant to Title 10 of the Code of Federal Regulations 2.340(f).
Specifically, the additional page includes four additional conditions in RFOL No. NPF-86 for Appendix C that the Board found necessary for Amendment No. 159 to satisfy regulatory requirements.
If you have any questions, please contact me at (301) 415-2048 or at Justin.Poole@nrc.gov.
Sincerely,
/RA/
Justin C. Poole, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
Attachment with Additional License Page cc: Listserv
ML20318A003 OFFICE DORL/LPL1/PM DORL/LPL1/LA OGC - NLO DORL/LPL1/BC DORL/LPL1/PM NAME JPoole LRonewicz JWachutka JDanna (JTobin for)
JPoole DATE 11/13/2020 11/13/2020 11/24/2020 11/24/2020 11/24/2020
Enclosure ATTACHMENT TO LICENSE AMENDMENT NO. 159 SEABROOK STATION, UNIT NO. 1 RENEWED FACILITY OPERATING LICENSE NO. NPF-86 DOCKET NO. 50-443 Add the following page to Renewed Facility Operating License No. NPF-86. The attached page is identified by amendment number and contains a marginal line indicating the added text.
Remove Insert Appendix C, page 3
Amendment Number Additional Condition Implementation Date (continued)
(c) NextEra shall undertake the monitoring required by MPR-4273, Revision 1, Appendix B, Check 3, for control extensometers every six months.
(d) If stress analyses conducted pursuant to the Structural Evaluation Methodology show that the stress in the rebar from ASR-induced expansion and other loads will exceed the yield strength of the rebar, NextEra must develop a monitoring program sufficient to ensure that rebar failure or yielding does not occur, or is detected if it has already occurred, in the areas at-risk of rebar failure or yielding.
(e) If the ASR expansion rate in any area of a Seabrook seismic Category I structure significantly exceeds 0.2 mm/m (0.02%) through-thickness expansion per year, NextEras Management will perform an engineering evaluation focused on the continued suitability of the six-month monitoring interval for Tier 3 areas. If the engineering evaluation concludes that more frequent monitoring is necessary, it shall be implemented under the Structures Monitoring Program.
(f) Each core extracted from Seabrook Unit 1 will be subjected to a petrographic analysis to detect internal microcracking and delamination.
3 Amendment No. 119, 159