Request for 30 Day Extension on GL-2008-01 (Tac Nos. MD7793 and MD7794)
ML081130197
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 05/02/2008
From: Hiltz T G
NRC/NRR/ADRO/DORL/LPLIV
To:
Entergy Operations
Wang, A B, NRR/DORL/LPLIV, 415-1445
References
GL-08-001, TAC MD7793, TAC MD7794
Download: ML081130197 (4)


Text

May 2, 2008

Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc. 1448 S.R. 333 Russellville, AR 72802

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - GENERIC LETTER 2008-01, "MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS," RESPONSE TO EXTENSION REQUEST (TAC NOS. MD7793 AND MD7794)

Dear Sir or Madam:

Generic Letter (GL) 2008-01, "Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal, And Containment Spray Systems," requests licensees to submit information to demonstrate that the emergency core cooling, decay heat removal, and containment spray systems are in compliance with the applicable regulatory requirements, and that suitable design, operational, and testing control measures are in place for maintaining this compliance. The GL 2008-01 states that each licensee is requested to submit a written response within 9 months to provide requested information and that if a licensee cannot meet the requested 9-month response date, a 3-month written response is required that describes the alternative course of action that the licensee proposes to take, including the basis for the acceptability of the proposed alternative course of action.

On April 8, 2008, Arkansas Nuclear One (ANO) staff called Mr. Jared Wermiel of the U.S. Nuclear Regulatory Commission (NRC) to request an additional 30 days to complete the 3-month response for ANO. The basis for the ANO request is the need to perform additional action(s) that were unanticipated (i.e., completion of system walkdowns). Mr. Wermiel stated that the request was acceptable and agreed to the new proposed due date for the ANO 3-month response of May 11, 2008. Mr. Wermiel requested that ANO follow this verbal request with a letter formally requesting the extension. By letter dated April 10, 2008, the licensee formally requested an extension of 30 days for the 3-month response requested in GL 2008-01.

This letter is to formally acknowledge the approval of the requested extension to the due date for submitting the 3-month response to GL 2008-01 and to document the telephone call with the NRC staff. Specifically, Entergy Operations, Inc. requested an extension for providing the above 3-month response from April 11, 2008, to May 11, 2008, at ANO, Unit Nos. 1 and 2. The NRC staff finds the justification for ANO to extend the due date for the 3-month written response to GL 2008-01 to May 11, 2008 is acceptable, and the extension request is granted. This letter does not alter or change the required 9-month response date of October 11, 2008. The NRC staff will evaluate your alternate plans (3-month response) for responding to GL 2008-01 after receipt and will respond appropriately.

If you have any questions regarding this issue, please feel free to contact Alan B. Wang at (301) 415-1445.

Sincerely, /RA/

Thomas G. Hiltz, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368

cc: See next page

If you have any questions regarding this issue, please feel free to contact Alan B. Wang at (301) 415-1445.

Sincerely,

/RA/

Thomas G. Hiltz, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368

cc: See next page

DISTRIBUTION

PUBLIC LPLIV RF RidsAcrsAcnw&mMailCenter RidsNrrDorlLpl4 RidsNrrDprPgcb RidsNrrDss RidsNrrDssSrxb RidsNrrLAGLappert RidsNrrPMAWang RidsOgcRp RidsRgn4MailCenter DBeaulieu, NRR/DPR/PGCB WLyon, NRR/DSS/SRXB Accession No.: ML081130197 (*) See previous concurrence OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/DSS/DD DPR/PGCB/BC NRR/LPL4/BC NAME AWang (*) GLappert (*) JWermiel MMurphy THiltz DATE 4/23/08 4/23/08 5/1/08 5/2/08 5/2/08 OFFICIAL RECORD COPY Arkansas Nuclear One (2/25/08) cc: Senior Vice President Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Vice President, Oversight Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Senior Manager, Nuclear Safety & Licensing Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995

Senior Vice President & Chief Operating Officer Entergy Operations, Inc. P.O. Box 31995 Jackson, MS 39286-1995 Associate General Counsel Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Manager, Licensing Entergy Operations, Inc. Arkansas Nuclear One 1448 SR 333 Russellville, AR 72802 Section Chief, Division of Health Radiation Control Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Section Chief, Division of Health Emergency Management Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Pope County Judge Pope County Courthouse 100 W. Main Street Russellville, AR 72801 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064